United States v. Hankins Const. Co.

510 F. Supp. 933, 29 Cont. Cas. Fed. 81,675, 1981 U.S. Dist. LEXIS 9489
CourtDistrict Court, E.D. Missouri
DecidedMarch 30, 1981
Docket78-334C(2)
StatusPublished
Cited by3 cases

This text of 510 F. Supp. 933 (United States v. Hankins Const. Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Hankins Const. Co., 510 F. Supp. 933, 29 Cont. Cas. Fed. 81,675, 1981 U.S. Dist. LEXIS 9489 (E.D. Mo. 1981).

Opinion

510 F.Supp. 933 (1981)

UNITED STATES of America, etc., Plaintiff,
v.
HANKINS CONSTRUCTION CO., et al., Defendants.

No. 78-334C(2).

United States District Court, E. D. Missouri, E. D.

March 30, 1981.

*934 Richard Wolff, Clayton, Mo., for plaintiff.

J. Dennis O'Leary, Dubail, Judge, Kilker & Maier, St. Louis, Mo., and Theodore C. Traeger, Clayton, Mo., for Hankins Construction Co. & U. S. Fidelity & Guaranty Co.

Edward M. Goldenhersh, Sidel, Sandweiss & Kaskowitz, St. Louis, Mo., for Maryland & Brunson Construction Corp.

Richard Wolff, St. Louis, Mo., for National Bonding & Ins. Co. & Robert & Gloria Schall.

MEMORANDUM

NANGLE, District Judge.

This case is now before the Court for decision upon the merits. Plaintiff brought this suit pursuant to the Miller Act, 40 U.S.C. §§ 270a and 270b, seeking to recover sums allegedly due and owing on grading and seeding subcontracts. Plaintiff also seeks a declaration that a promissory note given to defendant has been satisfied by a credit given to defendant on the amount owing under the above grading subcontract. Defendant has counterclaimed, seeking damages for plaintiff's alleged breach of the above subcontracts, as well as seeking to collect the above-mentioned promissory note.

This case was tried before the Court sitting without a jury. This Court, having considered the pleadings, the testimony of *935 the witnesses, and the documents and depositions in evidence, and being fully advised in the premises, hereby makes the following Findings of Fact and Conclusions of Law, as required by Rule 52, Federal Rules of Civil Procedure.

FINDINGS OF FACT

Plaintiff Suburban Tree Service, Inc. (Suburban) and defendant Hankins Construction Company (Hankins) are Missouri corporations, duly registered and transacting business in that state. Defendant United States Fidelity and Guarantee Company (U.S.F. & G.) is a Maryland corporation. Counter-defendants Robert and Gloria Schall are individuals residing in Missouri, and are officers and directors of plaintiff.

On June 10, 1976, Hankins entered into a written contract with the United States of America, acting by and through the Department of the Army and the Corps of Engineers (the Corps), for the construction of improvements at Fort Leonard Wood in southern Missouri.[1] The project was referred to as the Ammunition Storage Facilities project. As a condition of the contract, Hankins was required to execute and deliver a payment bond for the benefit of persons supplying labor and materials in the prosecution of the work provided for in the contract. Hankins obtained such a bond from defendant U.S.F. & G.[2]

THE GRADING SUBCONTRACT

On June 30, 1976, defendant entered into a subcontract with Brunson Construction Corporation (Brunson), formerly a defendant herein, wherein Brunson was to perform the environmental protection, and grading, excavating, filling and backfilling portions of the project (the grading subcontract). Brunson was to be paid the lump sum of three hundred thousand dollars ($300,000.00) for this work. On that same date, Brunson, in turn, sub-subcontracted this work to plaintiff for the lump sum of one hundred forty-eight thousand six hundred dollars ($148,600.00).[2a]

Plaintiff commenced work on this project on or about July 19, 1976. Though progress was slowed somewhat by the unexpected presence of large amounts of uncharted rock, plaintiff was satisfactorily progressing until the onset of winter. At that time, work was discontinued due to severe weather conditions. Plaintiff resumed work on the project in the spring. During these periods, Brunson performed only a minimal amount of supervisory work. All the actual labor on the Brunson-Hankins subcontract was performed by Suburban pursuant to the Brunson-Suburban sub-subcontract. In the spring, a dispute arose between plaintiff and Brunson as to the amount of work plaintiff had completed and its entitlement to payment therefor.

Matters eventually came to a head on May 16, 1977. Plaintiff had informed Brunson that unless plaintiff was paid a substantial sum prior to that date, plaintiff would pull off the job. When not paid, plaintiff did so. Brunson then fired plaintiff, thus terminating the sub-subcontract between those parties. Plaintiff had been paid by Brunson up to this time a total of eighty-one thousand five hundred fifty-seven dollars ($81,557.00).

Plaintiff immediately contacted Hankins and informed it of what had transpired. Plaintiff told Hankins that the subcontract was eighty percent complete, and expressed the fear that Brunson would hire someone at an exorbitant rate to complete the small amount of work remaining, thereby harming plaintiff's chances of recovering the *936 money owed it. The parties discussed the possibility of Suburban taking over the Brunson subcontract.

The parties are in sharp dispute as to the agreement eventually reached. On the basis of all the credible evidence, this Court believes the agreement reached is as follows: Brunson would be fired by Hankins, and Suburban would be hired to complete the subcontract. Suburban would be paid on a "machine time" basis, with a maximum payment of the amount still owning to Suburban on the Brunson sub-subcontract — sixty-seven thousand forty-three dollars ($67,043.00). Hankins agreed to advance Suburban thirty thousand dollars ($30,000.00), since Suburban was short on operating funds. Suburban, and Robert and Gloria Schall individually, would sign a promissory note evidencing this advance. This note would subsequently be cancelled upon completion of the work.

In accordance with this agreement, Hankins fired Brunson on May 16, 1977. Hankins has subsequently paid Brunson the amount outstanding on the three hundred thousand dollar subcontract, less amounts sufficient to cover backcharges and an amount equal to that outstanding on the Brunson-Suburban sub-subcontract. Hankins also advanced Suburban thirty thousand dollars that day, and a promissory note evidencing that advance was signed the next day by Robert and Gloria Schall individually, and by Robert Schall on behalf of Suburban. Suburban returned to work on the project on May 17, 1977.

Suburban worked on the grading subcontract until October 14, 1977, when it pulled off the job. The contract was substantially completed at that time, though further work was subsequently necessary on Hankins' part to bring the project into compliance with the Corps' specifications.

During this time period, plaintiff expended machine time which exceeded the amount remaining on the Brunson-Suburban sub-subcontract. The most reliable records of the amounts of time expended by plaintiff are defendant's daily time sheets (Exhibits V through V-6). These time sheets indicate that plaintiff's machinery was used in the following amounts on the basic grading contract:

D7E Dozer                     777 hours
Wabco Scraper                 282 hours
544 Payloader                 341 hours
International 250C              4 hours
310 Backhoe                    80 hours
760 Scraper                    74 hours.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
510 F. Supp. 933, 29 Cont. Cas. Fed. 81,675, 1981 U.S. Dist. LEXIS 9489, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-hankins-const-co-moed-1981.