State Ex Rel. Stites v. Goodman

351 S.W.2d 763, 1961 Mo. LEXIS 521
CourtSupreme Court of Missouri
DecidedNovember 13, 1961
Docket48846
StatusPublished
Cited by14 cases

This text of 351 S.W.2d 763 (State Ex Rel. Stites v. Goodman) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Ex Rel. Stites v. Goodman, 351 S.W.2d 763, 1961 Mo. LEXIS 521 (Mo. 1961).

Opinion

STORCKMAN, Judge.

This is an original proceeding in mandamus to compel the Circuit Judge of Dunklin County to render judgment in accordance with the mandate of this court in Bloomfield Reorganized School District No. R-14, Stoddard County, Missouri v. Stites, Mo., 336 S.W.2d 95. The defendant in that case, F.. M. Stites,, undertook to erect a combination gymnasium and music building for the plaintiff school district under a written contract. The relator here is the defendant E. M. Stites. The parties will be generally referred to as they were denominated in the reported case. Controversies having arisen, the plaintiff school district filed suit for possession of the building claiming that the defendant Stites had violated the construction contract. On March 9, 1959, the trial court rendered judgment for plaintiff for possession, for liquidated damages against the defendant in the sum of $7,000 and for a credit of $4,344 in favor of the plaintiff for ■ Y'placement of. the roof in accordance with the stipulation of the parties. The trial court held that the defendant was entitled to recover 95 per cent of the contract price of $276,247 and $1,798.68 for extra work done. Giving effect to the debits and credits and the amounts paid by plaintiff on account of the contract price, the trial court rendered a net judgment in favor of defendant for $774.68. From this judgment the defendant appealed to the Supreme Court.

On May 9, 1960, the Supreme Court rendered its judgment reversing the judgment and remanding the cause with directions to enter judgment in accordance with the opinion of the court. The opinion' decided that the plaintiff was entitled to retain $7,-000 as liquidated damages a!nd $4,344 for the roof and that the defendant was entitled to $1,798.68 for extra work, all as found by the trial court. The Supreme Court found, however, that the architect had certified that the building was substantially complete, that the plaintiff had thereafter taken the building over and was using it, and that the defendant was entitled to the full contract price plus the amount due for extra work less the amounts paid on account, the other items of credit, and the sum expended by the plaintiff to complete the building. The motion for rehearing or to transfer to the court en banc was overruled June 13, 1960, and the mandate was issued accordingly.

Thereafter, the defendant filed in the Circuit Court of Dunklin County his motion for judgment pursuant to the mandate which motion is as follows: “Comes now defendant and states that under the mandate from the Supreme Court of Missouri this cause was remanded for entry of a judgment in conformity with the opinion, and he states that under the mandate of the Supreme Court he is entitled to collect the contract price, to-wit: $276,247.00 plus $1,-798.68 for extra work, less payments previously made, to-wit: $252,114.65, and also less liquidated damages in the amount of $7,000.00, the amount paid by stipulation for replacement of a portion of the roof, to-wit: $4334.00, and ‘less whatever sum *765 has, in fact, been expended to finally complete the building.’ Defendant states that the facts are that no sums have been expended by plaintiff to complete the building, and that under the court’s opinion and mandate, he is entitled to collect the sum of $14,586.99, together with interest thereon at 6% per annum from the time when the school board terminated the contract, to-wit: June 25, 1957.

“Wherefore, defendant prays the court to enter judgment herein in his favor and against the plaintiff for the sum of $14,586.-99, plus interest at 6% per annum from June 25, 1957, together with the sum of $129.10 costs in connection with the appeal which the Supreme Court on July 11, 1960, taxed against plaintiff and in favor of the defendant.”

The relator Stites asserts, and there is no denial, that the school district in response to his motion for judgment admitted that it had expended nothing toward completion of the building, but asserted that it intended to do so in the future and requested that judgment be stayed until it did so. On March 27, 1961, the respondent overruled the defendant’s motion for judgment. Thereafter, Mr. Stites filed his petition in this court for a writ of mandamus which was sustained, and our alternative writ was issued requiring the respondent “to conduct a hearing to determine and adjudicate what sums, if any, the Bloomfield Reorganized School District No. R-14 had in fact expended as of May 9, 1960, (the date of this court’s opinion), to correct defective work and to complete the gymnasium and music building in accordance with the plans and specifications, and further that you render judgment in accordance with the mandate and opinion of this court in Case No. 47,-666,” or to show cause. The respondent has filed his return to the writ and the relator has answered the return.

The plaintiff contends that the opinion holds that it is entitled to a “completed building” and apparently assumes that it had an unlimited time to complete the building and claim its credits. Plaintiff’s petition,, filed July 24, 1957, alleged that it had elected to terminate the contract on July 1, 1957, because of defendant’s breaches of contract and that it was “entitled to possession of the same for the purpose of completing the construction of said building.” On August 5, 1957, plaintiff filed its ancillary petition for a temporary injunction in which it alleged that the defendant was interfering with the “plaintiff’s election and right to complete the construction” of the building and prayed that the defendant be enjoined so that the building could be used for the beginning of the 1957 school year. On August 5, 1957, a temporary restraining order against the defendant was issued. On November 22, 1957, the parties filed a stipulation wherein it was agreed that the plaintiff might enter and commence the use of the building and also stipulated for replacement of the roof at a cost of $4,344 to be charged against the defendant. Trial of the case was commenced in July 1958 and judgment was rendered March 9, 1959. At the beginning of the trial, the plaintiff voluntarily dismissed Paragraph III of its pleadings (in the nature of a counterclaim) wherein it sought $25,000 damages because of defendant’s failure “to do the construction work on said building in accordance with the plans and specifications”, and because the “defendant did faulty work thereon”. Nine items of alleged failures and faulty work were listed.

At the trial the evidence showed that on September 6, 1957, plaintiff’s architect, the defendant, and the attorneys for the parties went through the building together and that the architect “made up a list of what remained to be done.” This was referred to as the “punch list” and was introduced in evidence as plaintiff’s Exhibit Y. No evidence was offered, however, as to the cost of completing the items on the punch *766 list. As to these items the opinion states, 336 S.W.2d loe. cit. 101: “As of September 21, 1957, the architect compiled a list of items (a punch list) necessary to finally complete the building in accordance with the plans and specifications.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SOMERSETT OWNERS ASS'N VS. SOMERSETT DEV. CO., LTD.
2021 NV 35 (Nevada Supreme Court, 2021)
Carver v. Delta Innovative Services
419 S.W.3d 792 (Missouri Court of Appeals, 2013)
Frost v. Liberty Mutual Insurance Co.
813 S.W.2d 302 (Supreme Court of Missouri, 1991)
Quality Wig Co., Inc. v. JC Nichols Co.
728 S.W.2d 611 (Missouri Court of Appeals, 1987)
Killian Construction Co. v. Tri-City Construction Co.
693 S.W.2d 819 (Missouri Court of Appeals, 1985)
Smith v. American Bank & Trust Co.
639 S.W.2d 169 (Missouri Court of Appeals, 1982)
John Henry Jones, Inc. v. Lanier
376 So. 2d 450 (District Court of Appeal of Florida, 1979)
S. G. Adams Printing & Stationery Co. v. Central Hardware Co.
572 S.W.2d 625 (Missouri Court of Appeals, 1978)
Forsythe v. Starnes
554 S.W.2d 100 (Missouri Court of Appeals, 1977)
Markham v. Kauffman
284 So. 2d 416 (District Court of Appeal of Florida, 1973)
Metropolitan Dade County v. Colsky
241 So. 2d 440 (District Court of Appeal of Florida, 1970)
Sherwood Park, Ltd., Inc. v. Meeks
234 So. 2d 702 (District Court of Appeal of Florida, 1970)
Southwest Engineering Co. v. Reorganized School District R-9
434 S.W.2d 743 (Missouri Court of Appeals, 1968)
Julian v. Kiefer
382 S.W.2d 723 (Missouri Court of Appeals, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
351 S.W.2d 763, 1961 Mo. LEXIS 521, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-stites-v-goodman-mo-1961.