Shaw Constructors v. PCS Nitrogen Fertilizer LP

326 F. App'x 860
CourtCourt of Appeals for the Fifth Circuit
DecidedJune 18, 2009
Docket08-30594
StatusUnpublished

This text of 326 F. App'x 860 (Shaw Constructors v. PCS Nitrogen Fertilizer LP) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shaw Constructors v. PCS Nitrogen Fertilizer LP, 326 F. App'x 860 (5th Cir. 2009).

Opinion

PER CURIAM: *

In a previous appeal in this case, we held that PCS Nitrogen Fertilizer, L.P. *862 was liable to Shaw Constructors under the Louisiana Private Works Act for subcontract work performed in connection with a construction project. Shaw Constructors v. ICF Kaiser Eng’rs, Inc., 395 F.3d 533 (5th Cir.2004). We rendered judgment only as to liability and remanded the case in order for the magistrate judge to determine the amount of liability. After a six-day trial, the magistrate judge entered a judgment in the amount of $1,455,060.47. PCS Nitrogen Fertilizer appealed the judgment and Shaw Constructors filed a cross-appeal asserting that the magistrate judge erred in calculating interest. For the reasons stated below, we reverse and remand only on the issue raised in the cross-appeal.

I. FACTUAL AND PROCEDURAL BACKGROUND

PCS Nitrogen Fertilizer, L.P. (“PCS”) entered into a contract with ICF Kaiser Engineers, Inc. (“Kaiser”) for the construction of a nitric acid production plant. Kaiser subcontracted the piping installation to Shaw Constructors, Inc. (“Shaw”). For reasons which are contested in this appeal, Shaw’s work fell significantly behind schedule. This delay resulted in Kaiser and Shaw entering into a change order that converted their original lump-sum contract into a cost-reimbursable contract. “Change Order No. 1” states, in relevant part:

As compensation for the remaining Subcontract Work, commencing as of the start of business on August 3, 1998 through Project completion, the Subcontractor will be reimbursed for reasonable and necessary costs....
Furthermore, a Not-to-Exceed (NTE) total amount of $7,677,918.00 ... has been established for compensation of costs incurred during the performance of all of the work associated with this Subcontract. It is mutually understood by the parties that the NTE amount may have to be adjusted if reasonable and necessary costs incurred during the performance of the work exceed the total NTE amount. If Contractor observes Subcontractor invoicing for, performing, or reporting work which falls outside of “reasonable and necessary,” Contractor will endeavor to transmit this information to the Subcontractor within 7 days of witnessing the nonconforming work so that billing or field work corrections can be made.

The change order retained the unaltered provisions of the original subcontract including the following prohibition against oral modifications: “No amendment, variance or change in the provisions of this Subcontract shall be made except in writing signed by the authorized representatives of the parties hereto.”

Thereafter, Kaiser fell behind on its payments to Shaw and eventually terminated Shaw from the project prior to completion. Kaiser hired a different company to complete Shaw’s scope of work. Shaw then filed a lien against PCS and a lawsuit against both PCS and Kaiser seeking to collect its unpaid invoices. As a result of this lawsuit, Kaiser and Shaw, but not PCS, entered into a Compromise Agreement. In this agreement, Kaiser agreed to make 20 monthly payments to Shaw of $291,012, which represented the full amount of Shaw’s outstanding invoices plus two extra monthly payments for interest.

Kaiser filed bankruptcy after making only 13 monthly payments under the Compromise Agreement. Rather than pursue its claim in Kaiser’s bankruptcy proceeding, Shaw elected to recover the remaining balance of its invoices from PCS by enforcing the statutory lien granted to it under the Louisiana Private Works Act (“LPWA”). PCS defended by relying on a provision in the original subcontract *863 whereby Shaw waived its right to file liens against PCS’s property. This dispute was the basis of the first appeal in this case. We concluded that, under Louisiana law, Shaw could regard the subcontract as dissolved upon Kaiser’s breach and PCS could not prevent Shaw from enforcing its LPWA lien. Shaw Constructors, 395 F.3d at 536. We remanded the case solely for determination of the amount that PCS owed Shaw under the LPWA. Id. at 555.

After a six-day bench trial, the magistrate judge concluded that: (1) the reasonable and necessary costs of Shaw’s work totaled $11,631,045.20, which was the full amount that it had invoiced Kaiser; (2) Shaw and Kaiser mutually agreed to exceed the NTE amount stated in the change order; (3) under the LPWA, Shaw was entitled to recover from PCS the remaining balance of the price of the work performed pursuant to the subcontract and the change order; (4) the balance owed for work under the subcontract and change order was $5,238,217.90, but PCS received credit for the $3,783,157.43 in payments made by Kaiser under the Compromise Agreement; (5) PCS was therefore liable to Shaw for $1,455,060.47 plus prejudgment interest on that amount from February 23, 1999, the date of judicial demand; and (6) Shaw did not breach its duty to mitigate damages by failing to pursue its claim in Kaiser’s bankruptcy proceeding. PCS filed a timely appeal of the judgment and Shaw filed a cross-appeal regarding the calculation of interest.

II. DISCUSSION

This appeal involves both findings of fact, which we review for clear error, and conclusions of law, which we review de novo. Triad Elec. & Controls, Inc. v. Power Sys. Eng’g, Inc., 117 F.3d 180, 186 (5th Cir.1997). ‘Where there are two permissible views of the evidence, the factfin-der’s choice between them cannot be clearly erroneous.” Anderson v. Bessemer City, 470 U.S. 564, 574, 105 S.Ct. 1504, 84 L.Ed.2d 518 (1985).

PCS raises the following issues regarding the magistrate judge’s findings of fact and conclusions of law: (1) whether Kaiser and Shaw mutually agreed to exceed the NTE amount; (2) whether all of Shaw’s costs were reasonable and necessary; and (3) whether Shaw breached its duty to mitigate by failing to pursue its claim in Kaiser’s bankruptcy proceeding. Additionally, both parties challenge the magistrate judge’s calculation of interest.

A. Did Kaiser and Shaw mutually agree to exceed the NTE amount?

Although PCS continues to assert that the NTE amount could only have been amended through a written agreement pursuant to the prohibition against oral modifications in the original subcontract, the magistrate judge correctly looked to the conduct of the parties to answer this question because, under Louisiana law, “ ‘[wjritten contracts for construction may be modified by oral contracts and by the conduct of the parties, and this is true even when the written contract contains the provision that an owner is liable only if the change orders are in writing.’ ” L & A Contracting Co., Inc. v. Ram Indus. Coatings, Inc., 762 So.2d 1223, 1232 (La.Ct.App.2000) (quoting Pelican Elec. Contractors v. Neumeyer, 419 So.2d 1, 5 (La.Ct.App.1982)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. City of Bessemer City
470 U.S. 564 (Supreme Court, 1985)
Lone Star Industries, Inc. v. American Chemical, Inc.
461 So. 2d 1063 (Louisiana Court of Appeal, 1984)
Allan E. Amundson, Inc. v. Hoppmeyer
442 So. 2d 1254 (Louisiana Court of Appeal, 1983)
Roques v. Alfonso
399 So. 2d 1294 (Louisiana Court of Appeal, 1981)
Long Leaf Lumber, Inc. v. Svolos
258 So. 2d 121 (Louisiana Court of Appeal, 1972)
Trans-Global Alloy v. First Nat. Bank
583 So. 2d 443 (Supreme Court of Louisiana, 1991)
L & a CONTRACTING v. Ram Indus. Coatings, Inc.
762 So. 2d 1223 (Louisiana Court of Appeal, 2000)
Unverzagt v. Young Builders, Inc.
215 So. 2d 823 (Supreme Court of Louisiana, 1968)
Alexander v. Burroughs Corp.
359 So. 2d 607 (Supreme Court of Louisiana, 1978)
Jefferson Door Co. v. Forman Const., Inc.
836 So. 2d 552 (Louisiana Court of Appeal, 2002)
Ridenour v. Wausau Ins. Co.
627 So. 2d 141 (Supreme Court of Louisiana, 1993)
Pelican Elec. Contractors v. Neumeyer
419 So. 2d 1 (Louisiana Court of Appeal, 1982)
Gifford Hill & Co. v. Harper
262 So. 2d 842 (Louisiana Court of Appeal, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
326 F. App'x 860, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shaw-constructors-v-pcs-nitrogen-fertilizer-lp-ca5-2009.