Old Colony Construction, LLC v. Southington

CourtSupreme Court of Connecticut
DecidedApril 21, 2015
DocketSC19346
StatusPublished

This text of Old Colony Construction, LLC v. Southington (Old Colony Construction, LLC v. Southington) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Old Colony Construction, LLC v. Southington, (Colo. 2015).

Opinion

****************************************************** The ‘‘officially released’’ date that appears near the beginning of each opinion is the date the opinion will be published in the Connecticut Law Journal or the date it was released as a slip opinion. The operative date for the beginning of all time periods for filing postopinion motions and petitions for certification is the ‘‘officially released’’ date appearing in the opinion. In no event will any such motions be accepted before the ‘‘officially released’’ date. All opinions are subject to modification and technical correction prior to official publication in the Connecti- cut Reports and Connecticut Appellate Reports. In the event of discrepancies between the electronic version of an opinion and the print version appearing in the Connecticut Law Journal and subsequently in the Con- necticut Reports or Connecticut Appellate Reports, the latest print version is to be considered authoritative. The syllabus and procedural history accompanying the opinion as it appears on the Commission on Official Legal Publications Electronic Bulletin Board Service and in the Connecticut Law Journal and bound volumes of official reports are copyrighted by the Secretary of the State, State of Connecticut, and may not be repro- duced and distributed without the express written per- mission of the Commission on Official Legal Publications, Judicial Branch, State of Connecticut. ****************************************************** OLD COLONY CONSTRUCTION, LLC v. TOWN OF SOUTHINGTON (SC 19346) Palmer, Eveleigh, McDonald, Robinson and Prescott, Js. Argued December 10, 2014—officially released April 21, 2015

Jared Cohane, with whom were Peter J. Martin and Luke R. Conrad, and, on the brief, Timothy T. Corey, for the appellant (plaintiff). Linda L. Morkan, with whom were Dennis C. Cavan- augh, and, on the brief, Ryan M. Burns, for the appel- lee (defendant). Wendy Kennedy Venoit and Peter J. Zarella filed a brief for the Connecticut Associated Builders and Contractors, Inc., as amicus curiae. Opinion

McDONALD, J. This appeal principally concerns a municipality’s ability to recover liquidated damages for a contractor’s failure to timely complete a public works contract if the municipality has elected to terminate the contract for convenience1 or has contributed to some portion of the delay. The plaintiff, Old Colony Construction, LLC (Old Colony), appeals from the judg- ment of the trial court awarding the defendant, the town of Southington (town), liquidated damages on its counterclaim and permitting the set off of those dam- ages against the damages awarded to Old Colony for the town’s failure to pay sums due under the contract’s termination for convenience provision. Old Colony con- tends that the town is barred from collecting liquidated damages because: (1) termination for convenience pre- cludes any default based remedies available for termina- tion for cause, including liquidated damages; and (2) the town’s contribution to the delay rendered the liquidated damages provision unenforceable under Hartford Elec- tric Applicators of Thermalux, Inc. v. Alden, 169 Conn. 177, 184, 363 A.2d 135 (1975). Old Colony further con- tends that, in light of change orders approved by the town acknowledging Old Colony’s entitlement to addi- tional time for certain delays, it is entitled to an equita- ble adjustment in the contract. The trial court rejected these claims in light of a reservation of the town’s rights and remedies in the termination for convenience provi- sion and contractual mechanisms for obtaining exten- sions of time for delays beyond Old Colony’s control, with which Old Colony had failed to strictly comply. We affirm the trial court’s judgment. The record reveals the following summary of the underlying facts, as found by the trial court or as reflected in the express terms of the parties’ contract. In early 2004, the town sought bids on a construction project known as the Pond View Drive Pump Station Replacement. The project required the demolition of an existing sewer pump station and the construction of a wet well, a pumping station, and an above grade garage. The town received eleven bids on the project, ranging from $912,500 to $1,665,000. By letter dated February 24, 2004, the town awarded the contract to Old Colony for $912,500. Included in the contract docu- ments was a document entitled ‘‘Standard General Con- ditions of the Construction Contract’’ (general conditions), which included, inter alia, provisions con- cerning the contractor’s responsibilities, execution of change orders, and suspension of work and termination. In executing the contract, Old Colony attested that it had examined the work site to ascertain any conditions that could affect performance and had undertaken any supplemental examination or testing necessary to meet the contract’s terms and conditions. Under the express terms of the contract, time was of the essence. The effective date of the contract was April 22, 2004. Substantial completion of the contract was due by January 17, 2005. The contract authorized liquidated damages in the amount of $400 for each day that substantial completion exceeded that date. The contract also provided mechanisms for Old Colony to seek extensions of time and increases in the contract price for delays beyond its control. Such extensions of time could be made only by way of change orders or amendments to the contract, but, unless the parties had agreed to the adjustment, Old Colony was required to file written notice of a claim to the project engineer— the town engineering department—within a specific period and with supporting documentation to obtain the adjustment. From the outset, the project was plagued with delays. Part of the delay stemmed from Old Colony’s misunder- standing as to when the contract time commenced. Old Colony’s first written submittals were more than three months late. Over the course of the project, the project engineer repeatedly brought to Old Colony’s attention the provisions pertaining to contract times, liquidated damages, and the extension of the construction period under specific conditions. In a letter dated November 16, 2004, in response to Old Colony’s complaint that the town had delayed responding to certain submittals and providing certain materials, the town agreed as a compromise to extend the substantial completion date to June 14, 2005. The letter advised: ‘‘[A]ny delay beyond June 14, 2005 will be assessed liquidated damages at $400 per day.’’ Following a May 16, 2005 meeting, the project engineer reiterated this position, advising by letter that ‘‘[o]nly the [t]own [c]ouncil can waive or reduce liquidated damages and only at [the] completion of the project.’’ After the substantial completion date was extended to June 14, 2005, several other problems arose that impacted the schedule. For example, Old Colony dis- covered that contract construction documents did not correctly reflect the location of underground electrical lines and the elevation of the force main for the sewer lines. Old Colony also discovered a caisson for the old pump station in the excavation site that had to be removed, which the town agreed was an unforeseen condition. In each of these instances, the project engi- neer signed off on change orders drafted by Old Colony to address certain costs arising from these circum- stances, which, in describing the change, noted that the impact to the schedule had not been determined and that additional time would be incorporated into the schedule. When the town, however, rejected as unnec- essary Old Colony’s new proposal for a temporary bypass system in lieu of a previously accepted proposal, it advised Old Colony by letter that it was not agreeing to any substantial change in the original contract as to time or costs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lisbon Contractors, Inc. v. The United States
828 F.2d 759 (Federal Circuit, 1987)
Krygoski Construction Company, Inc. v. United States
94 F.3d 1537 (Federal Circuit, 1996)
Tupelo Redevelopment Agency v. Gray Corp.
972 So. 2d 495 (Mississippi Supreme Court, 2007)
M.J. Paquet, Inc. v. New Jersey Department of Transportation
794 A.2d 141 (Supreme Court of New Jersey, 2002)
Isham v. Isham
972 A.2d 228 (Supreme Court of Connecticut, 2009)
Glynn v. City of Gloucester
401 N.E.2d 886 (Massachusetts Appeals Court, 1980)
Washington Metropolitan Area Transit Authority v. Nello L. Teer Co.
618 A.2d 128 (District of Columbia Court of Appeals, 1992)
Norwalk Door Closer Co. v. Eagle Lock & Screw Co.
220 A.2d 263 (Supreme Court of Connecticut, 1966)
Hartford Electric Applicators of Thermalux, Inc. v. Alden
363 A.2d 135 (Supreme Court of Connecticut, 1975)
Town of Plainfield v. Paden Engineering Co.
943 N.E.2d 904 (Indiana Court of Appeals, 2011)
Mosler Safe Co. v. Maiden Lane Safe Deposit Co.
93 N.E. 81 (New York Court of Appeals, 1910)
Paragon Restoration Group, Inc. v. Cambridge Square Condominiums
42 A.D.3d 905 (Appellate Division of the Supreme Court of New York, 2007)
In re the Arbitration between Niagara Frontier Transportation Authority & Computer Sciences Corp.
209 A.D.2d 1009 (Appellate Division of the Supreme Court of New York, 1994)
Tishman Construction Corp. v. City of New York
228 A.D.2d 292 (Appellate Division of the Supreme Court of New York, 1996)
Sutton Corp. v. Metropolitan District Commission
667 N.E.2d 838 (Massachusetts Supreme Judicial Court, 1996)
Skopek Bros. v. Webster Housing Authority
416 N.E.2d 1006 (Massachusetts Appeals Court, 1981)
Litton Industries Credit Corp. v. Catanuto
394 A.2d 191 (Supreme Court of Connecticut, 1978)
United Partition Systems, Inc. v. United States
90 Fed. Cl. 74 (Federal Claims, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
Old Colony Construction, LLC v. Southington, Counsel Stack Legal Research, https://law.counselstack.com/opinion/old-colony-construction-llc-v-southington-conn-2015.