Fru-Con Construction Co. v. Southwestern Redevelopment Corp. II

908 S.W.2d 741, 1995 Mo. App. LEXIS 1443, 1995 WL 479578
CourtMissouri Court of Appeals
DecidedAugust 15, 1995
Docket67724
StatusPublished
Cited by9 cases

This text of 908 S.W.2d 741 (Fru-Con Construction Co. v. Southwestern Redevelopment Corp. II) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fru-Con Construction Co. v. Southwestern Redevelopment Corp. II, 908 S.W.2d 741, 1995 Mo. App. LEXIS 1443, 1995 WL 479578 (Mo. Ct. App. 1995).

Opinion

SMITH, Presiding Judge.

Defendant, Southwestern Redevelopment Corporation II, appeals from the denial by the trial court of its motion for stay of proceedings pending arbitration. The court denied the motion on the basis that the “claim” asserted by the plaintiff, Fru-Con Construction Co., against the defendant was not arbi-trable under the contract of the parties. Finding that determination to be erroneous as to all but one portion of the cause of action we reverse.

Fru-Con as Contractor and Southwestern as Owner entered into a contract for the construction of the Southwestern Bell Data Center in the City of St. Louis. The total contract exceeded one hundred million dollars. The parties utilized a standard form contract supplied by the American Institute of Architects with amendments in some areas. Several provisions of that contract are pertinent to the issue on appeal.

§ 2.2.7 The Architect will be the interpreter of the requirements of the Contract Documents and the judge of the performance thereunder by both the Owner and Contractor.
§ 2.2.9 Claims, disputes and other matters in question between the Contractor and the Owner relating to the execution or progress of the Work or the interpretation of the Contract Documents shall be referred initially to the Architect for decision which he will render in writing within a reasonable time.
2.2.12 Any claim, dispute or other matter in question between the Contractor and the Owner referred to the Architect ... shall be subject to- arbitration under Para *743 graph 7.9 upon the written demand of either party. However, no demand for arbitration of any such claim, dispute or other matter may be made until the earlier of (1) the date on which the Architect has rendered a written decision, or (2) the tenth day after the parties have presented their evidence to the Architect or have been given a reasonable opportunity to do so, if the Architect has not rendered his written decision by that date ...
7.9.1 All claims, disputes and other matters in question between the Contractor and the Owner arising out of, or relating to, the Contract Documents or the breach thereof ... shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining unless the parties mutually agree otherwise ... 7.9.3 Unless otherwise agreed in writing, the Contractor shall carry on the Work and maintain its progress during any arbitration proceedings, and the Owner shall continue to make payments to the Contractor in accordance with the Contract Documents.

By amendment the parties added to the first line of § 7.9 the following:

“, if the total amount of damages arising from the claim or dispute, as estimated by the Architect, are less than $200,000. Any claim, dispute or other matter in question for which the amount of damages is estimated by the Architect to be greater than $200,000, is not subject to arbitration unless the parties mutually agree otherwise.”

During the construction process, Contractor submitted Contractor Change Proposals (CCPs) to the architect. In October 1991 the contractor submitted CCP 297 to the architect. In that CCP Contractor stated that he relied on Owner’s pre-bid representations for cooperation in a team concept and agreed to a “very aggressive” work schedule in reliance on those representations. Contractor alleged those representations were not true and then listed several situations of delay, misleading plans, and lack of cooperation commencing early in the project and continuing throughout the project. A not complete list of the situations covered included excavation problems, dewatering problems, delays because of the condition of a building across the street not owned by Owner, difficulties with the Metrolink tunnel which went under the real estate, structural concrete formwork problems, and additional subcontracting costs. CCP 297 set an amount of $20,000,000 as the additional amount it was owed by the Owner for the construction of the Data Center from the combination of items contained in the CCP.

In August 1992 the Contractor filed suit claiming breach of contract, quantum meruit, and misrepresentation. Contractor made no request of the architect to evaluate CCP 297, which formed the basis for the lawsuit. In 1994, at the request of Owner, the architect submitted his evaluation of CCP 297 and found that it was comprised of multiple events giving rise to a series of different claims, only one of which exceeded $200,000 and therefore outside the arbitration requirement. In December 1994, Owner served on Contractor its demand for arbitration and filed its motion to stay proceedings. Following hearing the court denied the motion by written order on January 20, 1995. In its order the court found that the “total” amount of Contractor’s “claim” exceeded $200,000 as the term “claim” is used in the contract and that the meaning of “claim” was not ambiguous. In defining what “claim” meant the court relied upon Committee for Educational Equality v. State, 878 S.W.2d 446 (Mo. banc 1994) [7, 8] wherein the court stated that “[Cjlaims are considered separate if they require proof of different facts and the application of distinguishable law, subject to the limitation that severing the claims does not run afoul of the doctrine forbidding the splitting of a cause of action.” The court also expressed its concern that holding arbitration is required for all but one item comprising CCP 297 would involve splitting up of a cause of action, and would result in certain items being subject to arbitration while another part of the cause of action is litigated.

The parties agree that the Federal Arbitration Act applies. 9 U.S.C.A. Secs. 1-16. It carries with it a body of federal law governing arbitration and arbitrability. This court’s review of the arbitrability of the con *744 troversy is de novo. 1 McMahan Securities Co. L.P. v. Forum Capital Markets L.P., 35 F.3d 82 (2nd Cir.1994) [2], A court must stay litigation if it determines that the parties agreed to arbitrate. Houlihan v. Offerman & Company, Incorporated, 31 F.3d 692 (8th Cir.1994) [2]. The court evaluates: (1) whether the parties agreed to arbitrate; (2) the scope of the agreement; (3) if federal statutory claims are asserted, whether Congress intended those claims to be arbitrable; and (4) if the court concludes that some but not all claims are arbitrable, whether to stay the balance of the proceeding pending arbitration. Genesco, Inc. v. T. Kakiuchi and Co., Ltd., 815 F.2d 840 (2nd Cir.1987) [1].

The United States Supreme Court in recent years has consistently taken a strong position in support of arbitration. In Moses H. Cone Memorial Hospital v. Mercury Construction Corporation, 460 U.S. 1, 103 S.Ct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shelter Products, Inc. v. Omni Construction Company, Inc.
479 S.W.3d 189 (Missouri Court of Appeals, 2016)
Schwarz v. Gierke
2010 ND 166 (North Dakota Supreme Court, 2010)
Nitro Distributing, Inc. v. Dunn
194 S.W.3d 339 (Supreme Court of Missouri, 2006)
Netco, Inc. v. Dunn
194 S.W.3d 353 (Supreme Court of Missouri, 2006)
Dunn Industrial Group, Inc. v. City of Sugar Creek
112 S.W.3d 421 (Supreme Court of Missouri, 2003)
Estate of Athon v. Conseco Finance Servicing Corp.
88 S.W.3d 26 (Missouri Court of Appeals, 2002)
McIntosh v. Tenet Health Systems Hospitals, Inc.
48 S.W.3d 85 (Missouri Court of Appeals, 2001)
Metro Demolition & Excavating Co. v. H.B.D. Contracting, Inc.
37 S.W.3d 843 (Missouri Court of Appeals, 2001)
Reis v. Peabody Coal Co.
935 S.W.2d 625 (Missouri Court of Appeals, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
908 S.W.2d 741, 1995 Mo. App. LEXIS 1443, 1995 WL 479578, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fru-con-construction-co-v-southwestern-redevelopment-corp-ii-moctapp-1995.