W.E. Koehler Construction Co. v. Medical Center of Blue Springs

670 S.W.2d 558, 1984 Mo. App. LEXIS 3720
CourtMissouri Court of Appeals
DecidedApril 24, 1984
DocketWD 34072
StatusPublished
Cited by11 cases

This text of 670 S.W.2d 558 (W.E. Koehler Construction Co. v. Medical Center of Blue Springs) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
W.E. Koehler Construction Co. v. Medical Center of Blue Springs, 670 S.W.2d 558, 1984 Mo. App. LEXIS 3720 (Mo. Ct. App. 1984).

Opinion

NUGENT, Judge.

Plaintiff, W.E. Koehler Construction Company, Inc., and defendant, Medical Center of Blue Springs, a Missouri limited partnership, entered into a written construction contract and plaintiff brought an action for breach of a later and related oral agreement. After a jury verdict for $46,-875.00 was returned in favor of plaintiff, the court sustained defendant’s motion for judgment notwithstanding the verdict and alternatively awarded a new trial on the ground that the verdict was against the weight of the evidence. Plaintiff appeals. We affirm the trial court’s entry of judgment notwithstanding the verdict.

In ruling on a judgment entered for the defendant notwithstanding the verdict, we consider only the evidence favorable to the verdict and the reasonable inferences derived from that evidence, and disregard the defendant’s evidence except insofar as it aids the plaintiff’s case. Murski v. Sportsman Cycles, Inc., 559 S.W.2d 67, 68 (Mo.App.1977).

Viewed in this light, the evidence was as follows. In August, 1977, defendant issued an invitation to bid for the construction of a new building for Medical Center of Blue Springs. Plaintiff submitted its bid of $535,835 on September 20, 1977, with the obligation and understanding that such bid was to remain open and firm for sixty days. In computing its bid, plaintiff, mindful of increases in construction costs at that time, relied upon the representation that a contract would be executed and work would commence within sixty days. No contract was entered into within the sixty days.

Mr. Koehler, the president of Koehler Construction, testified that in early February, Mr. Champlin, the architect, Dr. William Whitley, a representative of defendant, 1 and defendant’s attorney met with him to see if plaintiff was willing to honor its September 20 bid. Plaintiff was no longer bound to do so, the sixty days having long since expired. At the meeting, Mr. Koehler said, “At this point in time, we can’t go ahead with this bid without some way of recouping our losses, but if the architect and I have all latitudes to change materials, methods of construction, I can hold by bid firm.” He testified that the parties then “orally agreed that Koehler and the architect would have all latitude to make changes as we could see fit that would not change the integrity of the building or the function ... or the appearance _” The parties did not put this agreement in writing, fearing that “it would effect the financing.” Plaintiff did, however, introduce into evidence a copy of its February 2, 1978 letter to the defendant, the architect and to defendant’s attorney, which put “on record” the oral agreement.

On February 21, 1978, a written contract was entered into between the plaintiff and defendant limited partnership for the construction of the medical center building. Although Mr. Koehler realized that nothing regarding the substitution of materials was put into the written contract, he testified that he entered the written contract because he believed that the parties’ prior oral agreement was part of the agreement he was then entering.

*560 The written contract is entitled “Standard Form of Agreement Between Owner and Contractor” and is approved by the American Institute of Architects. Article 1 of the agreement is entitled “The Contract Documents.” The following is printed under Article 1:

The Contract Documents consist of this Agreement, the Conditions of the Contract (General, Supplementary and other Conditions), the Drawings, the Specifications, all Addenda issued prior to and all Modifications issued after execution of this Agreement. These form the Contract, and all are as fully a part of the Contract as if attached to this Agreement or repeated herein. An enumeration of the Contract Documents appears in Article 7.

The following is printed under Article 7:

7.2 The Contract Documents, which constitute the entire agreement between the Owner and the Contractor, are listed in Article 1 and, except for Modifications issued after execution of this Agreement, are enumerated as follows: (List below the Agreement, the Conditions of the Contract (General, Supplementary, and other Conditions), the Drawings, the Specifications, and any Addenda and accepted alternates, showing page or sheet numbers in all cases and dates where applicable.)

Pursuant to 7.2, the following is typed and hand-printed insertion appears:

Agreement, dated February 21, 1978, by and between Owner and Contractor; Specifications, by Robert E. Champlin, Architect, and Leon B. Carlson & Associates, Engineers; Architectural Drawings, dated August 24, 1977; Mechanical Drawings dated August 29, 1977, and Revised Drawings 1, 3, 5, 7, 9, 11, 13, 14, E-l, M-l, M-3, and M-4, dated October 11, 1977, and Revised Drawing 4, dated February 6, 1978; Bid Proposal by Contractor.

On the first page of the printed A.I.A. form entitled “General Conditions of the Contract for Construction,” the following standard integration clause appears:

This Contract represents the entire and integrated agreement between the parties hereto and supersedes all prior negotiations, representations, or agreements, either written or oral.

The contract also authorizes later changes in the work by written change orders.

The essential terms of the written contract were that defendant would pay plaintiff a contract sum, based upon plaintiffs bid proposal of $535,835, for erecting the medical center according to the specifications and drawings. No provision for substitution of materials is included in any of the contract documents.

In late March or early April, while plaintiff was on the job site after he had begun work on the medical center, defendant informed plaintiff that no changes in the construction (other than drain pipe and duct work changes) would be allowed unless accompanied by written change orders as the contract permitted. Plaintiff testified that “as far as he was concerned” this made the contract “null and void,” because he was “induced to sign the original” contract, because- he thought he “could make changes in the materials and methods of construction.” When Mr. Koehler threatened to leave the job, Dr. Whitley suggested that “there must be some way we can work this out.” The parties then orally agreed that if plaintiff would finish construction of the building in accordance with the written contract, defendant would allow plaintiff to do any and all additional work on the lower unfinished level of the building at any time in the future at a reasonable price. That agreement was never put into writing and no plans existed at the time the agreement was made for any specific additional work to complete the additional 10,500 square feet on that level.

The plaintiff finished the building in accordance with the written contract. The defendant performed its side of the written agreement. What plaintiff complains of is defendant’s use of another contractor for later construction of a dental suite and finish work on the lower level. Defendant *561

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J.R. Waymire Co. v. Antares Corp.
975 S.W.2d 243 (Missouri Court of Appeals, 1998)
Brewer v. Devore
960 S.W.2d 519 (Missouri Court of Appeals, 1998)
CIT Group/Sales Financing Inc. v. Lark
906 S.W.2d 865 (Missouri Court of Appeals, 1995)
Union Electric Co. v. Fundways, Ltd.
886 S.W.2d 169 (Missouri Court of Appeals, 1994)
Cash v. Benward
873 S.W.2d 913 (Missouri Court of Appeals, 1994)
Gross v. Diehl Specialties International, Inc.
776 S.W.2d 879 (Missouri Court of Appeals, 1989)
Southgate Bank & Trust Co. v. Axtell
710 S.W.2d 247 (Missouri Court of Appeals, 1986)
Centerre Bank of Kansas City, N.A. v. Distributors, Inc.
705 S.W.2d 42 (Missouri Court of Appeals, 1985)
Don Gaston & Son, Inc. v. Vic Koepke Excavating & Grading Co.
693 S.W.2d 850 (Missouri Court of Appeals, 1985)
Moore v. Seabaugh
684 S.W.2d 492 (Missouri Court of Appeals, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
670 S.W.2d 558, 1984 Mo. App. LEXIS 3720, Counsel Stack Legal Research, https://law.counselstack.com/opinion/we-koehler-construction-co-v-medical-center-of-blue-springs-moctapp-1984.