Fiordelisi v. Mt. Pleasant, LLC

254 S.W.3d 120, 2008 Mo. App. LEXIS 422, 2008 WL 820926
CourtMissouri Court of Appeals
DecidedMarch 25, 2008
DocketED 89627
StatusPublished
Cited by4 cases

This text of 254 S.W.3d 120 (Fiordelisi v. Mt. Pleasant, LLC) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fiordelisi v. Mt. Pleasant, LLC, 254 S.W.3d 120, 2008 Mo. App. LEXIS 422, 2008 WL 820926 (Mo. Ct. App. 2008).

Opinion

LAWRENCE E. MOONEY, Presiding Judge.

The plaintiff homeowner, Gina Fiordeli-si, appeals the judgment of the Circuit Court of St. Louis County confirming the arbitration award entered on her claims against the defendant contractor, Mt. Pleasant, LLC. The homeowner sued the contractor for breach of contract, negligence, intentional misrepresentation, and establishment of a constructive trust in connection with the parties’ contract for construction work to be performed by the contractor on the homeowner’s residence.

Because we conclude that the homeowner implicitly affirmed the contract and sought damages for the contractor’s non-compliant work, we hold that her misrepresentation claim was arbitrable pursuant to the parties’ arbitration agreement. Thus, the trial court did not err in confirming the arbitration award. We affirm the trial court’s judgment.

Facts

In July 2004, the contractor and the homeowner executed a contract for the contractor to perform certain remodeling work on the homeowner’s residence and to construct an addition to the house. The contract included a clause, which provided for arbitration of certain disputes.

Settlement of Disputes. In the event of any dispute arising hereunder as to whether the work complies with this Contract and the Drawings or whether payment is properly due and the same is not settled within ten (10) days, then either party may request that the dispute be submitted for decision to three arbitrators, one of whom shall be chosen by the [Home] Owners, and one by the Contractor. The said two arbitrators shall choose a third arbitrator and the parties shall proceed with arbitration in accordance with the rules and procedures of the American Arbitration Association and the provisions of the Missouri Uniform Arbitration Act.

Disputes arose between the parties, and the homeowner ultimately sued the contractor for breach of contract, negligence, intentional misrepresentation, and establishment of a constructive trust. The homeowner also sued the contractor’s owner, Bart Perry, for intentional misrepresentation, establishment of a constructive trust, and defamation. 1

On the misrepresentation claim, the petition alleged, inter alia, that the contractor and Perry made false statements to the homeowner that the company was bonded, licensed, and insured and that the homeowner reasonably relied on these statements in entering the contract with the contractor. The homeowner also alleged *124 that Perry falsely represented that the City of Glendale had inspected the building and framing on the home addition, causing the homeowner to make an advance payment not required by the contract. The homeowner’s petition sought actual and punitive damages on the misrepresentation count, including damages for emotional distress and mental anguish. The homeowner did not seek to rescind the contract.

The defendants sought to compel arbitration pursuant to the contract. The trial court ordered arbitration of all of the homeowner’s claims against the contractor, but not those against Perry individually because Perry was not a party to the contract. The arbitrator found that the homeowner had breached the contract with the contractor, but nonetheless awarded her “$19,287.59 for work billed and paid under the contract that was not performed in a good and workmanlike manner.” 2 The award did not mention the homeowner’s misrepresentation claim, and the arbitrator denied “[a]ny and all other claims not specifically mentioned in this Award.” The trial court confirmed the arbitration award and entered the award as a judgment as to all counts against the contractor. The homeowner now appeals.

Discussion

In her point relied on, the homeowner challenges both the order compelling her to arbitrate her intentional misrepresentation claim against the contractor and the judgment confirming the arbitration award. We note as a preliminary matter that an order compelling arbitration is not appealable, McCamey v. Nearing, Stoats, Prelogar and Jones, 866 S.W.2d 881, 887 (Mo.App. W.D.1993), although a court’s judgment confirming the arbitration award may be appealed, section 435.440.1(3) RSMo. (2000). 3 Therefore, we review the homeowner’s claim of error as one challenging confirmation of the arbitration award because the parties’ dispute was not arbitrable under their agreement.

In one point on appeal, the homeowner contends that her misrepresentation claim fell outside the scope of the parties’ arbitration agreement. She argues that the alleged misrepresentations were not “dis-putéis] arising [under the contract] as to whether the work complies with this Contract and the Drawings or whether payment is properly due,” and thus the disputes were not among those she had agreed to arbitrate. The homeowner asserts that the misrepresentation claim is independent of the contract’s terms and does not require reference to the contract for its resolution. To support her assertion, she maintains, first, that the false statements that the contractor was bonded, licensed, and insured pre-dated the contract and induced her to enter the contract and, second, that the false statements about the city inspection caused a delay in discovering the non-conforming work and induced her to make an advance payment not required under the contract.

The contractor counters that the heart of the homeowner’s misrepresentation claim concerned the contractor’s work and *125 the homeowner’s alleged payment of sums not due. The contractor points to the averments contained in the homeowner’s petition, arguing that they actually complain of work that failed to conform to the contract and drawings and payments that the homeowner made. The contractor contends that none of the allegations have any meaning without reference to the contract or drawings and therefore are intrinsically linked to the contract.

Standard of Review

“When faced with a motion to compel arbitration, the motion court must determine whether a valid arbitration agreement exists and, if so, whether the specific dispute falls within the scope of the arbitration agreement.” Nitro Distributing, Inc. v. Dunn, 194 S.W.3d 339, 345 (Mo. banc 2006). Missouri contract law applies to determine whether the parties entered a valid agreement to arbitrate disputes. State ex ret. Vincent v. Schneider, 194 S.W.3d 853, 856 (Mo. banc 2006). Whether a dispute is arbitrable is a question of law, which we review de novo. Id.; Tallmadge ex rel. Tallmadge v. Beverly Enterprises-Missouri, Inc., 202 S.W.3d 47, 49 (Mo-App. E.D.2006).

Choice of Law

We must first determine whether the Federal Arbitration Act (FAA), 9 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Riley v. Lucas Lofts Investors, LLC
412 S.W.3d 285 (Missouri Court of Appeals, 2013)
Saddleridge Estates, Inc. v. Ruiz
323 S.W.3d 427 (Missouri Court of Appeals, 2010)
Woods v. QC Financial Services, Inc.
280 S.W.3d 90 (Missouri Court of Appeals, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
254 S.W.3d 120, 2008 Mo. App. LEXIS 422, 2008 WL 820926, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fiordelisi-v-mt-pleasant-llc-moctapp-2008.