Husar Industries, Inc. v. A.L. Huber & Son, Inc.

674 S.W.2d 565
CourtMissouri Court of Appeals
DecidedJuly 31, 1984
DocketWD 34538
StatusPublished
Cited by9 cases

This text of 674 S.W.2d 565 (Husar Industries, Inc. v. A.L. Huber & Son, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Husar Industries, Inc. v. A.L. Huber & Son, Inc., 674 S.W.2d 565 (Mo. Ct. App. 1984).

Opinion

MANFORD, Judge.

This civil action seeks recovery of monies arising from the construction of a building. The judgment is affirmed.

*567 Before setting forth the pertinent facts and the charged errors, it is necessary, for purposes of clarity, to identify the respective parties, plus to briefly outline the manner in which this case developed procedurally.

This case commenced as an action to enforce a mechanic’s lien by Manuel Morris, the original architect, against Nick Hú-sar, Húsar Industries, Inc., Goppert Bank (mortgagee), and The Land Clearance for Redevelopment Authority of Kansas City, landowner. A.L. Huber & Son, Inc. subsequently secured leave to become a party defendant. Huber then cross-claimed against all other parties, claiming a mechanic’s lien and asking for enforcement of its alleged lien against the property. In addition, Huber sought recovery against Húsar in two separate claims of an account and quantum meruit. By amended answer, Húsar then filed a counterclaim against Morris for design defects in the building and cross-claimed against Huber for failing to construct the building in a workmanlike manner in accordance with the contract between Húsar and Huber.

Just prior to trial, Morris and Húsar settled the claims between them. At the same time, the trial court ordered a separate trial on the mechanic’s lien claim of Huber. This case then became a matter of the contract claims and the quantum meruit claim as between Huber and Húsar. In addition, just prior to trial, Húsar, as an individual, was dismissed by the trial court.

With all of the foregoing changes and developments, and after a conference with and the agreement of counsel for the remaining parties, the trial court realigned the parties. As a result of the trial court’s action, A.L. Huber & Son, Inc. (hereinafter Huber) became plaintiff and Húsar Industries, Inc. (hereinafter Húsar) became defendant. The case was finally tried, and on November 22, 1982, the jury entered its verdict for Huber on its Count I (account) in the sum of $5,193.52 and on its Count II (quantum meruit) in the sum of $23,287.67. On the same date, the trial court entered judgment and added interest, bringing the judgment amount on Count I to $6,864.44 and as to Count II, $30,782.20.

Huber filed an appeal, which was dismissed. Húsar filed an appeal. Huber then filed a motion to reinstate its appeal. Huber then filed a cross appeal. The two cases on appeal were consolidated under the present case number. To prevent any more confusion relative to the party designation and description, this appeal will simply refer to the parties as Huber and Hú-sar and in light of the judgment having been entered against Húsar, this court will, for purposes of the disposition of this appeal, approach the points of alleged error presented by Húsar as if he was the only appellant in the proceedings. This approach permits full discussion and consideration of all the issues between the parties on this appeal, including Huber’s cross appeal.

The record discloses the following pertinent facts.

Huber is a general contractor. Húsar is an automobile automatic transmission repair business. Both parties are closely held corporations in good standing. In 1976, Húsar decided to expand its transmission repair business. This expansion included the erection of a new building. Hú-sar decided upon property at 1620 Troost, Kansas City, Missouri as the location. This particular location was within an area under urban renewal, and as a result, Húsar was able to secure favorable financing. After securing financing, Húsar contacted Manuel Morris and hired Morris as the architect. Morris then drew the building plans. Húsar then contacted various contractors for bids. Following several discussions with Húsar and Morris, which included consideration of building specifications, Huber was selected as the contractor. On February 6, 1978, Húsar and Huber entered into a written contract for the construction of the building.

The contract was a form contract prepared by the American Institute of Architects and called a “Standard Form of Agreement Between Owner and Contractor.” It is also referred to as “A.I.A. 101.” The con *568 tract called for Huber to construct the building and for Húsar to pay the sum of $328,597.00 therefor. In addition, the base contract incorporated other documents as a part thereto. These other documents included A.I.A. A201, which provided for General Conditions of the Contract for Construction, final buildings plans, and specifications. Huber was to build a “shell” type building, and Húsar was to finish most of the interior. The building encompassed some 31,000 square feet. Húsar was to use the building for storage of transmissions and machinery related to the service and rebuilding of transmissions. Húsar had from 1,500 to 2,000 transmissions on hand at any one point in time, and it was contemplated that these would be stored on racks along the interior walls.

Húsar testified that he had disclosed to Huber and Morris the intended use of the building. Huber testified that he did not know of the intended use. Morris had previously stated that Húsar was very secretive about the building’s use.

The contract provided for periodic payments as the work progressed. Payments were made conditional upon approval of the work by the architect. The contract further provided at the point of “substantial completion”, 90% of the contract price was due the contractor, and that within 30 days thereafter, the remainder of the contract price was to be paid “provided the work has been completed, the Contract fully performed, and a final Certificate for payment has been issued by the Architect.”

Huber commenced work on May 31, 1978. The location was cleared of surface trees and debris in preparation of excavation for the foundation. As the excavation proceeded, buried debris consisting of foundations of old buildings, bottles, cinders, and other matter was encountered. This debris was the buried remainder of buildings which had been previously razed by the urban renewal program. It had to be removed in order that excavation and preparation of the building foundation could proceed. The removal and the attending cost are the basis of Huber’s quantum me-ruit claim, and a more detailed discussion of the facts relative thereto are disclosed infra.

Huber completed the excavation, and concrete footings were poured in July and August, 1978. The building designed called for the installation of pre-cast concrete “T” panels to be installed in “slots” designed into the top of the concrete footings. The “T” panels formed the walls of the building. The “T” panels were to be manufactured by the Wilson Company, but Wilson could not meet its commitment, so Huber secured “T” panels from the Omega Company. The “T” panels were shipped to the location, and they were found to be larger than the Wilson panels. In order to accommodate the Omega panels, the slots in the footings had to be enlarged. Additional excavation was also required. The slots were enlarged by sawing them with a concrete saw. Some of the panels had to be “pounded” by sledge hammer into place.

In late July, 1978, the architect Morris quit the project. Húsar appointed a successor architect, John Hueser, eighteen days later. Hueser left the job in November, 1978.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Diversified Metal Fabricators, Inc. v. Blue Skies, Inc.
899 S.W.2d 556 (Missouri Court of Appeals, 1995)
Kansas City v. Keene Corp.
855 S.W.2d 360 (Supreme Court of Missouri, 1993)
Murphy v. City of Springfield
738 S.W.2d 521 (Missouri Court of Appeals, 1987)
Person v. Foggy
726 S.W.2d 489 (Missouri Court of Appeals, 1987)
Craft v. Scaman
715 S.W.2d 531 (Missouri Court of Appeals, 1986)
Manufacturers American Bank v. Stamatis
719 S.W.2d 64 (Missouri Court of Appeals, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
674 S.W.2d 565, Counsel Stack Legal Research, https://law.counselstack.com/opinion/husar-industries-inc-v-al-huber-son-inc-moctapp-1984.