Ahrens & McCarron, Inc. v. Mullenix Corp.

793 S.W.2d 534, 1990 Mo. App. LEXIS 974, 1990 WL 89525
CourtMissouri Court of Appeals
DecidedJune 26, 1990
Docket56984
StatusPublished
Cited by9 cases

This text of 793 S.W.2d 534 (Ahrens & McCarron, Inc. v. Mullenix Corp.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ahrens & McCarron, Inc. v. Mullenix Corp., 793 S.W.2d 534, 1990 Mo. App. LEXIS 974, 1990 WL 89525 (Mo. Ct. App. 1990).

Opinion

JOSEPH J. SIMEONE, Senior Judge.

I

These proceedings are appeals by defendants-appellants, Mullenix Corporation and Ivan L. Mullenix from a final judgment entered upon a jury verdict on July 31, 1989 by the circuit court of St. Louis County which judgment (1) awarded plaintiff-respondent, Ahrens & McCarron, Inc., a net amount of $126,490.19 including interest and attorney’s fees for goods sold and delivered and (2) imposed a mechanic’s lien in the total sum of $7,405,79 — $5,631.78 principal and $1,774.01 interest — upon property known as Bogey Hills owned by appellant, Ivan Mullenix. We affirm.

II

Appellant Ivan Mullenix is a real estate developer whose business, Mullenix Corporation, acts as general contractor for certain projects. In the mid-1980’s, appellants were engaged in building two projects: Bogey Hills Apartments, located in St. Charles County and Summerwood Condominiums located in St. Louis County. Bogey Hills was intended to be built for sole ownership by Ivan Mullenix and Summer-wood was built to be sold to individual owners. Respondent, Ahrens & McCarron, Inc. supplied various building materials and fixtures for the two developments from approximately July 1984 to September 1986.

In particular, respondent provided plastic laminate to be used as a backsplash in the kitchens at Bogey Hills. This material was used to cover an entire wall in each kitchen. Originally, Mullenix Corporation purchased standard grade plastic laminate in eight foot sheets from another supplier, but that supplier became unreliable. Ah-rens & McCarron negotiated to supply vertical grade plastic laminate which was available in ten foot sections, a more desirable length. The vertical grade laminate was made identically to the standard grade laminate but was not as thick and therefore not as strong.

After the vertical grade laminate had been installed in a number of units, cracks began to appear. Respondent contacted the wholesaler of the laminate, Dexter Zar-ing, who examined the Bogey Hills project and determined that the cracks were caused by improper installation methods. Particularly, the laminate was installed directly onto gypsum board and not on a wood-based product and the laminate was not properly cut. Zaring sent a letter to Mullenix Corporation detailing the proper installation methods.

Appellants decided to discontinue use of the vertical grade laminate. Repairs were made on the 36 units which had already cracked at a total cost of $6,800. Vertical grade plastic laminate had been installed in 144 other units which had not cracked. Because of the possibility that these latter units might develop cracks, appellants decided to withhold payments on their balance due respondent for both the Bogey Hills and Summerwood projects. Appellants sought to hold these funds as a reserve to pay for any future repairs.

Respondent filed mechanic’s liens against forty individual condominium units at Sum-merwood and against Bogey Hills on March 13, 1986. Later, it filed a petition in St. Louis County seeking to enforce the forty Summerwood mechanic's liens and to recover against Mullenix Corporation on open account, unpaid invoices not attributable to a mechanic’s lien. Respondent also filed a petition in St. Charles County seeking enforcement of the Bogey Hills mechanic’s lien. These two actions were consolidated for trial in St. Louis County.

The Summerwood petition contained a billing statement dated July 31, 1986, which stated the outstanding balance at $81,-666.06 including late charges of $7,675.77. *537 These charges were computed at a rate of 1% per month pursuant to the credit agreement between Mullenix Corporation and respondent. The petition used this statement to support the $35,536.96 claim on open account. The forty mechanic’s liens counts stated the amounts due which were drawn from the mechanic’s liens themselves. The petition also stated that, as a personal judgment, Mullenix Corporation was indebted to respondent in the sum of $81,-666.06, plus interest and attorney’s fees. The Bogey Hills petition prayed for a judgment of $5,631.78 plus interest and attorney fees against Mullenix Corporation and a mechanic’s lien for that amount against Bogey Hills. This amount was supported by four attached invoices.

Appellant Mullenix Corporation filed a counterclaim alleging breach of warranty and sought $98,500.00 in damages.

At trial, respondent’s credit manager, Brenda Rathert, testified that she had prepared a four-page summary of the amounts due on each of the 42 counts which was introduced and denominated as exhibit 12. Appellants objected to the introduction of exhibit 12. For each count, she stated a principal amount, an interest amount of 12% and an attorney’s fee amount of 15%. Each mechanic’s lien claim also contained a separate column stating the same principal amount with an interest amount at 9% and no attorney’s fees. The amounts reflected those in the petition and were based on the amounts stated in the mechanic’s liens themselves. The open account amount represented the outstanding balance due which was not attributable to a mechanic’s lien. This total of $35,536.95 was drawn from invoices and a billing statement dated May 31, 1989, all of which were included in exhibit 13. Appellants objected to the introduction of exhibit 12 on the ground that no foundation was laid.

Exhibit 11, which was submitted at the same time as exhibit 12, was a billing statement dated February 28, 1986 showing the total balance due of $82,287.66 including $3,758.63 in late charges.

At the conclusion of Ms. Rathert’s testimony concerning the summary of the accounts, plaintiff’s counsel read into evidence certain interrogatories answered by Mullenix. On Bogey Hills, Mullenix admitted owing $5,419, and calculated the unpaid balance due on Summerwood to be $72,-183.08.

The attorney for Ahrens & McCarron took the stand and testified that he was an attorney and worked on these lawsuits. He testified that the claim began in February, 1986. His time records show that prior to trial he devoted 165 hours to the preparation and prosecution of the lawsuit and his billing rate is $95.00 per hour for a total of $15,684.50 up to the point of trial. His time records were introduced as evidence. No objection was made.

Mullenix’s evidence, on its counterclaim, showed that the materials installed in the kitchens were vertical grade plastic laminate. After installing about 180 kitchens at Bogey Hills, cracks started appearing running “all the way across the wall.” Corrections were made and standard grade laminate was used to correct the defects at a cost of $6,856.56 at Bogey Hills. Mr. Mullenix testified that payments were not made to Ahrens & McCarron because it “refused to correct our plastic laminate problems” at Bogey Hills, and he held the bills he owed at Summerwood as a “reserve against our problem at Bogey Hills.”

At the conclusion of the trial, an instruction conference was had. Several objections to instructions were made by Mulle-nix at the conference.

The court instructed the jury. Among other instructions, the court gave instructions 7, 8, 11, and 12. Instruction No. 7, the verdict director on the mechanic’s lien, informed the jury that its verdict must be for Ahrens & McCarron if it believed:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smith v. American Family Mutual Insurance Co.
289 S.W.3d 675 (Missouri Court of Appeals, 2009)
Hadley v. Burton
265 S.W.3d 361 (Missouri Court of Appeals, 2008)
Syn, Inc. v. Beebe
200 S.W.3d 122 (Missouri Court of Appeals, 2006)
Huffy Corp. v. CUSTOM WAREHOUSE, INC.
169 S.W.3d 89 (Missouri Court of Appeals, 2005)
Babb v. Pfuehler
944 S.W.2d 331 (Missouri Court of Appeals, 1997)
Sigrist by and Through Sigrist v. Clarke
935 S.W.2d 350 (Missouri Court of Appeals, 1996)
AGRIBANK FCB v. Cross Timbers Ranch, Inc.
919 S.W.2d 256 (Missouri Court of Appeals, 1996)
Refrigeration Industries, Inc. v. Nemmers
880 S.W.2d 912 (Missouri Court of Appeals, 1994)
Helmtec Industries, Inc. v. Motorcycle Stuff, Inc.
857 S.W.2d 334 (Missouri Court of Appeals, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
793 S.W.2d 534, 1990 Mo. App. LEXIS 974, 1990 WL 89525, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ahrens-mccarron-inc-v-mullenix-corp-moctapp-1990.