St. Luke's Hospital v. Midwest Mechanical Contractors, Inc.

681 S.W.2d 482, 1984 Mo. App. LEXIS 4196
CourtMissouri Court of Appeals
DecidedNovember 20, 1984
DocketWD 34990
StatusPublished
Cited by9 cases

This text of 681 S.W.2d 482 (St. Luke's Hospital v. Midwest Mechanical Contractors, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
St. Luke's Hospital v. Midwest Mechanical Contractors, Inc., 681 S.W.2d 482, 1984 Mo. App. LEXIS 4196 (Mo. Ct. App. 1984).

Opinion

MANFORD, Judge.

This is an appeal from a circuit court judgment in the form of an order of a temporary stay of arbitration pursuant to § 435.355, RSMo 1978. The judgment is affirmed.

*484 While formally three points are presented, in reality they are but variations of a single alleged error, to wit, the trial court incorrectly interpreted a specific provision within a construction contract. The three variations are considered within the disposition of the appeal.

In summary, the applicable facts are as follows.

On December 7, 1982, respondent, St. Luke’s Hospital (hereinafter St. Luke’s), issued invitations to bid on a contract for the construction of a flue gas heat recovery system. The project was in part to be funded by the federal government. St. Luke’s had requested the right to negotiate the selection of the project contractor, but the Department of Energy, as the approving federal agency, required that St. Luke’s submit the mechanical work for competitive bidding. St. Luke’s extended the bid invitation to five Kansas City area mechanical contractors. Appellant, Midwest Mechanical Contractors, Inc. (hereinafter Midwest), was one of the bidding contractors.

Midwest submitted the lowest bid in the sum of $116,800.00. St. Luke’s awarded the contract to the second lowest bidder, with a bid of $119,000.00, the A.D. Jacobson Co., Inc. There was a “formal bid opening” at which time no formal rejection of the Midwest bid was entered.

The evidence reveals that the bidding contractors were required to complete their bid proposal form which contained information for the bidders relative to the project specifications. Included with the specifications was a two-page form captioned, “Bidder’s Statement of Qualifications.” Each bidder was required to submit proof of its experience, qualifications, financial responsibility, and ability to complete the project. The specifications, when read, establish that St. Luke’s was soliciting bids, and within sub-section 4(g), St. Luke’s, as owner, reserved the right to waive any infor-malities in the proposals and also to reject any and all of the proposals. It was established that the Vice-President of Midwest had read and was familiar with the foregoing reservations. In addition, within each proposals form was a “bidder’s acknowledgment” that the bidder understood St. Luke’s reserved the right to waive infor-malities and to reject any and all bids.

When read, the invitation does not state directly, nor is there any implication, that the lowest bidder was guaranteed the award of the contract. Section 8(b) of the invitation informed all bidders of the criteria that St. Luke’s, as owner, would consider in the awarding the contract. That section reads:

In awarding the contract, Owner [St. Luke’s] may take into consideration the ability to promptly handle the additional work, skill, facilities, capacity, experience, ability, responsibility, previous work and financial standing of bidder; quality, efficiency and construction of equipment proposed to be furnished; period of time within which equipment is proposed to be furnished and delivered; and necessity of prompt and efficient completion of work herein described. Inability of any bidder to meet the requirements mentioned above may be cause for rejection of his proposal.

St. Luke’s entered into a contract with the A.D. Jacobson Co., Inc. and at no time did St. Luke’s and Midwest enter into any agreement.

In addition to the above specific terms, the written specifications contained a part captioned, “General Conditions.” This part specified the mutual obligations as between the “owner” [St. Luke’s] and the “contractor” [i.e., the contractor selected by St. Luke’s]. The terms “owner” and “contractor” are defined within this part. St. Luke’s is defined as “owner”. “Contractor” is defined as, “[t]he person, firm or corporation with whom Owner has entered into an agreement.” In addition, the term “agreement” is defined as “[t]he written agreement between Owner and Contractor covering the work to be performed; other Contract Documents are attached to the agreement and made part thereof as provided therein.”

*485 In addition to the foregoing, there is found with the “General Conditions” Article 13, which reads as follows:

ARTICLE 13
Arbitration
All claims, disputes and other matters in question between OWNER and CONTRACTOR arising out of, or relating to the Contract Documents or the breach thereof, shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining subject to the limitations of this Article 13. This agreement so to arbitrate and any other agreement or consent to arbitrate entered into in accordance herewith as provided in this Article 13 will be specifically enforceable under the prevailing arbitration law of any court having jurisdiction.

Subsequent to the award of the contract to Jacobson, Midwest filed its demand for arbitration. This demand was premised upon Midwest’s alleged rights under the above Article 13. It was and continues to be the position of Midwest that St. Luke’s should have awarded the contract to Midwest since Midwest submitted the lowest bid. In response, St. Luke’s filed an “Application to Stay Threatened Arbitration Proceedings” in the circuit court within and pursuant to § 435.355, RSMo 1978. A hearing was conducted and both St. Luke’s and Midwest submitted evidence. The circuit court then entered its order staying the pending arbitration proceedings. 1 The circuit court, in entering its order, declared that upon the evidence submitted there was found no agreement to arbitrate between St. Luke’s and Midwest. This appeal followed the entry of the stay order.

As noted above, the main assertion of Midwest is that the circuit court erred in its interpretation of the above Article 13 of the “General Conditions” of the contract. Within this broad assertion, Midwest includes three specific contentions, which are summarized and disposed of as follows:

(1) The evidence revealed that St. Luke’s did not have a substantial and bona fide objection to the agreement to arbitrate in that Article 13 expressly provides that “all claims and disputes and other matters in question between owner and contractor arising out of or relating to the contract documents or the breach thereof shall be decided by arbitration;” the proposal forwarded to the bidders expressly stated on its face that this portion of the bidding documents was part of the contract documents and any bidding disputes that were covered by the contract documents in that they arose out of and related to the contract documents, and the court erred because even if there existed two alternative interpretations of Article 13, one permitting and another preventing arbitration, the trial court could not positively declare that the parties intended to exclude the dispute from arbitration since the trial court merely found that no agreement existed and in so finding the trial court “failed to consider the existence of a color-able dispute of an arbitriable nature which requires arbitration.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Creech v. MBNA America Bank, N.A.
250 S.W.3d 715 (Missouri Court of Appeals, 2008)
Estate of Burford ex rel. Bruse v. Edward D. Jones & Co.
83 S.W.3d 589 (Missouri Court of Appeals, 2002)
HitCom Corp. v. Flex Financial Corp.
4 S.W.3d 618 (Missouri Court of Appeals, 1999)
Local 781 International Ass'n of Firefighters v. City of Independence
996 S.W.2d 112 (Missouri Court of Appeals, 1999)
Silver Dollar City, Inc. v. Kitsmiller Construction Co.
874 S.W.2d 526 (Missouri Court of Appeals, 1994)
H.T.I. Corp. v. Lida Manufacturing Co.
785 S.W.2d 110 (Missouri Court of Appeals, 1990)
American Business Interiors, Inc. v. Haworth, Inc.
798 F.2d 1135 (Eighth Circuit, 1986)
Davis v. Human Development Corp.
705 S.W.2d 540 (Missouri Court of Appeals, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
681 S.W.2d 482, 1984 Mo. App. LEXIS 4196, Counsel Stack Legal Research, https://law.counselstack.com/opinion/st-lukes-hospital-v-midwest-mechanical-contractors-inc-moctapp-1984.