Empire Paving, Inc. v. City of Milford, No. Cv-94-0362457s (Mar. 3, 1998)

1998 Conn. Super. Ct. 2687
CourtConnecticut Superior Court
DecidedMarch 3, 1998
DocketNo. CV-94-0362457S
StatusUnpublished

This text of 1998 Conn. Super. Ct. 2687 (Empire Paving, Inc. v. City of Milford, No. Cv-94-0362457s (Mar. 3, 1998)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Empire Paving, Inc. v. City of Milford, No. Cv-94-0362457s (Mar. 3, 1998), 1998 Conn. Super. Ct. 2687 (Colo. Ct. App. 1998).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]MEMORANDUM OF DECISION I

This is a contract dispute. In December, 1991, the parties entered into an agreement whereby the plaintiff undertook sewer line repairs and installation and road repairs on various streets in the City of Milford. The project was a considerable one, involving construction of some 6500 feet of sanitary sewers at a bid price of $677,801.00, based on unit or lump sum prices. Metcalf and Eddy ("M E"), an engineering firm, was named Engineer for the project.

The plaintiff substantially completed its work under the contract by May, 1993, and the defendant has paid for all work completed with the exception of the items contested in these proceedings.

II
Plaintiff's Amended Complaint is in two counts. The first count alleges breach of contract by the defendant; the second count, unjust enrichment. At issue are six requests for change order by plaintiff which defendant disallowed in whole or in part. These six requests for change order are numbered #2, #5, #8, #9, #10 and #11. Claims #2 and #10 may be considered together, as may claims #5 and #9.

III
Plaintiff's request for change order #11 was for extra work required to repair two damaged curb areas in the vicinity of the intersection of Maple and Meadow Streets. The claim is in the amount of $536.00. Defendant has refused to pay this claim, alleging that the curb damage was caused by the plaintiff. Mr. Sterback, assigned as an observer for the City of Milford's engineering department, testified he observed plaintiff's equipment damage one of the areas in question. (Exhibit R). Plaintiff's vice president, Mr. Tucker, testified as to his belief that the curb damage was caused by the gas company installing laterals. Plaintiff was unable to establish it was not responsible for said damage and the court will disallow this claim. CT Page 2689

IV
Requests for change order numbers #2 and #10 have to do with claims by plaintiff for additional costs incurred in saw cutting pavement. Request #2, dated February 18, 1992, claims an amount of $20,991.18 for 9,752 linear feet of "Extra Depth" saw cutting. Request #10, dated July 7, 1992, claims an amount of $19,211.46 for another 4,744 linear feet. In putting together its bid, plaintiffs anticipated using a "pizza wheel" cutter at a cost of $.20 per linear foot. Plaintiffs relied on certain data in the bid documents (eleven boring logs) which indicated a pavement depth of .1 or .2 feet. On beginning work plaintiff encountered pavement thickness ranging from .4 to .6 feet. This required substitution of a "road saw cutter" for the "pizza wheel", at a cost of $2.25 per linear foot. Defendant's engineers, M E, denied both requests in their entirety, citing provisions of the contract.

Section IB.6 BIDDERS TO INVESTIGATE provides that:

Bidders must satisfy themselves by personal examination of the site of the work and by such other means as they may wish, as to the actual conditions there existing, the character and requirements of the work, the difficulties attendant upon its execution, and the accuracy of all estimated quantities stated in the bid.

Section IB.7 INFORMATION NOT GUARANTEED states in pertinent part:

All information given on the Drawings or in the other Contract Documents relating to subsurface and other conditions . . . is from the best sources at present available to the Owner. All such information is furnished only for the information and convenience of bidders and is not guaranteed.

It is agreed and understood that the Owner does not warrant or guarantee that the subsurface or other conditions . . . will be the same as those indicated on the Drawings or in the other Contract Documents.

It is further . . . understood . . . that no bidder or contractor shall use or be entitled to use any of the information made available to him or obtained in any examination made by him in any manner as a basis of or ground for any claim or CT Page 2690 demand against the Owner . . . arising from or by reason of any variance which may exist between the information made available and the actual subsurface or other conditions . . . actually encountered during the construction work . . .

Further, in Section B Bid, pp. B1 and B2 the plaintiff declares:

(5) he understands that information relative to subsurface and other conditions . . . has been furnished only for his information and convenience without any warranty or guarantee, express or implied, that the subsurface and/or other conditions . . . actually encountered will be the same as those shown on the Drawings or in any of the other Contract Documents and he agrees that he shall not use or be entitled to use any such information . . . as a basis of or ground for any claim against the Owner . . . arising from or by reason of any variance which may exist between the aforesaid information made available or acquired by him and the subsurface and/or other conditions . . . actually encountered during construction work, and he has made due allowance therefor in this BID . . .

In the face of these contract provisions the plaintiff's claim must fail. A court must enforce the contract as drafted by the parties and may not relieve a contracting party from anticipated or actual difficulties undertaken pursuant to the contract, unless the contract is voidable on grounds such as mistake, fraud or unconscionability (citations omitted), HollyHill Holdings v. Lowman, 226 Conn. 748, 756. The plaintiff has failed to establish such grounds here.

As to plaintiff's argument that "Everyone relies on the info provided by the City", Maskel Construction Co. v. Glastonbury,158 Conn. 592, is dispositive. In Maskel the plaintiff sought compensation for what it claimed was due it for services and materials under a sewer construction contract. The trial court found that it was the custom in the trade for an owner or a municipality to be charged the extra costs arising out of "conflicts" (situations where what is actually found in the ground differs from what is shown on the map or plans). Our supreme court, finding no factual basis to support the trial court's decision, went on to say: "Even if the existence of such a custom in the sewer construction trade had been approved, it nevertheless could not have varied the specific terms of the contract, Maskel Construction Co. v. Glastonbury, supra, at 596. CT Page 2691 Plaintiff's claim of "unforeseen circumstances" must fail. Plaintiff cites Dills v. Enfield, 210 Conn. 705, in support of his claim. But Dills stresses that "only in the most exceptional circumstances have courts concluded that a duty is discharged because additional financial burdens make performance less practicable than initially contemplated." Dills v. Enfield, supra, at 717. The Dills court goes on to make the critical distinction: "If an event is foreseeable a party who makes an unqualified promise to perform necessarily assumes an obligation to perform even if the occurrence of the event makes performance impracticable." Thus, an event must be not only unforeseen, but unforseeable. Such was not the case here: the possibility of a variance in thickness of the pavement was clearly contemplated in the cited contract provisions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Maskel Construction Co. v. Town of Glastonbury
264 A.2d 557 (Supreme Court of Connecticut, 1969)
Providence Electric Co. v. Sutton Place, Inc.
287 A.2d 379 (Supreme Court of Connecticut, 1971)
Dills v. Town of Enfield
557 A.2d 517 (Supreme Court of Connecticut, 1989)
John T. Brady & Co. v. City of Stamford
599 A.2d 370 (Supreme Court of Connecticut, 1991)
Holly Hill Holdings v. Lowman
628 A.2d 1298 (Supreme Court of Connecticut, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
1998 Conn. Super. Ct. 2687, Counsel Stack Legal Research, https://law.counselstack.com/opinion/empire-paving-inc-v-city-of-milford-no-cv-94-0362457s-mar-3-1998-connsuperct-1998.