Rexite Casting Co. v. Midwest Mower Corp.

267 S.W.2d 327
CourtMissouri Court of Appeals
DecidedApril 20, 1954
Docket28840
StatusPublished
Cited by30 cases

This text of 267 S.W.2d 327 (Rexite Casting Co. v. Midwest Mower Corp.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rexite Casting Co. v. Midwest Mower Corp., 267 S.W.2d 327 (Mo. Ct. App. 1954).

Opinion

HOUSER, Commissioner.

Action on a written contract. Plaintiff corporation, Rexite Casting Company, and defendant Midwest Mower Corporation entered into a contract based upon a letter dated November 19, 1947 and an attached purchase order for 100,000 cast aluminum side frames for use in the manufacture of lawn mowers, at a unit price of each. By the terms of the contract plaintiff was obligated to procure and furnish the necessary permanent molds for casting these parts, but defendant was not to be liable for any cost of molds until they were accepted by defendant as satisfactory as evidenced by sample parts produced. The actual cost of the molds as evidenced by invoice (not to exceed a total of $3,600) was to be amortized over 100,000 parts at a sum not to exceed 3.6^ each. The molds were to be and remain the sole property of the Midwest Mower Corporation, which had the right to cancel the purchase order without recourse upon 30 days’ written notice, in which event the mower corporation would pay “the balance due on molds after all payments have been credited to the cost of the molds.” After the molds were procured and satisfactory sample castings made plaintiff, in June, 1948, commenced production of the side frames. After approximately 17,000 to 20,000 castings had been shipped, and on *329 August 16, 1948 .William F. Reck, Jr., vice-president of plaintiff company, notified Sigmund Rudman and Harry Bobroff, officers of defendant corporation, that it was necessary to increase the price of the castings due to increased metal costs which plaintiff’s officers could not foresee when the contract was negotiated in 'November, 1947; that unless plaintiff increased the price it would be losing money every time it made a casting; Jand that defendant could “take it or leave Í it,” i. e. either pay the increase or plaintiff would not make delivery. According to plaintiff’s evidence defendant’s officers opposed the increased price but, after discussing the “pros and cons” of the upward price, finally “acquiesced” and told Reck to write a letter to that effect. Plaintiff’s letter “confirmed” the parties’ conversation “regarding adjusted price on future delivery of permanent mold castings” at the “adjusted price” of 78%p, the new price to become effective after delivery of the castings already finished and awaiting delivery on plaintiff’s floor, which we,re to be invoiced to defendant at the old price.

Defendant’s officers claimed that after beginning the delivery of castings at the contract price plaintiff changed the invoice j price to 78¾{⅞ without any prior^agreement, ] and that when defendant’s representatives complained and pointed to the contract price Reck told them “in no uncertain terms” that he would have to raise the price, and that 78% would be the price “or else we would get no castings.” Defendant had a substantial number of orders for lawn mowers for which delivery had been contracted at a fixed, established price. An officer of defendant testified that plaintiff raised the .price of the castings (approximately 50%) at a time when defendant was in heavy production in an amount which, if paid, would absorb enough of the contemplated profit to make the operation unprofitable. The frame castings were an .essential part-, of the lawn mower, without which the whole manufacturing operation would have to shut down. It was too late to contract for castings from other sources for delivery during that production year. It takes months to' make the necessary molds. If defendant did not agree to pay the increased price the plant could no longer operate — they would not be able to deliver and therefore would lose all of their customers. According to defendant’s officers defendant was “over a barrel” on the matter; plaintiff had put defendant in an untenable position and defendant had no choice but to agree; had “no other recourse, to stay in business.” Defendant’s officers felt that plaintiff had “gone back on the original deal.” Defendant did not reply in writing to plaintiff’s letter of August 16 but did order, receive and_pay at the increased price for several lots of castings which were delivered by plaintiff during .the fall of 1948 and until it had enough castings to carry it through that season. The payments made at, the advanced price included the stipulated payment on account of the molds. Defendant. quit taking castings from plaintiff in December 1948. Immediately after the price was raised defendant made efforts to procure molds elsewhere. On January 5, 1949, after three or four months of negotiating, defendant entered into a contract with Missouri Die Casting Company for the manufacture of side frames, using the die casting method, and for the production of the necessary dies at a guaranteed maximum price of $3,600. The castings were to be supplied at the cost of 57‡ per unit. Defendant refused to take more castings from plaintiff as soon as Missouri Die Casting Company had assured defendant that it could produce the castings in sufficient quantity during the coming season. Thereupon defendant made demand for reimbursement for overcharges, claiming the difference between the contract and the “adjusted price” on all deliveries made under the increased price. After defendant refused to take more castings plaintiff demanded payment for castings furnished but not paid for and offered to turn over the molds to defendant provided defendant paid 1 plaintiff the balance of" $2,937.21 claimed to be due on the molds.

Rexite Casting Company then brought suit against Midwest Mower Corporation in two counts. Count I was for the balance due for. castings made and delivered but not paid for, in the sum of $783.22, figured *330 at the rate of 78¾$ each, based upon the written contract as amended and modified. Count II was for the balance due on the molds in the sum of $2,937.21, based upon the original written contract, without any ,-allegation as to modification. The mower corporation, answering Count I, admitted the existence and terms of the original contract but denied that there was a modifica-i-tion thereof. In answer to Count II the mower corporation alleged that the casting company had breached the contract; that it agreed to pay the increase demanded by the casting company under duress; that the increase was without consideration and void, and that because of the casting company’s breach of contract the latter was not entitled to recover the balance claimed on the molds. The mower corporation also filed a counterclaim in which it sought to recover as overcharges the difference between the contract price and the increased price paid on parts cast and delivered after the price hike went into effect, in the sum 6f $2,301.75, and for $662.79 paid on the molds at the times the overcharges on the parts were paid, less $578.25 which the mower corporation conceded was due the casting company on unpaid invoices figured at the original contract rate of 52‡ each.

The trial court submitted the issues arising on Count I and on the counterclaim to a jury, which returned a verdict for the casting company and against the mower corporation on Count I of the petition for the full amount, figured at the rate of 78¾^ each for castings delivered but not paid for, and for the casting company on the mower corporation’s counterclaim. The court directed a verdict for defendant mower corporation on Count II of the petition.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carr, Cody
Court of Appeals of Texas, 2015
HGS Homes, Inc. v. Kelly Residential Group, Inc.
948 S.W.2d 251 (Missouri Court of Appeals, 1997)
In re Downtown Properties, Inc.
162 B.R. 244 (W.D. Missouri, 1993)
McKnight v. Midwest Eye Institute of Kansas City, Inc.
799 S.W.2d 909 (Missouri Court of Appeals, 1990)
Homier v. Faricy Truck & Equipment Co.
784 P.2d 798 (Colorado Court of Appeals, 1989)
Big River Hills Ass'n v. Altmann
747 S.W.2d 738 (Missouri Court of Appeals, 1988)
Adrian N. Baker & Co. v. Demartino
733 S.W.2d 14 (Missouri Court of Appeals, 1987)
Dippel v. Rokwell Industries, Inc.
715 S.W.2d 553 (Missouri Court of Appeals, 1986)
W.E. Koehler Construction Co. v. Medical Center of Blue Springs
670 S.W.2d 558 (Missouri Court of Appeals, 1984)
Twin River Construction Co. v. Public Water District No. 6
653 S.W.2d 682 (Missouri Court of Appeals, 1983)
Dyer-Bussey Realtors, Inc. v. Wright
647 S.W.2d 215 (Missouri Court of Appeals, 1983)
Stokes v. Enmark Collaborative
634 S.W.2d 571 (Missouri Court of Appeals, 1982)
Willhite v. Marlow Adjustment, Inc.
623 S.W.2d 254 (Missouri Court of Appeals, 1981)
United States v. Hankins Const. Co.
510 F. Supp. 933 (E.D. Missouri, 1981)
Glen O'Brien Movable Partition Co. v. McMullen
608 S.W.2d 512 (Missouri Court of Appeals, 1980)
Sayers v. BAGGRAFT CORP. OF AMERICA
597 S.W.2d 280 (Missouri Court of Appeals, 1980)
Blythe v. Blythe
586 S.W.2d 393 (Missouri Court of Appeals, 1979)
C & M DEVELOPERS, INC. v. Berbiglia, Inc.
585 S.W.2d 176 (Missouri Court of Appeals, 1979)
B & B Equipment Co., Inc. v. Bowen
581 S.W.2d 80 (Missouri Court of Appeals, 1979)
Katz v. Pulaski Savings & Loan Ass'n
546 S.W.2d 24 (Missouri Court of Appeals, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
267 S.W.2d 327, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rexite-casting-co-v-midwest-mower-corp-moctapp-1954.