Cork Plumbing Co. v. Martin Bloom Associates, Inc.

573 S.W.2d 947, 25 U.C.C. Rep. Serv. (West) 1245, 1978 Mo. App. LEXIS 2325
CourtMissouri Court of Appeals
DecidedOctober 3, 1978
Docket38968
StatusPublished
Cited by28 cases

This text of 573 S.W.2d 947 (Cork Plumbing Co. v. Martin Bloom Associates, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cork Plumbing Co. v. Martin Bloom Associates, Inc., 573 S.W.2d 947, 25 U.C.C. Rep. Serv. (West) 1245, 1978 Mo. App. LEXIS 2325 (Mo. Ct. App. 1978).

Opinion

REINHARD, Judge.

This appeal arises from an action instituted by respondent Cork Plumbing Company, Inc. (hereafter referred to as Cork), which sought a judgment for the imposition of a mechanic’s lien upon certain real property located in St. Louis County, Missouri. Appellant, Martin Bloom Associates, Inc. (hereafter referred to as M.B.A.), was the owner of the improved real property and sought damages for breach of contract in a counterclaim. The trial court ordered a mechanic’s lien against the real property, in the form of special execution to be levied only against that property, and held against M.B.A. on its counterclaim.

Respondent has made a motion to dismiss this appeal for failure to make a “fair and concise” statement of facts as required by Rule 84.04(c). We deny respondent’s motion.

In October 1972, M.B.A. entered into a joint venture with Grand Glaize Village Co. for the construction of the Grand Glaize Apartments in St. Louis County. This joint venture was known as Grand Glaize Apartments Co., with each company holding a 50% interest. Grand Glaize Village Co. was to provide land for the project, and M.B.A. was to provide for the construction of the buildings. In October or November of 1973, Grand Glaize Village Co. encountered financial difficulties; consequently, the project was sold to a limited partnership, of which M.B.A. was one of two general partners. Appellant Security Properties ’73 was the second general partner. M.B.A. was involved in this project as owners to this extent until February or March of 1976, at which time M.B.A. sold its interest and ceased being a general partner. Appellants Gershman Investment Corporation, Solon Gershman and Oritani Savings and Loan Association were involved here originally as holders of the Deed of Trust for the subject real property. However, this Deed of Trust has been satisfied and released of record. Consequently, these appellants hold no present interest in the real property.

On August 29, 1972, Cork submitted a proposal to M.B.A. for the materials and labor necessary for the completion of plumbing and sewer work in 176 apartment units in the Grand Glaize apartment complex. The proposal was accepted thereafter, subject to final commitment by the Federal Housing Administration. In November of 1972, the commitment was received. On February 12, 1973, M.B.A. sent Cork a second contract which covered the same work as the August 29, 1972 contract and requested that it be signed. Cork signed this contract and returned it to M.B.A. Thereafter, on May 22, 1973, Cork sent M.B.A. a letter informing M.B.A. that the prices quoted in the August 29, 1972 contract would be honored for only one year, and that a 6½% increase should be anticipated at the end of that period. On June 26, 1973, M.B.A. authorized Cork to begin work as per the August 29, 1972 contract and agreed to pay the increase starting in August, 1973. Shortly thereafter, on June 28, 1973, Cork began its work.

On April 10, 1974, Cork submitted an additional proposal to M.B.A. for plumbing work to be done on a “clubhouse” in the Grand Glaize apartment complex. Thereafter on May 22, 1974, the proposal was accepted less the cost for labor and materials for certain minor items which were excluded from the original proposal. In addition to these written agreements there were also several minor oral agreements between Cork and M.B.A. for extra work which arose during this period.

The payment terms of the two contracts at issue here are different. The August 29, *951 1972 agreement called for payments “to be billed as the job progresses.” The February 12, 1973 contract, however, called for monthly progress payments due on or about the 20th day of each month for 90% of all labor performed, and for all the materials incorporated in the work or suitably stored at the jobsite during the preceding month. Cork billed M.B.A. monthly for the work completed. Billings were made and payments were received until May of 1974, when M.B.A. failed to pay for its May invoices. In the latter part of June 1974, the president of Cork, Willard Swyers, contacted M.B.A. in regard to the late payment. M.B.A. made assurances to Swyers that they did not have the money to make payment, but that they would have the money to do so in the near future.

An additional period of time passed in which Cork did not receive payment. At this time, Don Cork, another Cork officer, contacted Frank Malone, M.B.A.’s executive vice-president, and informed him that if payments were not received, Cork would be forced to pull off the job site. Malone indicated that M.B.A. could not pay the May, June or July invoices. Consequently, because of this failure to make current payments and M.B.A.’s statements that it would not make payments in the future, Cork pulled its men off the job on July 17, 1974. Subsequent to the removal of his men from the job, Mr. Cork and his foreman, Fred Richter, at the request of M.B.A., came back to make an adjustment on some completed ground work so that a particular building could pass inspection. This occurred on July 24, 1974, and was the last work performed by Cork for M.B.A. Cork alleged the balance due was $39,-830.90.

Thereafter, in a letter dated July 30, 1974, M.B.A. proposed a different payment plan. This plan would have called for an immediate payment of $6,600 with weekly payments of $1,200 for two weeks to cover the required payroll for the project. Thereafter, upon receipt of the latest FHA-approved draw, M.B.A. would promptly pay Cork an additional $7,000. One-half the balance due would then be deferred until the final FHA-approved draw, and the rest of the balance due would be paid in monthly installments. Cork refused this plan. Subsequently, M.B.A. contracted the uncompleted work out to other plumbing contractors. M.B.A. in its counterclaim, claims the excess costs of $58,009.27 caused by the refusal of Cork to complete the work in accordance with the contracts.

On September 5, 1974, Cork filed a mechanic’s lien statement in the office of the Clerk of the Circuit Court of St. Louis County in the amount of $39,830.90, pursuant to § 429.010 et seq., RSMo. 1969. Thereafter, on October 4, 1974, Cork filed suit in the Circuit Court of St. Louis County to enforce its mechanic’s lien.

On June 30, 1975, M.B.A. filed a petition for arrangement under Chapter XI in the United States District Court of the Eastern District of Missouri. Subsequently, on November 25, 1975, Cork and M.B.A. entered into an agreement whereby any allowances given Cork in the Chapter XI proceeding would be without prejudice to the rights of Cork or M.B.A. and would not be deemed res judicata in the mechanic’s lien litigation. Further, pursuant to Rule ll-44(d) of the Bankruptcy Act, Cork prayed for relief from the stay that had been issued by the Bankruptcy Court so that Cork could proceed in the mechanic’s lien suit. Such relief was granted on October 17, 1975, by order of the Bankruptcy Court in which Cork was allowed to enforce its lien. However, Cork was limited to seeking a finding of indebtedness against M.B.A. and obtaining satisfaction through execution upon the subject improved real property, rather than enforcing a money judgment against M.B.A. On December 15, 1975, M.B.A. was discharged in bankruptcy. Cork received an allowance of $6,329.63.

After a trial in the circuit court without a jury, a judgment was entered in favor of Cork in the amount of $38,522.90. This *952

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bob DeGeorge Associates, Inc. v. Hawthorn Bank
377 S.W.3d 592 (Supreme Court of Missouri, 2012)
RACMP Enterprises, Inc. v. Commissioner
114 T.C. No. 16 (U.S. Tax Court, 2000)
RACMP Enters. v. Commissioner
114 T.C. No. 16 (U.S. Tax Court, 2000)
TDV Transportation, Inc. v. Keel
966 S.W.2d 347 (Missouri Court of Appeals, 1998)
Tacoma Athletic Club, Inc. v. Indoor Comfort Systems, Inc.
902 P.2d 175 (Court of Appeals of Washington, 1995)
Higgins v. Lauritzen
530 N.W.2d 171 (Michigan Court of Appeals, 1995)
Central District Alarm, Inc. v. Hal-Tuc, Inc.
886 S.W.2d 210 (Missouri Court of Appeals, 1994)
In re Trailer & Plumbing Supplies
578 A.2d 343 (Supreme Court of New Hampshire, 1990)
Wooten v. DeMean
788 S.W.2d 522 (Missouri Court of Appeals, 1990)
Missouri Farmers Ass'n v. McBee
787 S.W.2d 756 (Missouri Court of Appeals, 1990)
Farmington Building Supply Co. v. Courtois
752 S.W.2d 477 (Missouri Court of Appeals, 1988)
Berra v. Papin Builders, Inc.
706 S.W.2d 70 (Missouri Court of Appeals, 1986)
Kenny's Tile & Floor Covering, Inc. v. Curry
681 S.W.2d 461 (Missouri Court of Appeals, 1984)
BCI Corp. v. Charlebois Construction Co.
673 S.W.2d 774 (Supreme Court of Missouri, 1984)
Art Metal Products Co. of Chicago v. Royal Equipment Co.
670 S.W.2d 152 (Missouri Court of Appeals, 1984)
Coakley & Williams, Inc. v. Shatterproof Glass Corp.
706 F.2d 456 (Fourth Circuit, 1983)
Norman v. Ballentine
627 S.W.2d 83 (Missouri Court of Appeals, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
573 S.W.2d 947, 25 U.C.C. Rep. Serv. (West) 1245, 1978 Mo. App. LEXIS 2325, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cork-plumbing-co-v-martin-bloom-associates-inc-moctapp-1978.