Dave Kolb Grading, Inc. v. Terra Venture Bridgeton Project Joint-Venture

85 F.3d 351, 1996 U.S. App. LEXIS 13212
CourtCourt of Appeals for the Eighth Circuit
DecidedJune 4, 1996
Docket95-1721
StatusPublished

This text of 85 F.3d 351 (Dave Kolb Grading, Inc. v. Terra Venture Bridgeton Project Joint-Venture) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dave Kolb Grading, Inc. v. Terra Venture Bridgeton Project Joint-Venture, 85 F.3d 351, 1996 U.S. App. LEXIS 13212 (8th Cir. 1996).

Opinion

85 F.3d 351

DAVE KOLB GRADING, INC., Appellant/Cross-Appellee,
v.
TERRA VENTURE BRIDGETON PROJECT JOINT-VENTURE; American
National Insurance Co., a General Partner; Bridgeton
Development Company, a Kansas General Partnership; Jack W.
Isley; L. Gary Turner; Larry D. Ross, Appellees/Cross-Appellants.

Nos. 95-1721, 95-1788.

United States Court of Appeals,
Eighth Circuit.

Submitted Jan. 11, 1996.
Decided June 4, 1996.

Joseph Devereux, argued, Clayton, MO, for appellant/cross-appellee.

Roy Bash, argued, Thomas A. Sheehan, Kansas City, MO, for appellees/cross-appellants.

Before BOWMAN and JOHN R. GIBSON, Circuit Judges, and KYLE,* District Judge.

JOHN R. GIBSON, Circuit Judge.

Dave Kolb Grading, Inc., a grading contractor, appeals from the judgment in its suit against Terra Venture Bridgeton Project Joint-Venture, a real estate developer. Kolb sued to recover money due under a written contract with Terra Venture, as well as additional moneys Kolb claimed were due for extra work it performed on Terra Venture's project. Terra Venture denied liability for the extra work, which it says it did not authorize, and also asserted a set-off claim for costs it incurred in settling a trespass claim that it contends Kolb is responsible for. The magistrate judge1 awarded Kolb the entire amount it had earned under the contract, denying Terra Venture's set-off claim, but also denying Kolb's claim for the extra work. The court awarded Kolb prejudgment interest and attorneys' fees under the contract. Kolb appeals the court's denial of the extra work claim, and Terra Venture cross-appeals the court's award of prejudgment interest and attorneys' fees. We affirm.

Kolb contracted with Terra Venture to do the site excavation and grading for a shopping center in St. Louis County, Missouri. The contract was a "lump sum" contract, meaning that it specified the work Kolb had to do and the total price Terra Venture had to pay (as opposed to, say, payment by the hour). The contract stated that no change order work would be approved or paid for without advance written approval by Terra Venture, in the form of the signatures of Terra Venture's management consultant, E.B. Roberts, and its project manager, Kevin Fitzpatrick.

The contract turned out to be a money-loser for Kolb. The contract called for performance within thirty-five working days, but it actually took Kolb more than 230 days to complete its work. Bad weather caused delays. Terra Venture failed to get timely approvals from municipal and sewer authorities and easements from neighboring landowners. Terra Venture's engineer also made frequent changes in the plans. The delays resulted in Kolb having to do site excavation while other contractors were already building on the site, which made Kolb's job more time consuming.

During the course of Kolb's performance, the parties executed two change orders for additional work by Kolb. The first change order was executed in writing in advance of the work, as required by the contract. Kolb then began a practice of filling out "hourly tickets" for work that its job superintendent, Lee Moorman, considered to be "extra" or beyond the scope of the contract. Moorman submitted these slips to Gene Bunton, who represented Phillips Construction Company, the general building contractor. Bunton had no authority to represent Terra Venture. Kolb then billed Terra Venture for the work represented by the slips. Terra Venture objected that the extra work had not been approved in advance, as the contract required, and at first refused to pay the extra charges. However, Kolb threatened to walk off the job if Terra Venture did not pay the charges, so Kevin Fitzpatrick met with Kolb and agreed to pay a portion of the charges as "change order two." At the meeting, Fitzpatrick warned Kolb that in the future Terra Venture would not pay any extra charges that were not authorized in advance in accordance with the contract.

Nevertheless, after change order two was approved, Kolb continued to do work it considered to be beyond the scope of its contract obligations without getting authorization from Terra Venture. Kolb eventually billed Terra Venture an extra $188,602.13. (The original contract plus change orders one and two amounted to $501,499.10.)

Terra Venture refused to pay for the extra work and also withheld $88,112.81 of the amount due under the contract. Terra Venture had been sued by a neighboring landowner for trespass; Terra Venture claimed that the suit was the result of Kolb's activities on the neighbor's land and relied on a clause in the contract giving it the right to indemnification from any damages arising from Kolb's negligence. Terra Venture eventually agreed to settle the trespass suit for $42,500, although the settlement had not been consummated at the time of the trial in this case, because Terra Venture had not fulfilled its obligations under the settlement agreement.

Kolb sued Terra Venture for the money due under the contract, as well as for the work it claimed was outside the scope of the contract. Terra Venture denied liability for the extra work, but on the first day of trial, offered to pay $38,560.11, which was the amount Terra Venture admittedly owed under the contract, less the settlement amount and expenses for the trespass suit.

The parties tried the case to the court. After Kolb closed its case, the magistrate judge stated that Kolb had failed to put on any evidence that Terra Venture had authorized the extra work. In its rebuttal Kolb called a new witness, Jeff Kolb, whom it had not identified as a potential witness in its pretrial list of witnesses. Kolb's lawyer asked Jeff Kolb:

Q: Well did you have any direct discussions or dealings with Mr. Fitzpatrick regarding authorization to do extra work sir?

A: Yes I did.

Q: Could you define when those occurred and where those occurred?

Terra Venture's lawyer objected that this was improper rebuttal, since Kolb was trying to patch a hole in its case in chief. The court explored the issue thoroughly and concluded that there was prejudice to Terra Venture in letting Jeff Kolb testify when he had never been identified as a potential witness and therefore had never been deposed. The court excluded the rebuttal testimony. Kolb made no offer of proof on the subject of Terra Venture authorizing the additional work.

Since Kolb had failed to prove the extra work was authorized, the court denied its claim for payment beyond the contract amount. The court found that Terra Venture objected to Kolb's practice of billing for extras after it had already done the work, instead of getting advance authorization. The court also found that much of the work Kolb characterized as extra was actually within the scope of its obligations under the lump sum contract, and that much of the work was properly billable to other contractors, rather than to Terra Venture.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Winn-Senter Construction Co. v. Katie Franks, Inc.
816 S.W.2d 943 (Missouri Court of Appeals, 1991)
Julian v. Kiefer
382 S.W.2d 723 (Missouri Court of Appeals, 1964)
Gilmartin Bros., Inc. v. Kern
916 S.W.2d 324 (Missouri Court of Appeals, 1995)
H. B. Deal Construction Co. v. Labor Discount Center, Inc.
418 S.W.2d 940 (Supreme Court of Missouri, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
85 F.3d 351, 1996 U.S. App. LEXIS 13212, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dave-kolb-grading-inc-v-terra-venture-bridgeton-project-joint-venture-ca8-1996.