Ali v. Morse Brothers, Inc., No. Cv98-0489792 S (Aug. 28, 2001)

2001 Conn. Super. Ct. 11792
CourtConnecticut Superior Court
DecidedAugust 28, 2001
DocketNo. CV98-0489792 S
StatusUnpublished

This text of 2001 Conn. Super. Ct. 11792 (Ali v. Morse Brothers, Inc., No. Cv98-0489792 S (Aug. 28, 2001)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ali v. Morse Brothers, Inc., No. Cv98-0489792 S (Aug. 28, 2001), 2001 Conn. Super. Ct. 11792 (Colo. Ct. App. 2001).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]

MEMORANDUM OF DECISION
The plaintiff, Gregory Ali, doing business as Ali's Landscape Garden Center, has brought suit against Morse Brothers, Inc. claiming breach of contract and unfair trade practices. Ali asserts that Morse Brothers breached an exclusive territory provision of the contract and delivered product that was substandard in quality. A claim that Morse Brothers delivered short loads of product was withdrawn by Ali at the outset of the trial. Morse Brothers denies the allegations of Ali and asserts by way of counterclaim that Ali breached the contract by failing and refusing to pay for delivered product and was unjustly enriched. Morse Brothers claims interest on the unpaid balance. Both sides seek attorneys' fees. The court heard evidence on July 18, July 19, August 15, August 16, August 27 and August 28, 2001. CT Page 11793

Late in August, 1997, the parties entered into a verbal delayed billing agreement whereby Ali was to purchase 3,650 cubic yards of bark mulch from Morse Brothers at a total cost of $60,862.50. Morse Brothers has its place of business in the State of Maine and sends its deliveries of bark mulch from that location. Since the deliveries of bark mulch were to take place in the off-season beginning in early September, 1997, there was a significant savings to Ali in the price of the bark mulch. Delivery dates were to be September through December, 1997. However, Morse Brothers reserved the option to make some deliveries early in 1998. Both parties understood that Ali intended to sell the bark mulch at retail and to landscapers at his Plantsville, Connecticut place of business beginning in April, 1998.

The first delivery of bark mulch arrived in Plantsville at the beginning of September, 1997. At the time of the second delivery, on September 4, 1997, the Morse Brothers' driver brought with him to Connecticut a written contract to supplant the verbal contract of the parties. The written contract specified that the law to be applied to the contract was the law of the State of Maine. Both parties executed the written contract. There is an addendum to the written contract calling for the signatures that Ali will designate as the only permissible signatories for acceptance of deliveries. Ali put no signatures on the addendum.

The quantity of bark mulch ordered in the 1997 contract was about 1,000 cubic yards higher than the delayed billing agreement between the same parties the previous year. Ali was willing to place a larger order because Morse Brothers agreed to sell and deliver its bark mulch to no new customers within the greater Plantsville area. Although the contract does not specify the time period for this territorial exclusion, it makes no sense to limit the time to the delivery period September, 1997, through January or February of 1998. Both parties knew that the bark mulch was intended for sale by Ali during the April to September, 1998 nursery season. Similarly, it makes no sense to extend the time period for the territorial exclusion beyond the 1998 selling season. The parties intended and contracted for Ali to have an exclusive territory for the sale of Morse Brothers bark mulch for the one-year period extending from September 1, 1997, to September 1, 1998.

Morse Brothers actually delivered bark mulch on more than seventeen occasions during September, October and November, 1997. The charge for the delivered bark mulch was $49,174.03. Ali paid a downpayment of $12,470.98 on September 4, 1997. An early snowstorm in mid-November, 1997, caused muddy conditions at the Plantsville, Connecticut nursery so that one of two Morse Brothers' delivery trucks became mired in the backyard of the nursery. Ali telephoned Morse Brothers and told Morse CT Page 11794 Brothers to cease deliveries until the ground froze. There were no further deliveries due to a mutual mistake of the parties. Morse Brothers understood that Ali was canceling further deliveries under the contract; Ali was puzzled as to why Morse Brothers had not completed the deliveries in January or February, 1998, when the ground was frozen. The telephone call from Ali requesting a delay in further deliveries was not an anticipatory breach of the contract. The failure of Morse Brothers to make additional deliveries under the delayed billing agreement was not a breach of the contract.

Ali took delivery of bark mulch from Morse Brothers on numerous occasions in the late summer and fall of 1997. There was ample opportunity for Ali to examine the delivered bark mulch. Indeed, the court finds that Ali did so, since he testified that there appeared to be nothing wrong with the bark mulch at the times of delivery. Ali accepted all of the Morse Brothers' deliveries. Ali's complaint is that the bark mulch weathered badly over the winter and was in a deteriorated state by the spring when he intended to sell it. It is common knowledge that dead organic material will begin to decompose when exposed to the elements. Ali had been in the nursery and landscaping business for several years by 1997. His claim of surprise that the product did not appear fresh in the spring of 1998, is disingenuous. The court does not find credible Ali's assertion that some of the bark mulch was mildewed as early as the spring of 1998. The court is not convinced by Ali's testimony that the delivered bark mulch was of inferior quality. The deterioration of some of the bark mulch in the spring of 1998, was caused by exposure to the elements over the preceding winter. This deterioration was as much capable of anticipation by Ali as by Morse Brothers. Ali owes Morse Brothers $36,703 for the bark mulch that was delivered and not paid for under the delayed billing contract.

The Morse Brothers' setoff and counterclaims allege that deliveries of bark mulch pursuant to the delayed billing agreement extended into April, 1998. However, the testimony of Benjamin Hawkins of Morse Brothers and the testimony of Gregory Ali were united in stating that the deliveries of bark mulch under this contract ended in November, 1997. The deliveries to Ali in April, 1998, were outside the scope of the delayed billing contract. Despite Morse Brothers' presentation of evidence that April, 1998 deliveries of bark mulch remain unpaid by Ali, those claims were not pleaded by Morse Brothers either in the setoff or the counterclaims. The court will not address claims that were not pleaded.

We now turn to the exclusive territory part of the contract. Morse Brothers' obligation under the contract was to take on no new bark mulch customers within a five-zip-code area including Plantsville and Southington, Connecticut. Morse Brothers breached that agreement when it CT Page 11795 mailed a business solicitation for the sale of bark mulch early in 1998, to Scott Comparone of Comparone Lawn Care in Southington, Connecticut (about two miles away from Ali's business) and to Guy Milo of Quality Landscaping in Plantsville, Connecticut (less than a mile from Ali's business). Comparone ordered and received one truckload of bark mulch in April, 1998; Milo ordered and received four truckloads of bark mulch in April, 1998. Each man received a "new customer" discount on these initial purchases.

In the spring of 1998, Milo had a plan in place to begin a business in competition with Ali. He would have purchased bark mulch from a source other than Morse Brothers if Morse Brothers had not been available as a supplier. In fact, Milo did make purchases of bark mulch from other vendors in the spring of 1998, both before and after the four truckloads from Morse Brothers. Although Milo had been a customer of Ali's for several years prior to 1998, he would not have continued as a customer even without the interference of Morse Brothers.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nor'easter Group, Inc. v. Colossale Concrete, Inc.
542 A.2d 692 (Supreme Court of Connecticut, 1988)
Beverly Hills Concepts, Inc. v. Schatz & Schatz, Ribicoff & Kotkin
717 A.2d 724 (Supreme Court of Connecticut, 1998)
Paulus v. LaSala
742 A.2d 379 (Connecticut Appellate Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
2001 Conn. Super. Ct. 11792, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ali-v-morse-brothers-inc-no-cv98-0489792-s-aug-28-2001-connsuperct-2001.