Paulus v. Lasala, No. Cv 87 0089213 (Jan. 20, 1998)

1998 Conn. Super. Ct. 844
CourtConnecticut Superior Court
DecidedJanuary 20, 1998
DocketNo. CV 87 0089213
StatusUnpublished

This text of 1998 Conn. Super. Ct. 844 (Paulus v. Lasala, No. Cv 87 0089213 (Jan. 20, 1998)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Paulus v. Lasala, No. Cv 87 0089213 (Jan. 20, 1998), 1998 Conn. Super. Ct. 844 (Colo. Ct. App. 1998).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]MEMORANDUM OF DECISION This case involves a dispute between homeowners and their builder. On April 14, 1986, the plaintiffs, John D. Paulus and Carol Paulus, of Wilton, entered into a written contract with the defendant, Cannondale Development Associates (Cannondale), a Connecticut partnership acting by the defendant, Andrew LaSala, Jr., a general partner. Cannondale and LaSala are hereafter referred to as the defendants.

The plaintiffs allege in the first count of their amended complaint dated October 6, 1988, that their signed agreement provided that the defendants would construct a new single family dwelling at 39 Wick End Lane, in Wilton, and convey that property to the plaintiffs for $834,000. The plaintiffs further claim, among other things, that they are entitled to a daily penalty because the work was not completed by January 15, 1987, as agreed to in the contract. Further, the plaintiffs allege that the construction was not performed in a workmanlike manner; that the defendants breached their one year contractual warranties regarding workmanship and a dry basement;1 that the defendants overcharged them and performed unauthorized work; and that at the closing on May 5, 1987, in addition to receiving the contract price, the defendants refused to convey title until they received an extra $19,388. The plaintiffs claim that they paid this money under duress.

In the second count of the complaint, the plaintiffs claim that defendant LaSala represented that he would work with an experienced builder, but did not do so; that Cannondale never filed a fictitious trade name certificate in violation of General Statutes § 35-12; that the plaintiffs had agreed to pay $834,000 for the land and house, but the defendants demanded and received an additional $19,388; and that the defendants' conduct violated General Statutes § 42-110 (b) et seq., the Connecticut Unfair Trade Practices Act (CUTPA). The plaintiffs CT Page 845 allege in the third count of their complaint that the defendants violated General Statutes § 47-116 et seq., the New Home Warranties Act3, by constructing a home with a number of defects.

The defendants, in their revised answer of April 6, 1994, deny the material allegations of the complaint and deny that they owe any money to the plaintiffs. The defendants also filed seven special defenses. The first special defense states that if the plaintiffs sustained water damage to their basement as they claimed, it was due to the fault and neglect of the swimming pool contractor. The defendants contend in the second special defense that the delay in closing was due to requests by the plaintiffs to modify and change the contract. The defendants claim in the third defense that the plaintiffs accepted the deed and took possession of the subject premises. Therefore, according to the defendants, the plaintiffs are not entitled to any recovery because of "waiver, estoppel and merger." In the fourth special defense, the defendants claim that the plaintiffs accepted all the changes to the contract and paid for all such changes, and are not entitled to any recovery. The defendants contend in their fifth special defense that the plaintiffs are estopped from claiming breaches of warranties because they never gave the defendants the opportunity to inspect and/or cure the alleged defects. In the sixth special defense, the defendants allege that the plaintiffs prevented the defendants from completing the work. In the seventh special defense, the defendants claim that the plaintiffs failed to mitigate damages.

The case was referred to an attorney trial referee, Attorney Michael T. Bologna, in accordance with General Statutes §52-434 (a) and Practice Book § 428 et seq. The referee conducted a trial, and thereafter submitted a report finding the following facts: (1) the defendants obtained a certificate of occupancy in May of 1987 and the closing occurred on May 20, 1987; (2) at the closing, $9,500 was held in escrow until the defendants could complete some items and this money was eventually turned over to the defendants in August of 1987; (3) the work was not performed by the defendants in a workmanlike or timely manner, and the plaintiffs were therefore obliged to hire others to complete the construction in a number of respects including: (a) the front and rear sidewalks . . . $5,869; (b) rough grading . . . $1,500; (c) topsoil . . . $5,000; (d) driveway paving . . . $17,000; (e) addition of Belgian blocks . . . $6,000; (f) family room cabinets . . . $2,400; (g) CT Page 846 cleaning of windows . . . $665; (h) skylight . . . $1,500; (i) water in the basement . . . $6,930; and (j) sanding, scraping and repainting the exterior . . $23,975; (4) the plaintiffs were entitled to legal fees totaling $5,420 because of the delayed closing; (5) the plaintiffs could not recover the $18,600 paid at the closing because they had an option to refuse to make such payment but nevertheless paid the money; (6) the plaintiffs were not authorized to add $5,607 for alleged overcharging because these funds were included in the $18,600 paid at the closing; and (7) the plaintiffs were not entitled to damages for the cost of repitching the rear patio because the defendants only did this work after a disclaimer of any liability or responsibility.

The attorney trial referee concluded, on the basis of the above findings of fact, that: (1) the defendants had breached the contract with the plaintiffs which obligated the defendants to construct the new house in a workmanlike and timely fashion: (2) the exterior painting performed by the defendants also breached the New Home Warranties Act; (3) the defendants' conduct had not violated CUTPA; and (4) the total cost of the damages suffered by the plaintiffs is $82,619, minus the $9,500 they had received previously from the escrow account.

Thus, the attorney trial referee found for the plaintiffs and recommended that they recover from the defendants $73,119, but without prejudgment interest under General Statutes § 37-3a, or CUTPA damages.

Pursuant to Practice Book § 438, the plaintiffs moved to correct the referee's report4 in several respects: (1) the referee improperly denied recovery of the $18,600 because the demand for this money was unjustified and exceeded the money due pursuant to the contract; (2) the referee improperly denied damages for correcting the pitch of the rear patios; (3) they seek to recover for overcharging by the defendants in the amount of $5,607 for various items; and (4) the plaintiffs reiterate their demand for prejudgment interest.

The referee, in response to this motion to correct, declined to change his conclusions and recommendations other than his decision to deny prejudgment interest. The referee found that the plaintiffs were entitled to General Statutes § 37-3a prejudgment interest on $38,424. This amount represents the amount of their damages for breach of contract based on poor workmanship. According to the referee, interest would begin on CT Page 847 July 6, 1987, when the defendants announced that they would do no further work at the subject premises, and terminate on April 28, 1993, the beginning of the trial of this action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ferris v. State
735 A.2d 491 (Court of Appeals of Maryland, 1999)
Nor'easter Group, Inc. v. Colossale Concrete, Inc.
542 A.2d 692 (Supreme Court of Connecticut, 1988)
Dills v. Town of Enfield
557 A.2d 517 (Supreme Court of Connecticut, 1989)
Argentinis v. Gould
592 A.2d 378 (Supreme Court of Connecticut, 1991)
Elgar v. Elgar
679 A.2d 937 (Supreme Court of Connecticut, 1996)
Blakeslee Arpaia Chapman, Inc. v. EI Constructors, Inc.
687 A.2d 506 (Supreme Court of Connecticut, 1997)
Bernard v. Gershman
559 A.2d 1171 (Connecticut Appellate Court, 1989)
Wilcox Trucking, Inc. v. Mansour Builders, Inc.
567 A.2d 1250 (Connecticut Appellate Court, 1989)
Argentinis v. Gould
579 A.2d 1078 (Connecticut Appellate Court, 1990)
Thermoglaze, Inc. v. Morningside Gardens Co.
583 A.2d 1331 (Connecticut Appellate Court, 1991)
Beizer v. Goepfert
613 A.2d 1336 (Connecticut Appellate Court, 1992)
State Bank v. New Dimension Homes of Connecticut, Inc.
661 A.2d 119 (Connecticut Appellate Court, 1995)
Spearhead Construction Corp. v. Bianco
665 A.2d 86 (Connecticut Appellate Court, 1995)
Foley v. Huntington Co.
682 A.2d 1026 (Connecticut Appellate Court, 1996)
Iroquois Gas Transmission System v. Mileski
682 A.2d 140 (Connecticut Appellate Court, 1996)
Aunyx Corp. v. Canon U. S. A., Inc.
507 U.S. 973 (Supreme Court, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
1998 Conn. Super. Ct. 844, Counsel Stack Legal Research, https://law.counselstack.com/opinion/paulus-v-lasala-no-cv-87-0089213-jan-20-1998-connsuperct-1998.