Dynasteel Corporation v. Black & Veatch Corporation

698 F. Supp. 2d 1170, 2010 U.S. Dist. LEXIS 22513, 2010 WL 924381
CourtDistrict Court, W.D. Missouri
DecidedMarch 11, 2010
DocketCase 08-0602-CV-W-ODS
StatusPublished
Cited by1 cases

This text of 698 F. Supp. 2d 1170 (Dynasteel Corporation v. Black & Veatch Corporation) is published on Counsel Stack Legal Research, covering District Court, W.D. Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dynasteel Corporation v. Black & Veatch Corporation, 698 F. Supp. 2d 1170, 2010 U.S. Dist. LEXIS 22513, 2010 WL 924381 (W.D. Mo. 2010).

Opinion

ORDER AND OPINION (1) DENYING DYNASTEEL’S MOTION FOR . SUMMARY JUDGMENT, AND (2) GRANTING BLACK & VEATCH PARTIAL SUMMARY JUDGMENT

ORTRIE D. SMITH, District Judge.

Pending is a motion for summary judgment filed by DynaSteel Corporation (DynaSteel) (Doc 109). , The motion is denied. In its suggestions in opposition to DynaSteel’s motion, Black and Veatch Corporation (B & V) requests partial summary judgment on an issue of liability. This request is granted.

*1173 I. BACKGROUND

On February 14, 2006, DynaSteel, a corporation -with its principal place of business in Memphis, Tennessee, contracted to supply labor, services, and materials, including ductwork and limestone silos, to B & V, a company located in Kansas City, Missouri, for the “Cardinal Units 1 & 2 FGD Retrofit Project” in Brilliant, Ohio. American Electric Power Service Corporation (AEPSC) was the owner on the project. Through subsequent revisions, the purchase price of the B & V/DynaSteel contract totaled $11,721,714.95.

An issue with DynaSteel’s performance arose after the initial duct sections were scheduled to be delivered. On August 22, 2006, B & V notified DynaSteel that it would be assessing charges against DynaSteel’s account (“backcharges”) for failing to install safety cables on several duct pieces. That same day, B & V authorized one of its subcontractors, Aker Kvaerner Songer, Inc. (AKSI) to install the missing safety cables. On August 23, 2006, B & V sent DynaSteel a “Backcharge Notification” estimating the cost of the backcharge to be $4,125.00.

Tension between the parties surfaced as DynaSteel’s performance continued. In September 2006, B & V backcharged DynaSteel for the alleged failure to provide base plates for several duct pieces. At a meeting held later that month, DynaSteel reportedly denied fabricating duct pieces with field splice joint gaps B & V claimed were too large. Despite DynaSteel’s denial of liability, B & V backcharged $16,875.00 for this alleged defect. In October 2006, B & V reportedly “threat[ened]” to impose liquidated damages against DynaSteel, apparently due to delayed duct-work shipments. According to B & V, it ultimately decided against the liquidated damages because DynaSteel threatened to stop fabrication ■ altogether if they were imposed.

DynaSteel delivered all the ductwork to the project site by March 19, 2007. In a letter dated June 7, 2007, B & V advised DynaSteel that it had “completed partial installation and inspection” of DynaSteel’s work and had discovered defects and/or nonconformities. Included with the letter was a “Backcharge Log” listing twenty-four backcharges estimated to cost DynaSteel $789,573.46. B & V’s correspondence also included an “Other Defects Log,” identifying various other alleged defects or nonconformities with a total estimated repair cost of over $1,000,000.00. In a brief response dated June 13, 2007, DynaSteel wrote, “Concerning your letter dated June 7, 2007, DynaSteel Corporation disagrees with its content and therefore rejects it in it’s [sic] entirety. Please release for payment all monies due under the contract.” Thereafter, B & V continued to assess additional backcharges against DynaSteel and refused to pay DynaSteel the full purchase price.

DynaSteel filed this action in federal court against B & V, asserting claims for breach of contract, quantum meruit, and declaratory relief, and seeking to recover attorney fees and a prompt payment penalty under Mo.Rev.Stat. § 431.180. According to DynaSteel, “at least $1,429,680.73” of the purchase price remains due and owing from B & V. B & V counterclaimed, asserting causes of action for breach of contract and breach of warranty. According to B & V, it owes B & V nothing; rather, B & V claims DynaSteel owes it. $3,433.79.00 for corrections or repairs B & V’s subcontractors were required to perform on DynaSteel’s allegedly defective and nonconforming work. DynaSteel maintains B & V is completely barred from any recovery.

II. DISCUSSION

Summary judgment is appropriate when the record, viewed in the light most favor *1174 able' to the non-moving party, demonstrates that there is no genuine issue of material fact and the moving party is entitled to judgment as a matter of law. Reynolds v. RehabCare Group East, Inc., 591 F.3d 1030, 1032 (8th Cir.2010). DynaSteel’s arguments in its motion for summary judgment can be grouped into six categories, which the Court will address in turn: (1) Notice; (2) Liquidated Damages; (3) Inspection Costs; (4) Design Change Notifications; (5) Approval of Drawings; and (6) Insulation Saturation.

1. Notice

DynaSteel claims that B & V cannot hold it liable for the work performed in correcting the alleged defects and nonconformities because B & V failed to provide it notice and an opportunity to cure prior to performing the corrective work and backcharging DynaSteel for the incurred costs. According to DynaSteel, B & V failed to provide it the notice- required by the Missouri Uniform Commercial Code— Sales (U.C.C.). In addition, DynaSteel claims that, under the contract, notice and an opportunity to cure were conditions precedent to DynaSteel’s liability for B & V’s corrective costs and backcharges. DynaSteel’s arguments do not entitle it to summary judgment.

(a) U.C.C. Notice

DynaSteel contends that the U.C.C. notice requirement found at Mo. Rev. Stat § 400.2-607(3)(a) bars B & V’s recovery. This argument was raised for the first time in DynaSteel’s reply brief. The Court declines to consider an argument raised for the first time to which B & V does not have an opportunity to respond. See U.S. v. Barraza, 576 F.3d 798, 806 n. 2 (8th Cir.2009) (citation omitted) (“Arguments raised for the first time in a Reply Brief need not be addressed.”). Justice requires that B & V be allowed to argue against the application of the U.C.C. and its remedy-limiting provisions. DynaSteel is not entitled to summary judgment on this issue.

Even if the Court assumed, without deciding, that Mo.Rev.Stat. § 400.2-607(3) applied, DynaSteel still would not be entitled to summary judgment. In relevant part, Mo.Rev.Stat. § 400.2-607(3) states:

(3) Where a tender has been accepted (a) the buyer must within a reasonable time after he discovers or should have discovered any breach notify the seller of breach or be barred from any remedy.

The sufficiency of notice and what is a reasonable time within which to give notice of defective goods are ordinarily questions of fact for the jury. See Rowe Intern., Inc. v. J-B Enterprises, Inc., 647 F.2d 830, 833 (8th Cir.1981). Here, DynaSteel relies on evidence that merely suggests

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
698 F. Supp. 2d 1170, 2010 U.S. Dist. LEXIS 22513, 2010 WL 924381, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dynasteel-corporation-v-black-veatch-corporation-mowd-2010.