Dale Benz, Inc., Contractors, an Arizona Corporation v. American Casualty Company of Reading, Pennsylvania

303 F.2d 80
Court of Appeals for the Ninth Circuit·Decided August 1, 1962·No. 17464·Published·Cited by 27 cases

Opinion

ROSS, District Judge.

This action involves a claim by appellants (hereinafter Benz), a general contractor, against Appellee (hereinafter American), the surety of Basich Brothers Construction Company (hereinafter Basich), a subcontractor, for damages incurred as a result of the failure of *82 Basich to complete its subcontract with Benz. It is a diversity case wherein the district court had jurisdiction pursuant to the provisions of 28 U.S.C. § 1332, and the matter is brought here under 28 U.S.C. § 1291.

According to the pertinent allegations contained in the complaint, on or about the 14th day of May, 1958, Benz held a general contract with the United States of America for construction of certain buildings. On said date it entered into a subcontract with Basich for the performance of work and the furnishing of materials required under the general contract, on a job at the Marine Corps Supply Center, Barstow, California. American, as surety for Basich, made and executed a Performance and Payment Bond. On January 27, 1959, Benz gave American and Basich notice that Basich was in default under the subcontract. Numerous demands were made upon Basich and American for completion of said subcontract, but they failed to comply with said demands. Because of the refusal of Basich, and/or its surety, to complete the subcontract, Benz, as prime contractor, was required to complete the work at its own cost and expense. Benz now seeks to recover from American, the Basich surety, the money thus expended, plus interest and attorney fees. 1

A bench trial was had between Benz and American Casualty Company and a judgment was entered for Benz in the sum of $12,525.00. Subsequently an order was entered denying Benz’s “Motion to Amend and Supplemental Findings of Fact and Conclusions of Law” and “Motion to Alter and Amend Judgment or in the Alternative for New Trial.” Benz has appealed from the above mentioned judgment and order, and also from an order denying its “Motion for Summary Judgment.”

We will list the contentions argued by Benz in its opening brief filed in this Court. However, before doing so we are compelled to comment on the District Court’s “Findings of Fact and Conclusions of Law.” We have heretofore stated the following:

“Findings of fact are required under Rule 52(a) Federal Rules of Civil Procedure, 28 U.S.C.A. The findings should be so explicit as to give the appellate court a clear understanding of the basis of the trial court’s decision, and to enable it to determine the ground on which the trial court reached its decision.” Irish v. United States, 225 F.2d 3, 8 (9th Cir., 1955).

Unfortunately the “Findings of Fact and Conclusions of Law” which were entered in this case fail to meet the standard alluded to in the above quotation. Therefore, the litigants, as well as this Court, are somewhat hampered by the Trial Judge’s manner of handling this facet of the case.

Further, at this juncture it is important to bear in mind that findings of fact shall not be set aside unless clearly erroneous. See Rule 52(a) of the Federal Rules of Civil Procedure, 28 U.S.C.A.

As a further preliminary statement to our discussion of this case we observe that ordinarily we would remand the matter back to the trial judge for more explicit findings. However, as this case is now before us we feel that we are in as good a position to determine the issues involved on the record before us as would be the trial judge on remand. Those issues arise out of and are concerned with figures and arithmetical calculations. In view of the foregoing, and to the end that useless motion and delay be eliminated we will determine the case at this time on its merits, being of the opinion that no good would be served by directing a remand for further and more specific findings.

In light of these comments we will address ourself to the following contentions contained in Benz’s argument.

*83 1. The District Court should have granted its Motion for Summary Judgment.

2. The computations of the District Court were erroneous.

A. Overhead is part of cost.

B. Ten Per Cent should have been added to the cost of the Yeager subcontract.

C. The Court erred in deducting wobble wheel rental of $4,200.00.

D. Back charges for October and November, 1958, are proper items of cost.

E. Damages to American were erroneously awarded.

i. Benz did not depart from the payment provisions of the subcontract.

ii. Benz did not misrepresent to American the percentage of the contract completed by Basich.

iii. There is no evidence that American suffered damage in any amount.

3. American is liable to Benz for attorneys’ fees.

A discussion of the above assertions follows:

1. The Court erred in denying" Benz’s motion for a summary judgment.

Pursuant to the provisions of Rule 56(c) of the Federal Rules of Civil Procedure, a summary judgment shall be rendered if the pleadings, depositions and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law. It is obvious that the lower court had before it genuine issues of material facts, therefore, in accordance with the provisions of Rule 56(c) the District Court properly denied the motion of Benz for summary judgment.

2A. Benz states that it is evident from the Findings of Fact and Conclusions of Law and the Judgment that the Trial Court deducted the overhead amount from its cost of finishing the Basich subcontract. It refers to Appendix B. 2

2B. Benz states, ten percent should have been added to the cost of the contract which Benz entered into with Yeager Brothers Construction Company for the completion of a portion of the uncompleted Basich subcontract.

A consideration of these assertions, 2A and 2B, involves an interpretation of paragraph 8 of the subcontract between Benz and Basich. This paragraph provides, inter alia, that should Basich fail to perform, Benz shall have the right after two days written notice, to terminate the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Dale Benz, Inc., Contractors, an Arizona Corporation v. American Casualty Company of Reading, Pennsylvania, 303 F.2d 80 (9th Cir. 1962).

303 F.2d 80 (Dale Benz, Inc., Contractors, an Arizona Corporation v. American Casualty Company of Reading, Pennsylvania) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United States v. Hankins Const. Co.
510 F. Supp. 933 (E.D. Missouri, 1981)
Bob Maxfield, Inc. v. American Motors Corp.
637 F.2d 1033 (Fifth Circuit, 1981)
Shinn v. First Nat. Bank of Hope
606 S.W.2d 154 (Court of Appeals of Arkansas, 1980)
McCune v. F. Alioto Fish Co.
597 F.2d 1244 (Ninth Circuit, 1979)
Boliver v. Surety Co.
72 Cal. App. Supp. 3d 22 (Appellate Division of the Superior Court of California, 1977)
Felder v. United States
543 F.2d 657 (Ninth Circuit, 1976)
Ronald G. Forsyth v. Cessna Aircraft Company
520 F.2d 608 (Ninth Circuit, 1975)
Chris-Craft Industries, Inc. v. Piper Aircraft Corp.
516 F.2d 172 (Second Circuit, 1975)
Southern Roofing & Petroleum Co. v. Aetna Insurance Co.
293 F. Supp. 725 (E.D. Tennessee, 1968)