Desert Irrigation Co., Inc. v. Tolmie

651 P.2d 938, 103 Idaho 673
CourtIdaho Court of Appeals
DecidedNovember 30, 1982
Docket13552
StatusPublished
Cited by4 cases

This text of 651 P.2d 938 (Desert Irrigation Co., Inc. v. Tolmie) is published on Counsel Stack Legal Research, covering Idaho Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Desert Irrigation Co., Inc. v. Tolmie, 651 P.2d 938, 103 Idaho 673 (Idaho Ct. App. 1982).

Opinions

SWANSTROM, Judge.

Desert Irrigation brought suit in the district court upon written and oral contracts to collect money claimed to be due for the construction of irrigation pipelines for defendants. Defendants counterclaimed for crop losses and other damages allegedly due to completion delays and faulty construction. Following a jury trial, judgment was entered in favor of Desert Irrigation on its claims against each defendant. Defendants contend that with respect to each contract, Desert Irrigation was required to prove the value of the services performed and failed to do so. Defendants have appealed from the judgment, asserting error in the trial court’s refusal to grant defendants’ motion for a directed verdict at the end of Desert Irrigation’s case-in-chief and at the close of trial. We affirm in part and reverse in part.

In February, 1976, Desert Irrigation entered into a written contract with defendant, Water User’s Association of the Carl-sen Lateral, to construct an underground irrigation pipeline known as the Carlsen Lateral for the benefit of the Association. The contract recited that the pipeline was to be installed “according to the specifications furnished or to be furnished to [Desert Irrigation] by [the Association] ... said specifications to include all engineering and other requirements as [the Association] may elect.” Mr. Looney, president and owner of Desert Irrigation, testified that the officers of the Association furnished him with specifications and a materials worksheet for the Carlsen Lateral which came from the “A.S. C.S.” office. Mr. Looney testified he furnished the Association with an estimate of the cost of the project, but it was not produced at trial, nor was the amount of it shown by the evidence. He testified further that after the route of the pipeline was staked on the ground some of the defendants and other landowners requested changes in the location of parts of the line and fixtures. These changes were agreed to and approved after the written contract between Desert Irrigation and the Association was signed. The contract did not specify the price for which the work was to be done. It merely said Desert Irrigation was to be paid “a sum not exceeding $25,000.00 for the installation of said pipe line.” The sum of $4,000 was paid in January, 1976, and the balance was to be paid upon completion and “upon submission ... of a final invoice showing the precise amount due, not to exceed $25,000.00 total as aforesaid.”

While work was getting underway on the Carlsen Lateral for the Association, the other defendants, the Tolmies, the Harrises, the Bulgins, and the Callaways, each entered into separate oral agreements with Desert Irrigation for Desert Irrigation to construct underground pipelines leading off of the Carlsen Lateral onto those defendants’ lands. There was no evidence that any of the oral contracts specified the price for the work to be done although Mr. Looney testified he furnished each defendant with an estimate. The written estimate he furnished to the Tolmies was introduced into evidence. After Desert Irrigation finished its work on the various projects, Mr. Looney presented all of the defendants with billings. The Association was billed a total of $25,987.42, with a $4,000 credit for a payment made at the start of construction.1 The Tolmies were billed $3,755.22. The Callaways were billed $1,408.48, less $839 credit given for labor contributed to the project by Mr. Callaway. The Bulgins were [675]*675billed $435.08. The Harrises were billed $3,027.49.

Throughout the trial Desert Irrigation contended it had a contract to construct the Carlsen Lateral for a price of $25,000. Desert Irrigation alleged the price was exceeded because of changes requested by defendants. The defendants contended no set price was agreed to with any of the contracts, but that, in each case, Desert Irrigation was to be paid the reasonable value of the work and services performed up to the maximum of $25,000. At the close of Desert Irrigation’s case-in-chief, and again at the close of all of the evidence, all defendants moved for a directed verdict under I.R.C.P. 50(a), on the ground that Desert Irrigation’s evidence failed to prove the reasonable value of work done for each defendant. The trial court correctly ruled that Desert Irrigation had the burden to show what was furnished both in labor and materials, and what was reasonable as far as the value of the materials and labor furnished. See Traylor v. Henkels & McCoy, Inc., 99 Idaho 560, 562, 585 P.2d 970, 972 (1978); Peavey v. Pellandini, 97 Idaho 655, 659-60, 551 P.2d 610, 614-15 (1976); and Weber v. Eastern Idaho Packing Corp., Inc., 94 Idaho 694, 697, 496 P.2d 693, 696 (1972); overruled on other grounds, Pierson v. Sewell, 97 Idaho 38, 539 P.2d 590 (1975).

In Smith v. Great Basin Grain Co., 98 Idaho 266, 561 P.2d 1299 (1977), the court stated:

On a motion for directed verdict pursuant to I.R.C.P. 50(a) or for judgment notwithstanding the verdict, pursuant to I.R.C.P. 50(b), the moving party admits the truth of the adverse evidence and every inference that may be legitimately drawn therefrom.... Neither motion should be granted if there is substantial evidence to justify submitting the case to the jury or to support the verdict once it has been returned. Barlow v. International Harvester Co., 95 Idaho 881, 886, 522 P.2d 1102, 1107 (1974); Mann v. Safeway Stores, Inc., 95 Idaho 732, 736, 518 P.2d 1194, 1198 (1974).

98 Idaho at 274, 561 P.2d at 1307. See also Curtis v. Dewey, 93 Idaho 847, 848, 475 P.2d 808, 809 (1970). The substantial evidence test requires only that the plaintiff produce “sufficient evidence (not a mere scintilla) from which reasonable minds could conclude that a verdict in favor of the plaintiff was proper.” (Emphasis added.) Gmeiner v. Yacte, 100 Idaho 1, 4, 592 P.2d 57, 60 (1979); Mann v. Safeway Stores, Inc., supra.

Each of the bills submitted to each defendant by Desert Irrigation listed in detail the pipe and fittings billed to that defendant, with a charge for each item or a unit charge. The labor charge for each job was a lump sum figure, which did not disclose the hours worked or the services performed or the hourly rate. There was no explanation given on the billing or at trial how Desert Irrigation computed either the material charges or the labor charges. Desert Irrigation offered no evidence as to what the materials charged to the job actually cost. Mr. Looney denied on cross-examination that such charges represented either his cost or his cost plus a percentage. There was no evidence as to what the labor furnished by Desert Irrigation actually cost Desert Irrigation. During cross-examination of Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Leavitt v. Swain
963 P.2d 1202 (Idaho Court of Appeals, 1998)
Desert Irrigation Co. v. Tolmie
675 P.2d 338 (Idaho Supreme Court, 1983)
Desert Irrigation Co., Inc. v. Tolmie
651 P.2d 938 (Idaho Court of Appeals, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
651 P.2d 938, 103 Idaho 673, Counsel Stack Legal Research, https://law.counselstack.com/opinion/desert-irrigation-co-inc-v-tolmie-idahoctapp-1982.