Julian v. Kiefer

382 S.W.2d 723, 1964 Mo. App. LEXIS 569
CourtMissouri Court of Appeals
DecidedOctober 5, 1964
Docket24047
StatusPublished
Cited by27 cases

This text of 382 S.W.2d 723 (Julian v. Kiefer) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Julian v. Kiefer, 382 S.W.2d 723, 1964 Mo. App. LEXIS 569 (Mo. Ct. App. 1964).

Opinion

CROSS, Judge.

Plaintiff Alfred A. Julian, a building contractor, entered into a written contract with defendant property owners to build a dwelling house for the total price of $27,200.00. He duly entered upon the agreed undertaking and completed the structure substantially in accordance with the contract plans .and specifications. During progress of the work defendants made monthly payments, upon the builder’s request and presentation of bills for labor and materials, total-ling $25,000.00. After the house was completed the contracting parties were unable to agree as to the balance owed by defendants. Thereafter this action was filed by plaintiffs Alfred A. Julian and Berniece Julian, who are husband and wife, and who claim to be building contractors in partnership.

Plaintiffs’ petition does not plead for a recovery under the contract, but sounds in ■quantum meruit. Its allegations are to the effect that the parties entered into a written contract, as above noted; that after plaintiffs had partially completed the work ■called for, defendants abandoned the contract, took charge of the project, ordered rthe materials, changed the plans, instructed the workers and did not permit plaintiffs to continue construction of the house under the terms of the contract; and, that plaintiffs had furnished materials and performed work and labor to the benefit of defendants in the sum and value of $35,767.03. Allowing defendants credit for $25,000.00 paid during the course of the work, plaintiffs pray judgment for the claimed balance of $10,767.03 and for a statutory lien on defendants’ real estate.

Defendants filed an answer and a counterclaim. In their answer, defendants denied they had abandoned the contract and affirmatively charged that any recovery by plaintiffs in excess of $25,000.00 must be computed in accordance with the contract. The counterclaim charges that plaintiffs failed to construct the house in a workmanlike manner and of good quality materials in accordance with the terms of the contract; that as a consequence the structure is defective; and, further, that plaintiffs omitted items of construction called for by the contract, and have failed and refused to remedy such defects and omissions — all to defendants’ damage in the sum of $7,-500.00, for which they pray judgment. The allegations of defendants’ counterclaim are denied by plaintiffs.

By stipulation of the parties the case was tried to the court. After hearing extensive evidence the trial judge concluded that “the ignoring of the terms of the contract by the parties, both plaintiffs and defendants, who did not protest or require compliance with the terms of the contract, constituted an abandonment of the contract”, and that plaintiffs were entitled to recover under their petition.

Judgment was entered in favor of plaintiffs on their petition demand, in the sum of $7,109.70, and a statutory lien for like amount was decreed as against defendants’ property. Additionally the trial court rendered judgment against defendants on their counterclaim and dismissed the pleading. Defendants appeal

*726 It is here contended by defendants that the trial court erred in finding as a fact and as a conclusion of law that the contract had been abandoned because (1) the final construction was substantially in accordance with the contract, (2) the parties at all times treated the contract as being in force, and (3) the evidence was insufficient to establish plaintiffs were prevented, by defendants’ interference, from completing the contract Defendants insist that the contract remained in full force and effect, that the extent of plaintiffs’ recovery should have been computed in accordance therewith, and that the judgment is erroneous because it awards plaintiffs a sum in excess of the contract price and is otherwise unsupported by the evidence.

On behalf of plaintiffs it is urged that the trial court was justified in finding and concluding as a matter of law that there had been an abandonment of the contract because (a) the conduct of defendants indicated their intention to abandon the written undertaking of the parties, and (b) the action and conduct of both parties indicated they considered the contract as abandoned. Plaintiffs contend that the judgment is proper and adequately supported by the evidence.

Thus, the primary and essentially determinative question on which the parties have drawn issue is whether the contract was abandoned or has remained in effect. In resolving this issue we first direct attention to the written instrument involved and to the circumstances surrounding its execution by the parties.

In planning the dwelling they wished to build, defendants consulted and employed an architect, Mr. Ellis Jones. The architect designed the structure, and prepared complete building plans consisting of six sheets of detailed drawings which provide that the construction thereunder “shall comply with the Federal Housing Administration’s Minimum Property Requirements in their entirety”. Defendants submitted these plans to plaintiff Alfred A. Julian and four other contractors for bids. After the expiration of approximately ten days, Mr. Julian submitted his bid in the sum of $27,-200.00 and thereby became the successful bidder. Defendants so informed the architect, who thereafter met with plaintiffs and defendants, at the home of the former, to assist the parties in making a contract.

The proposed written agreement was prepared by Mr. Jones on a standard form approved by the American Institute of Architects, and entitled “Agreement and General Conditions Between Contractor and Owner”. The document designates plaintiff Alfred A. Julian as the “Contractor”' and both defendants as “Owners”, provides that “the Contractor shall furnish all of the materials and perform all of the work. * * * as shown on the drawings and described in the specification * * * ” and obligates the owners to pay the contractor the sum of $27,200.00 “for the performance of the contract subject to the additions and deductions provided therein”. The specifications provided in the contract document are “F.H.A. Minimum Property Requirements”.

Other material provisions of the instrument are as follows:

“The Contractor shall permit and facilitate inspection of the work by the Owner and his agents and public authorities at all times”, * * *.
“The Owner may order changes in; the work, the Contract Sum being adjusted accordingly. All such orders- and adjustments shall be in writing. Claims by the Contractor for extra, cost must be made in writing before-executing the work involved”. * * *-
“The Owner shall make payments. * * * on request by contractor, but not to be more than once per month, and on a set date, allowing the owner 10 days to pay only receipted bills”.. * * *
“The Architect shall have general supervision of the work. He has author *727 ity to stop the work if necessary to insure its proper execution. He shall certify to the Owner when payments under the contract are due and the amounts to he paid. * * * ”

After some preliminary discussion the written agreement was signed by both defendant property owners and by plaintiff Alfred A. Julian, but plaintiff Berniece Julian refused to sign the instrument.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Daugherty v. Bruce Realty & Development, Inc.
892 S.W.2d 332 (Missouri Court of Appeals, 1995)
Winn-Senter Construction Co. v. Katie Franks, Inc.
816 S.W.2d 943 (Missouri Court of Appeals, 1991)
Historic Hermann, Inc. v. Thuli
790 S.W.2d 931 (Missouri Court of Appeals, 1990)
Bash v. B.C. Construction Co.
780 S.W.2d 697 (Missouri Court of Appeals, 1989)
Becker Electric Co. v. Director of Revenue
749 S.W.2d 403 (Supreme Court of Missouri, 1988)
Contour Chair Lounge Co. v. True-Fit Chair, Inc.
648 F. Supp. 704 (E.D. Missouri, 1986)
Pilla v. Estate of Pilla
689 S.W.2d 727 (Missouri Court of Appeals, 1985)
Husar Industries, Inc. v. A.L. Huber & Son, Inc.
674 S.W.2d 565 (Missouri Court of Appeals, 1984)
W.E. Koehler Construction Co. v. Medical Center of Blue Springs
670 S.W.2d 558 (Missouri Court of Appeals, 1984)
Waddington v. Wick
652 S.W.2d 147 (Missouri Court of Appeals, 1983)
Desert Irrigation Co., Inc. v. Tolmie
651 P.2d 938 (Idaho Court of Appeals, 1982)
Kranz v. Centropolis Crusher, Inc.
630 S.W.2d 140 (Missouri Court of Appeals, 1982)
United States v. Hankins Const. Co.
510 F. Supp. 933 (E.D. Missouri, 1981)
Collins v. Swope
605 S.W.2d 538 (Missouri Court of Appeals, 1980)
St. Charles Floor Co. v. Hoelzer
565 S.W.2d 844 (Missouri Court of Appeals, 1978)
Forsythe v. Starnes
554 S.W.2d 100 (Missouri Court of Appeals, 1977)
Hall v. Knapp
552 S.W.2d 299 (Missouri Court of Appeals, 1977)
Wright v. Wright
538 S.W.2d 750 (Missouri Court of Appeals, 1976)
Burger v. Wood
446 S.W.2d 436 (Missouri Court of Appeals, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
382 S.W.2d 723, 1964 Mo. App. LEXIS 569, Counsel Stack Legal Research, https://law.counselstack.com/opinion/julian-v-kiefer-moctapp-1964.