Dills v. Town of Enfield

557 A.2d 517, 210 Conn. 705, 1989 Conn. LEXIS 103
CourtSupreme Court of Connecticut
DecidedApril 18, 1989
Docket13533
StatusPublished
Cited by164 cases

This text of 557 A.2d 517 (Dills v. Town of Enfield) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dills v. Town of Enfield, 557 A.2d 517, 210 Conn. 705, 1989 Conn. LEXIS 103 (Colo. 1989).

Opinion

Peters, C. J.

The principal issue in this appeal is whether the doctrine of commercial impracticability excuses a developer from submitting construction plans when he discovers that necessary financing has become unavailable. The plaintiffs, Timothy E. Dills and the Neecon Corporation, sued the defendants, the town of Enfield (town) and the Enfield development agency (agency), to recover a $100,000 deposit Dills had paid the agency under an option and contract for sale. The trial court referred the case to Attorney J. Read Murphy, a state trial referee appointed pursuant to General Statutes § 52-434 (a) (4). Following a hearing and the parties’ submission of briefs, the referee reported his findings of fact and recommended that judgment enter for the plaintiffs. The trial court rejected the referee’s recommendation, instead rendering judgment for the defendants. The plaintiff Neecon Corporation appealed to the Appellate Court and we transferred the case here pursuant to Practice Book § 4023. We find no error.

The relevant facts reported by the referee, accepted by the trial court and supported by the record are as [707]*707follows. The town of Enfield instructed its development agency to solicit private developers for the Enfield Memorial Industrial Park to be constructed on town property. Pursuant to an earlier option agreement, on May 1, 1974, the plaintiff Dills and the development agency entered into a contract for the sale of the land to be developed. Dills at that time paid a $100,000 deposit toward the contract price of $985,900. The plaintiff Neecon Corporation, owned by Dills, was to perform the necessary work, and has become, by virtue of an assignment from Dills, the only remaining plaintiff in this appeal.

Under the terms of the contract, the development agency agreed to convey the property to the developer sixty days after the fulfillment of two conditions: (1) the submission and approval of construction plans in accordance with section 301 of the contract;1 and (2) [708]*708the submission of evidence of financial capacity in accordance with section 304 of the contract.2 The contract also included provisions for its termination by either party. Section 702 (b) of the contract allowed the developer to withdraw and to reclaim his deposit if, after the preparation of construction plans satisfactory to the agency, the developer could not obtain the necessary mortgage financing.3 Section 703 (b) of the contract allowed the agency to terminate the contract, retaining the deposit as liquidated damages, if the developer failed to submit acceptable construction plans.4

[709]*709Dills never submitted construction plans that were acceptable to the agency. A set of plans denominated “preliminary” was rejected by the agency on June 24, 1974. The agency accepted a revised set of “preliminary plans” and drawings three months later, but demanded the submission of full construction plans and specifications by early December. The referee found that the preliminary sets of plans did not themselves meet the definition of “construction plans” in section 301.5 The referee agreed with the agency’s interpretation of section 301 of the contract as requiring the developer to submit full construction plans within 210 days of the agency’s approval of preliminary plans.

The reason Dills failed to submit construction plans was that, despite diligent efforts, he was unable to obtain mortgage financing. Thereafter, both parties attempted, with proper notification, to invoke the contract’s termination clauses. On December 19, 1974, the agency, having been informed by Dills of his financial difficulties, voted to terminate the agreement pursuant to section 703 (b) of the contract of sale and to retain the $100,000 deposit as liquidated damages.6 On [710]*710December 22,1974, Dills’ attorney notified the agency that, because of Dills’ inability to obtain financing within the time specified in the contract,7 Dills was terminating the agreement pursuant to section 702 (b) of the contract of sale.

In the referee’s view, although Dills had never submitted anything more than “preliminary plans,” the fact that he could not obtain financing had become evident and “[t]he costly rendition of detailed drawings and specifications which were part of the Construction Plans thus became a useless act.” He concluded, therefore, that “[t]he duty of [Dills] to provide full Construction Plans by December, 1974 was discharged by supervening impracticability.” Accordingly, he recommended that the plaintiffs recover their $100,000 deposit.

After unsuccessful efforts to persuade the referee to make material changes in his report, the defendants moved the trial court, pursuant to Practice Book § 440, to reject the report and refer the case to another referee for a new trial, or to revoke the reference and leave the case to be disposed of in court. Alternatively, the defendants took exception in the trial court to the referee’s report and findings of fact and moved the court, pursuant to Practice Book § 439, to grant the corrections they had proposed in their motion to correct and to strike the corrections granted at the plaintiff’s request.

On July 14, 1988, the trial court issued its decision rejecting the referee’s recommendation that judgment enter for the plaintiffs. The court accepted the referee’s findings that the plans submitted by Dills were preliminary plans but not construction plans as defined by [711]*711the contract. It also accepted the finding that Dills had unsuccessfully engaged in “diligent efforts” to secure financing. Reviewing the history of the contract negotiations between the parties, the court held that the defendants were entitled to judgment. The court noted that the town had been concerned about the developer’s reliability because an earlier option agreement between Dills and the town, concerning this same property, had failed to come to fruition. In response, Dills had publicly assured the town “that he was going to be putting $250,000 on the line,” the contemplated cost of preparing the construction plans. Because the various contract provisions, including the furnishing of construction plans, had been bargained for, the court concluded that Dills could not invoke the doctrine of impracticability in this case. Absent a showing of the impracticability of preparing and submitting construction plans, the court held that “the facts found by the attorney-referee can only lead to one conclusion,” i.e., judgment for the defendants.

After the trial court denied the plaintiffs’ motion for reconsideration,8 the plaintiff Neecon took the present appeal. It claims that the trial court erred in (1) rendering judgment for the defendants, rather than either rendering judgment for the plaintiffs or revoking the reference to the attorney state trial referee and remanding the case for further findings by an appropriate factfinder, and (2) finding facts not found by the [712]*712attorney state trial referee. We conclude that the trial court did not err either procedurally or substantively.

I

In its procedural attack on the trial court’s judgment, the plaintiff proceeds from the premise that reference of a case to an attorney trial referee necessarily limits the subsequent authority of the trial court to address issues of law.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vibo Construction, Inc. v. Friedman, No. Cv 97-0157328 S (Apr. 24, 2002)
2002 Conn. Super. Ct. 5438 (Connecticut Superior Court, 2002)
McMahon v. New London County, No. Cv 98-0408032 (Aug. 23, 1999)
1999 Conn. Super. Ct. 11872 (Connecticut Superior Court, 1999)
Kubish v. Zega, No. Cv97-0075105s (May 19, 1999)
1999 Conn. Super. Ct. 5541 (Connecticut Superior Court, 1999)
Olsen v. Weiss, No. 536688 (Jul. 20, 1998)
1998 Conn. Super. Ct. 8550 (Connecticut Superior Court, 1998)
Atlantic Mutual Insurance Co. v. Altena, No. Cv 97 0158703 (Apr. 30, 1998)
1998 Conn. Super. Ct. 5249 (Connecticut Superior Court, 1998)
Paulus v. Lasala, No. Cv 87 0089213 (Apr. 24, 1998)
1998 Conn. Super. Ct. 5005 (Connecticut Superior Court, 1998)
Victory v. Morris Construction Co., No. Cv 96 0152254 (Apr. 7, 1998)
1998 Conn. Super. Ct. 4942 (Connecticut Superior Court, 1998)
Empire Paving, Inc. v. City of Milford, No. Cv-94-0362457s (Mar. 3, 1998)
1998 Conn. Super. Ct. 2687 (Connecticut Superior Court, 1998)
Paulus v. Lasala, No. Cv 87 0089213 (Jan. 20, 1998)
1998 Conn. Super. Ct. 844 (Connecticut Superior Court, 1998)
Teachers Ins. v. Broad Hanranhan, No. Cv93 0132304 S (Dec. 12, 1997)
1997 Conn. Super. Ct. 14018 (Connecticut Superior Court, 1997)
New England Rock Serv. v. Empire Paving, Inc., No. 540878 (Oct. 31, 1997)
1997 Conn. Super. Ct. 10976 (Connecticut Superior Court, 1997)
Khan v. Ct Home Inspection Service, No. 32 30 76 (Oct. 17, 1997)
1997 Conn. Super. Ct. 10558 (Connecticut Superior Court, 1997)
nemeth/martin Personnel Cons. v. Blake Equip., No. 31 37 75 (Jun. 11, 1997)
1997 Conn. Super. Ct. 7022 (Connecticut Superior Court, 1997)
Nordmann v. Risoli, No. Cv90 0110297 S (Apr. 25, 1997)
1997 Conn. Super. Ct. 4571 (Connecticut Superior Court, 1997)
Littas v. Burrows, No. Cvno 93092710 (Nov. 27, 1996)
1996 Conn. Super. Ct. 6379 (Connecticut Superior Court, 1996)
Poughkeepsie Shg. v. Bd. of Tax Rev., No. Cv93 030 51 23 S (Jul. 19, 1996)
1996 Conn. Super. Ct. 5123-OO (Connecticut Superior Court, 1996)
United Illuminating Co. v. Hi-Ho Mall, No. Cv93 030 86 79 S (Jul. 12, 1996)
1996 Conn. Super. Ct. 5163-N (Connecticut Superior Court, 1996)
Wright Brothers Builders, Inc. v. Dowling, No. Cv 940136604 (Jun. 26, 1996)
1996 Conn. Super. Ct. 5020 (Connecticut Superior Court, 1996)
Kallas v. Harnen, No. 30 36 11 (May 10, 1996)
1996 Conn. Super. Ct. 4186-VV (Connecticut Superior Court, 1996)
Tds Painting Rest. v. Copper Beach Farm, No. Cv 92 0124488 (Mar. 4, 1996)
1996 Conn. Super. Ct. 1720 (Connecticut Superior Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
557 A.2d 517, 210 Conn. 705, 1989 Conn. LEXIS 103, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dills-v-town-of-enfield-conn-1989.