Triad Electric & Controls, Inc. v. Power Systems Engineering, Inc.

117 F.3d 180, 1997 WL 361943
CourtCourt of Appeals for the Fifth Circuit
DecidedAugust 1, 1997
Docket94-20783
StatusPublished
Cited by32 cases

This text of 117 F.3d 180 (Triad Electric & Controls, Inc. v. Power Systems Engineering, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Triad Electric & Controls, Inc. v. Power Systems Engineering, Inc., 117 F.3d 180, 1997 WL 361943 (5th Cir. 1997).

Opinion

RHESA HAWKINS BARKSDALE, Circuit Judge:

The primary issues arising out of this Texas diversity action, concerning a construction contract dispute tried to the district court, are whether the court reversibly erred first, by allowing, after close of the evidence, the addition of a fraud counterclaim, and second, by then ruling in favor of that new claim, including awarding punitive damages of $3 million, without allowing the counterclaim defendant, Triad Electric & Controls, Inc., to defend, post-addition, against the claim. Triad, the electrical subcontractor on a construction project, appeals a take-nothing judgment on its contract-based claims against both the project owner’s engineer, Power Systems Engineering, Inc. (PSE), and the general contractor, Century Contractors West, Inc.; the judgment for Century on its counterclaim for overpayments; and the judgment for Century and PSE on their counterclaim for fraud. Century cross-appeals the denial of attorneys’ fees. We AFFIRM in part, REVERSE in part, and REMAND for further proceedings.

I.

The following factual scenario is based primarily on the voluminous and detailed findings of fact by the district court, which, for the most part, Triad does not contest. In mid-1983, PSE invited Century and other general contractors to submit bids for the construction of a cogeneration facility (electricity and steam) at a refinery near Houston, Texas. The PSE-provided bid package consisted of engineering drawings, which included cable schedules describing the electrical connections to be installed and setting forth the approximate wire footage; the Specification for General Construction, which established the quality and quantity standards for the facility, specified types of material and construction codes and practices, and incorporated by reference the PSE Standard Specifications; and the Design Control Specification (DCS), a narrative document describing generally the facility’s systems, operating parameters, and major items of equipment.

At that time, the facility’s design was only partially complete; portions of it were described in detail in the engineering drawings and the Specification for General Construction, but other portions were described only in a narrative manner in the DCS. In fact, the facility was to be constructed as a “fast track” project; construction was to begin before the design drawings were complete, and PSE continued to work on the design after issuing the bid package.

PSE requested two bid prices from each invited general contractor: a “base” bid, based on the incomplete drawings included in the bid package; and a “guaranteed maximum” bid, which was to include all work necessary to complete the project in accordance with the DCS. Pursuant to the base/guaranteed maximum concept, the successful bidder would receive extra payment, *183 above the base price, for any changes in the work described in the incomplete drawings, up to the amount of the guaranteed maximum; but, generally, the cost above that maximum, due to farther changes to the drawings, would be at the successful bidder’s risk. The successful bidder would, however, be entitled to receive payment above the guaranteed maximum price for work performed pursuant to changes to the DCS.

In September 1983, Century and other general contractors bidding on the project invited Triad and other electrical subcontractors to bid the electrical and instrumentation portions. Century furnished Triad with the portion of the bid package pertaining to that portion of the work, including the Specification for General Construction with attachments, the electrical drawings, the piping and instrumentation diagrams, and the DCS. Century invited only prequalified subcontractors to bid on the project; prequalification was based partially on each subcontractor’s representation that it was experienced in bidding projects from conceptual design documents. Triad made such a representation.

Addendum No. 1 to the Specification for General Construction, which was included in the bid package furnished to Triad, requested that the electrical and instrumentation contractors “provide (a) a base bid ... and (b) a guaranteed maximum bid”. The base bid was defined as the “Scope of Work shown in [the] General ... Specification”, which incorporated the engineering drawings. On the other hand, the “guaranteed maximum bid” was defined as the “Scope of Work in [the] General ... Specification ... plus that additional amount necessary to furnish a plant which will start-up and operate as stated in the [DCS]”.

The base/guaranteed maximum concept was defined further in PSE’s 22 September 1983 Clarifications to Addendum No. 1:

The [DCS] establishes the design basis for an operable and rehable plant as defined by [PSE]. The conceptual design, process design, and detail engineering design will be performed by [PSE]. There is no requirement for detail design evaluation, system evaluation, detail auditing of PSE engineering calculations, etc. The contractor is to provide (a) a base bid based on the bid documents, and (b) a guaranteed maximum bid based on the level of confidence the contractor feels that the plant described in the Bid Documents can start-up and operate as defined in the DCS.

Contrary to the foregoing, however, Triad submitted an unpriced “scope letter” to Century on 28 September 1983, stating that the electrical scope of work was “based on the cable schedules”, which were part of the drawings included in the bid package. Triad verbally informed Century that it would perform the scope of work described in that letter for approximately $2.9 million. But, Triad submitted bids of approximately $3.9 million to three other general contractors, Century’s competitors.

In November 1983, Century advised Triad that its initial bid was non-responsive because Triad was not allowed to limit its scope of work to the cable schedules; instead, it had to include everything shown, implied, or required by the DCS. Century gave Triad the option to participate in a base/guaranteed maximum bid, as in the Century/PSE contract, but Triad declined.

Triad submitted its final proposal to Century in December 1983. That proposal removed the qualifieation/limitation to the cable schedules, and proposed a price of approximately $3.1 million.

Subsequent to the 15 November 1984 Century/PSE contract, Century issued a letter of intent to Triad in February 1985, and Triad began work on the project. After several months of negotiations over the Triad subcontract drafted by Century, it was signed in mid-Juhe 1985.

Triad’s subcontract consists of a Purchase Order and a Subcontract Agreement which required it to supply all labor and materials required for the installation of complete and operational electrical and instrumentation systems for the “GUARANTEED MAXIMUM LUMP SUM PRICE” of $3.4 million. In defining the scope of work, the Purchase Order referenced the following: (1) the contract specifications, as modified; (2) the DCS; (3) listed drawings, which included the cable schedules; (4) an equipment list; and *184 (5) a list of instruments to be installed, calibrated, and connected by instrumentation wiring. Those listed drawings- — the contract drawings — were the same as those included in the bid package.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fustolo v. Patriot Grp. LLC (In Re Fustolo)
896 F.3d 76 (First Circuit, 2018)
Richard Jones, Jr. v. Wells Fargo Bank, N.A., et a
858 F.3d 927 (Fifth Circuit, 2017)
Gould v. Ochsner
2015 WY 101 (Wyoming Supreme Court, 2015)
Hedrick v. Commissioner of the Department of Public Safety
2013 OK 98 (Supreme Court of Oklahoma, 2013)
Clearline Technologies Ltd. v. Cooper B-Line, Inc.
948 F. Supp. 2d 691 (S.D. Texas, 2013)
City Of El Paso Texas v. El Paso Entertainment, In
464 F. App'x 366 (Fifth Circuit, 2012)
Metcalf Construction Co. v. United States
102 Fed. Cl. 334 (Federal Claims, 2011)
Shaw Constructors v. PCS Nitrogen Fertilizer LP
326 F. App'x 860 (Fifth Circuit, 2009)
Brown v. Morris
243 F. App'x 31 (Fifth Circuit, 2007)
U-Save Auto Rental of America, Inc. v. Moses
80 F. App'x 929 (Fifth Circuit, 2003)
South Dakota Farm Bureau, Inc. South Dakota Sheep Growers Association, Inc. Haverhals Feedlot, Inc. Sjovall Feedyard, Inc. Frank D. Brost Donald Tesch William A. Aeschlimann Spear H. Ranch, Inc. Marston Holben Marston and Marian Holben Family Trust Montana-Dakota Utilities Company Northwestern Public Service Otter Tail Power Company v. Joyce Hazeltine, in Her Official Capacity as Secretary of State of South Dakota Mark W. Barnett, in His Official Capacity as Attorney General of South Dakota, Dakota Rural Action South Dakota Resources Coalition, Intervenors State of Nebraska Everett Holstein Rudy Meduna Dan Hodges, Amicus on Behalf of the American Farm Bureau Federation Alabama Farm Bureau Federation Arkansas Farm Bureau Federation Kansas Farm Bureau Federation Kentucky Farm Bureau Federation Minnesota Farm Bureau Federation North Dakota Farm Bureau Federation Utah Farm Bureau Federation, Amicus on Behalf of South Dakota Farm Bureau, Inc. South Dakota Sheep Growers Association, Inc. Haverhals Feedlot, Inc. Sjovall Feedyard, Inc. Frank D. Brost Donald Tesch William A. Aeschlimann Spear H. Ranch, Inc. Marston Holben Marston and Marian Holben Family Trust Montana-Dakota Utilities Company Northwestern Public Service Otter Tail Power Company v. Joyce Hazeltine, in Her Official Capacity as Secretary of State of South Dakota Mark W. Barnett, in His Official Capacity as Attorney General of South Dakota, Dakota Rural Action South Dakota Resources Coalition, Intervenors Everett Holstein Rudy Meduna Dan Hodges, Amicus on Behalf of South Dakota Farm Bureau, Inc. South Dakota Sheep Growers Association, Inc. Haverhals Feedlot, Inc. Sjovall Feedyard, Inc. Frank D. Brost Donald Tesch William A. Aeschlimann, Spear H. Ranch, Inc. Marston Holben Marston and Marian Holben Family Trust, Montana-Dakota Utilities Company Northwestern Public Service Otter Tail Power Company v. Joyce Hazeltine, in Her Official Capacity as Secretary of State of South Dakota Mark W. Barnett, in His Official Capacity as Attorney General of South Dakota, Dakota Rural Action South Dakota Resources Coalition, Intervenors South Dakota Farm Bureau, Inc. South Dakota Sheep Growers Association, Inc. Haverhals Feedlot, Inc. Sjovall Feedyard, Inc. Frank D. Brost Donald Tesch William A. Aeschlimann, Spear H. Ranch, Inc. Marston Holben Marston and Marian Holben Family Trust Montana-Dakota Utilities Company Northwestern Public Service Otter Tail Power Company v. Joyce Hazeltine, in Her Official Capacity as Secretary of State of South Dakota Mark W. Barnett, in His Official Capacity as Attorney General of South Dakota, Dakota Rural Action South Dakota Resources Coalition, Intervenors
340 F.3d 583 (Eighth Circuit, 2003)
South Dakota Farm Bureau, Inc. v. Hazeltine
340 F.3d 583 (Eighth Circuit, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
117 F.3d 180, 1997 WL 361943, Counsel Stack Legal Research, https://law.counselstack.com/opinion/triad-electric-controls-inc-v-power-systems-engineering-inc-ca5-1997.