Cas Construction Co. v. East Hartford, No. Cv-98-0087320-S (May 1, 2002)

2002 Conn. Super. Ct. 5614
CourtConnecticut Superior Court
DecidedMay 1, 2002
DocketNo. CV-98-0087320-S
StatusUnpublished

This text of 2002 Conn. Super. Ct. 5614 (Cas Construction Co. v. East Hartford, No. Cv-98-0087320-S (May 1, 2002)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cas Construction Co. v. East Hartford, No. Cv-98-0087320-S (May 1, 2002), 2002 Conn. Super. Ct. 5614 (Colo. Ct. App. 2002).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]

MEMORANDUM OF DECISION
In its second amended complaint, dated October 2, 2000, the plaintiff, in Three Counts, alleges; in Count One, Breach of Contract, in Count Two, non-payment for extra work, and in Count three, delays to contract performance.

On October 16, 2000, the defendant filed its Answer and Special Defenses alleging; in its First Special Defense, failure to provide proper invoices required under the contract, in its Second Special Defense, actions of the plaintiff resulting in delays, in its Third Special Defense, no obligation to pay sub-contractors, in its Fourth Special Defense, lack of certified statement as to items completed, and, in its fifth special defense, failure to pay sub-contractors from proceeds paid by defendant.

On October 18, 2000, the plaintiff filed its Reply denying the defendant's Special Defenses.

The issues having been joined, trial was had to the court.

The parties having been heard, the court, by a preponderance of the credible, relevant, reliable and legally admissible evidence and the reasonable, logical, rational and lawful inferences to be drawn therefrom finds, determines and rules as follows.

On May 21, 1997, the plaintiff, CAS Construction Company, Inc. and the defendant, Town of East Hartford, entered into a written contract for CT Page 5615 work to be known as the Forest Street Reconstruction Project (Project). The project, which was funded by the Connecticut Department of Transportation, consisted of removing the top layer of Forest Street, removing and replacing the existing storm drainage systems and repairing the roadway and curbs.

The court finds that the plaintiff cannot prevail on its Third Count claiming that the defendant caused delays in the plaintiff's ability to perform the contract in a timely manner. To begin with, the plaintiff did substantially complete the project in the 240 days allotted under the contract. Further, the delay in the signing of the contract was caused by the plaintiff's error on its bid. To correct this error required approval by the state which was attained on May 6, 1997. Had the plaintiff not erred in its bid, no such state approval would have been necessary. The error consisted of the plaintiff submitting a bid item where the numerical number did not correspond to the written numbers. The written number, if adopted, would have deducted $47,012.00 from the plaintiff's bid. The plaintiff benefitted from the action of the defendant in that the bid was awarded despite the error and the plaintiff was not held to the lower written number.

Further, in closing down the project for the winter, the defendant acted properly and in accordance with the rules and procedures authorizing a winter closure.

Judgment on the Third Count should enter for the defendant.

The parties have fashioned their briefs in accordance with Exhibit 6 as an index of their respective claims, defenses and argument. The court will follow the format and rules on the claims as so presented.

Initially, the court notes that the contract between the parties is a unit price contract. In a unit price contract the contractor's bid is not determined as a single overall price, but the bid is an accumulation of the costs for each unit item to be installed, the submitted bid being subsequently determined by the number of such units required under the bid specifications and to be installed by the contractor. See MaskelConstruction Company v. Glastonbury, 158 Conn. 592-4 (1969).

Because the work to be performed was to be funded by the State Department of Transportation (DOT) the defendant was required to inspect the work as it progressed and to measure and count exact quantities of work for each line item of the contract, whether it was material, e.g., pipe, fill, sod, etc. installed or used, man hours worked, e.g., police officers, traffic signalmen, etc. or safety items used, e.g. cones, barrels, lights, etc. CT Page 5616

Gilles Bellot, an employee of Barakos Landino, an engineering/consulting firm that the defendant engaged to inspect the work, was the designated inspector assigned to the instant project. Mr. Bellot is a civil engineer with 17 years experience in the field. His duty was to, each day, inspect the work done by the plaintiff, measure quantities, traffic control personal used, and note the measures taken by the plaintiff in utilizing safety items as required under the contract.

The plaintiff was unable to complete road excavation, pipe installation and paving before the start of the winter season.

On November 24, 1997, the defendant notified the plaintiff that it was necessary to suspend work on the project for the winter and that the project was to be re-started no later than April 1, 1998 and that the time between November 24, 1997 and April 1, 1998 would not be charged against the contract time for completion of 240 days.

The court expressly finds that the defendant's actions in closing the project during the winter period was proper and justified. See above where the court ruled on Count Three of the plaintiff's complaint.

As indicated above, the court will rule on the plaintiff's claims with reference to plaintiff's Exhibit 6, which confirms to the pattern adopted by both the plaintiff and the defendant in their Briefs.

The court further notes that the defendant's inspector fully performed his inspection duties in a thorough and workmanlike manner. His reports are meticulous, complete and may confidently be relied upon.

The plaintiff on the other hand, through its principal, Mr. Coons, although requested, did not provide to the Town documentation that was required under the contract by reference to the DOT's regulations concerning a unit price contract. Many of Mr. Coons claims were speculative and subjective on his part. The court requires objective, tangible evidence from which it can conclude the extent of damages, if any. See Bronson Townsend Co. v. Battistoni,, 167 Conn. 321, 326-327.

Items 1, 6, 7 and 8. Gas main obstruction.

The plaintiff's claim that for these items it is owed $13,025.56.

These items became necessary when during the course of excavation the plaintiff encountered a gas main that partially blocked the installation of Reinforced Concrete Pipe (RCP). The problem was solved by the installation of polyvinyl chloride pipe (PVC) which was thinner than RCP CT Page 5617 pipe and would fit under the gas main. Such substitution is an acceptable alternative under the circumstances. However, there was no line item in the contract for PVC pipe. Where there is no line item, according to DOT regulations, particularly form 814A, the contractor is to submit a detailed price proposal to complete the extra work for the Town to review. The Town may accept the price proposal or order the work to be completed on a cost-plus basis. Once a decision has been made as to payment, the work will be authorized by a construction change order.

As to these items, the court expressly finds that the defendant has paid for all the work and its only obligation is to pay for the added cost, if any, of the PVC pipe over the RCP pipe. But, again, the plaintiff did not offer any documented proof but relied on its subjective and speculative opinion as to cost.

The court expressly finds that the plaintiff has failed to prove its claims under items 1, 6, 7 8.

Item 2. Enlarging ports on existing structure.

While excavating an area of Oak Street, the plaintiff encountered an underground structure in the nature of a large catch basin.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bronson & Townsend Co. v. Battistoni
355 A.2d 299 (Supreme Court of Connecticut, 1974)
Maskel Construction Co. v. Town of Glastonbury
264 A.2d 557 (Supreme Court of Connecticut, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
2002 Conn. Super. Ct. 5614, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cas-construction-co-v-east-hartford-no-cv-98-0087320-s-may-1-2002-connsuperct-2002.