Nor'easter Group, Inc. v. Colossale Concrete, Inc.

542 A.2d 692, 207 Conn. 468, 1988 Conn. LEXIS 122
CourtSupreme Court of Connecticut
DecidedMay 17, 1988
Docket13291
StatusPublished
Cited by134 cases

This text of 542 A.2d 692 (Nor'easter Group, Inc. v. Colossale Concrete, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nor'easter Group, Inc. v. Colossale Concrete, Inc., 542 A.2d 692, 207 Conn. 468, 1988 Conn. LEXIS 122 (Colo. 1988).

Opinion

Callahan, J.

This is a contract action brought pursuant to General Statutes § 49-421 by the plaintiff, The [470]*470Nor’easter Group, Inc. (Nor’easter), a subcontractor, to recover a balance due for labor and material furnished in the construction of a municipal swimming pool for the city of Torrington. The action was brought on a payment bond against Colossale Concrete, Inc. (Colossale), the general contractor and principal on the bond, and the Continental Casualty Co. (Continental), the surety.

Colossale, as general contractor, built the pool pursuant to a contract with the city of Torrington. Pursuant to an agreement with the defendant Colossale, the plaintiff, a swimming pool contractor, was to supply the labor and material for the installation of a stainless steel overflow system, drain piping, and forms for a gutter groove channel in connection with the pool construction. In conformity with General Statutes § 49-41 2 [471]*471the defendant Colossale, as principal, and the defendant Continental, as surety, furnished a bond in the amount of $230,000 guaranteeing payment to subcontractors supplying labor and material to the project.

The plaintiff alleged that it had performed labor and furnished material for the pool project commencing in October, 1982, and terminating in July, 1984. At trial, through its president, Walter Liff, the plaintiff offered evidence that it had properly completed its portion of the Torrington pool contract and that there remained a balance due it of $25,817.84. It is undisputed that this balance remained unpaid for more than ninety days after the plaintiff last supplied labor or material to the job, before Nor’easter commenced suit under § 49-42 in October, 1984.

The defendant’s president, Dominic Colossale, testified that Colossale had not paid the balance due on its contract with the plaintiff because the plaintiff’s work was defective. He claimed that there were leaks in two of the drains installed by the plaintiff and that the city of Torrington would not accept the pool or pay Colossale the unpaid balance of approximately $75,000 on Colossale’s contract with the city until the leaks were fixed. Dominic Colossale also testified that it had cost his company considerable money to locate the leaks and that he and others had attempted, without success, over a period of three years, to induce the plaintiff to correct the problems.

The trial court found for the plaintiff and rendered judgment for Nor’easter to recover from the defendants the total amount claimed of $25,817.84 together with costs and interest at the legal rate from July 6, 1984.

On appeal, the defendants claim that the trial court erred in: (1) awarding damages to the plaintiff when it had found for the defendants “on the issue of per[472]*472formance by the plaintiff”; (2) finding for the plaintiff despite the fact that it did not comply with the notice provision of General Statutes § 49-4 la (b); and (3) awarding the plaintiff interest on the judgment.

I

The defendants first claim that the plaintiff cannot prevail because the trial court resolved the question of whether the plaintiff had performed its obligations under the contract with Colossale in the defendants’ favor. That simply is not so. It is true that at the beginning of its memorandum of decision the trial court appears to have found “that the drains which Nor’easter had installed were leaking.”3 It went on in its memorándum, however, to determine “that the plaintiff has in fact established its right to recover against Colossale” and rendered judgment for the plaintiff for the full amount of its claim.4 This seeming contradiction was clarified and resolved in the plaintiff’s favor by the trial court’s response to the plaintiff’s subsequent motion for articulation. Therein the trial court stated that it had found “(A) . . . that the plaintiff substantially performed its obligation under its contract with the defendant Colossale [and] (B) . . . that the defendant Colossale failed to establish that a leak in the pool drain system was caused by the negligence or improper workmanship of the plaintiff Nor’easter.”

Whether a building contract has been substantially performed is ordinarily a question of fact for the trier to determine. Edens v. Kole Construction Co., 188 Conn. 489, 494, 450 A.2d 1161 (1982); Randolph Con[473]*473struction Co. v. Kings East Corporation, 165 Conn. 269, 274, 334 A.2d 464 (1973); Chinigo v. Ehrenberg, 112 Conn. 381, 384, 152 A. 305 (1930). The resolution of conflicting factual claims falls within the province of the trial court. Edens v. Kole Construction Co., supra 495; Fairfield County National Bank v. DeMichely, 185 Conn. 463, 466, 441 A.2d 569 (1981). “The trial court’s findings are binding upon this court unless they are clearly erroneous in light of the evidence and the pleadings in the record as a whole. Practice Book § 3060D; Superior Wire & Paper Products, Ltd. v. Talcott Tool & Machine, Inc., 184 Conn. 10, 17, 441 A.2d 43 (1981); Pandolphe’s Auto Parts, Inc. v. Manchester, 181 Conn. 217, 221-22, 435 A.2d 24 (1980).” Edens v. Kole Construction Co., supra, 494. We cannot retry the facts or pass on the credibility of the witness. Id., 495; Vesce v. Lee, 185 Conn. 328, 335, 441 A.2d 556 (1981).

Upon reviewing the entire record we can find no reason to disturb the trial court’s finding that the plaintiff had substantially completed the contract with the defendant and was entitled to recover the full amount of its claim. The trial court’s factual findings and ultimate conclusion are adequately supported by the record and are not clearly erroneous. Practice Book § 4061; see also Pandolphe’s Auto Parts, Inc. v. Manchester, supra; Howie’s Painting Service, Inc. v. Ferreria, 12 Conn. App. 583, 584, 532 A.2d 1318 (1987).

II

The defendants next contend that the trial court erred when it determined that it was unnecesssary for the plaintiff to give the defendants the notice required by General Statutes § 49-41a (b)5 before commencing [474]*474suit on the defendants’ payment bond under General Statutes § 49-42. The defendants argue that § 49-41a (b) is an integral part of the statutory scheme that furnishes a subcontractor with a cause of action against the general contractor and the surety on a payment bond under § 49-42. The defendants claim that § 49-41a (b) must be read together with, and its notice provision applied to § 49-42.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United Concrete Products, Inc. v. NJR Construction, LLC
207 Conn. App. 551 (Connecticut Appellate Court, 2021)
CCT Communications, Inc. v. Zone Telecom, Inc.
153 A.3d 1249 (Supreme Court of Connecticut, 2017)
Pack 2000, Inc. v. Cushman
Supreme Court of Connecticut, 2014
ANDY'S OIL SERVICE, INC. v. Hobbs
9 A.3d 433 (Connecticut Appellate Court, 2010)
Gravius v. Klein
3 A.3d 950 (Connecticut Appellate Court, 2010)
Del Vento, Inc. v. Braca, No. Cv00 037 56 93s (Mar. 20, 2003)
2003 Conn. Super. Ct. 3512 (Connecticut Superior Court, 2003)
Wright v. the Rugged Bear, Inc., No. Cv01 0184328 (Dec. 20, 2002)
2002 Conn. Super. Ct. 16511 (Connecticut Superior Court, 2002)
Connecticut Elec. v. Fidelity Guaranty, No. Cv00-0274893-S (Oct. 24, 2002)
2002 Conn. Super. Ct. 13633 (Connecticut Superior Court, 2002)
Chila v. Stuart, No. Cv 99 0170228 (Sep. 6, 2002)
2002 Conn. Super. Ct. 11359 (Connecticut Superior Court, 2002)
Mottolese v. Administrator, Uca, No. Cv 02 0187890 (Jul. 18, 2002)
2002 Conn. Super. Ct. 8873 (Connecticut Superior Court, 2002)
Barnard v. Town of Greenwich, No. Cv 970158251 (Apr. 12, 2002)
2002 Conn. Super. Ct. 4763 (Connecticut Superior Court, 2002)
Phoenix Horizon, Inc. v. Anderson, No. Cv 00 0083363s (Jan. 7, 2002)
2002 Conn. Super. Ct. 136 (Connecticut Superior Court, 2002)
Kaufman v. Cornerstone Bank, No. Cv 99 0171179 (Sep. 5, 2001)
2001 Conn. Super. Ct. 12390 (Connecticut Superior Court, 2001)
Ali v. Morse Brothers, Inc., No. Cv98-0489792 S (Aug. 28, 2001)
2001 Conn. Super. Ct. 11792 (Connecticut Superior Court, 2001)
MacDonald v. Pinto, No. Cv97-0479007 S (Aug. 24, 2001)
2001 Conn. Super. Ct. 11501 (Connecticut Superior Court, 2001)
Suburban Health Plan v. Yannes, No. Cv99 0067043s (May 2, 2001)
2001 Conn. Super. Ct. 5814 (Connecticut Superior Court, 2001)
In Re Sheena, (Sep. 7, 2000)
2000 Conn. Super. Ct. 10941 (Connecticut Superior Court, 2000)
Garthwaite v. Lynch, No. Cv 95 0146452 (Feb. 24, 2000)
2000 Conn. Super. Ct. 2487 (Connecticut Superior Court, 2000)
Yearms v. Ledgebrook Condominium A., Inc., No. Cv 97 0162344 (Feb. 22, 2000)
2000 Conn. Super. Ct. 2314 (Connecticut Superior Court, 2000)
Collins v. Ferrero, No. Cv 97 0158805 (Jan. 21, 2000)
2000 Conn. Super. Ct. 951 (Connecticut Superior Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
542 A.2d 692, 207 Conn. 468, 1988 Conn. LEXIS 122, Counsel Stack Legal Research, https://law.counselstack.com/opinion/noreaster-group-inc-v-colossale-concrete-inc-conn-1988.