United Concrete Products, Inc. v. NJR Construction, LLC

207 Conn. App. 551
CourtConnecticut Appellate Court
DecidedSeptember 21, 2021
DocketAC42244
StatusPublished
Cited by3 cases

This text of 207 Conn. App. 551 (United Concrete Products, Inc. v. NJR Construction, LLC) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Concrete Products, Inc. v. NJR Construction, LLC, 207 Conn. App. 551 (Colo. Ct. App. 2021).

Opinion

*********************************************** The “officially released” date that appears near the be- ginning of each opinion is the date the opinion will be pub- lished in the Connecticut Law Journal or the date it was released as a slip opinion. The operative date for the be- ginning of all time periods for filing postopinion motions and petitions for certification is the “officially released” date appearing in the opinion.

All opinions are subject to modification and technical correction prior to official publication in the Connecticut Reports and Connecticut Appellate Reports. In the event of discrepancies between the advance release version of an opinion and the latest version appearing in the Connecticut Law Journal and subsequently in the Connecticut Reports or Connecticut Appellate Reports, the latest version is to be considered authoritative.

The syllabus and procedural history accompanying the opinion as it appears in the Connecticut Law Journal and bound volumes of official reports are copyrighted by the Secretary of the State, State of Connecticut, and may not be reproduced and distributed without the express written permission of the Commission on Official Legal Publica- tions, Judicial Branch, State of Connecticut. *********************************************** UNITED CONCRETE PRODUCTS, INC. v. NJR CONSTRUCTION, LLC, ET AL. (AC 42244) Moll, Devlin and Flynn, Js.

Syllabus

The plaintiff subcontractor sought to recover damages for, inter alia, the breach of a contract it had entered into with the defendant N Co., the general contractor on a bridge construction project, which required the plaintiff to provide various concrete elements, including beams that would form the deck of the bridge. N Co. had contracted with the Department of Transportation to replace a bridge on Route 74 by August 31, 2016. To complete the work, N Co. was to detour traffic for no longer than eight weeks. The contract further specified that N Co. could earn incentive payments for each day Route 74 was reopened prior to the expiration of the eight week period. N Co. triggered the eight week period when it closed the bridge on June 13, 2016, which thereby required that Route 74 be reopened by August 8, 2016. To receive the maximum incentive payment, N Co. had to reopen Route 74 on or before July 19, 2016. Pursuant to statute (§ 49-41), N Co., as principal, also obtained from the defendant A Co., as surety, a bond that secured payment for labor and materials on the project, and made N Co. and A Co. jointly and severally liable for any unpaid balance on the subcontract. The plaintiff was required under the subcontract to deliver the concrete elements to N Co. at the jobsite on or before June 7, 2016, and N Co. was to pay the plaintiff the contract price. Relying on information the plaintiff provided about its production of the beams, N Co. scheduled delivery of the beams for June 29, 2016. On June 27, 2016, the plaintiff informed N Co. that the beams would not be ready for delivery as scheduled. The beams were thereafter delivered on July 26, 2016, and the project was completed on August 31, 2016. N Co. thereafter remitted partial payment to the plaintiff under the subcontract and refused to pay the remaining balance. In its complaint, the plaintiff alleged that N Co. breached the subcontract by failing to pay the remaining balance, and sought attorney’s fees and interest pursuant to statute (§ 49-41a (c)). The plaintiff also sought payment from A Co. under the bond pursuant to statute (§ 49-42). N Co. filed a two count counterclaim, alleging that the plaintiff breached the subcontract as a result of the delayed delivery of the beams and engaged in unfair trade practices in violation of the Connecticut Unfair Trade Practices Act (§ 42-110a et seq.). The trial court rendered judgment for the plaintiff on its breach of contract claim against N Co. The court found that the plaintiff was entitled to recover the contract amount because N Co. had ultimately accepted the beams. The court denied the plaintiff’s claim under § 49- 41a (c) for attorney’s fees and interest from N Co., as well as its claim against A Co. for payment on the bond under § 49-42. The court reasoned that those claims were barred because the plaintiff materially breached the subcontract by virtue of its delayed delivery of the beams. The court also found that N Co. was entitled to damages and attorney’s fees on its breach of contract counterclaim. It further determined that the plain- tiff had not proven that N Co. failed to mitigate its damages. The court also determined that the plaintiff’s false and misleading statements with respect to the readiness of the beams and the timing of their delivery constituted a violation of CUTPA. On the plaintiff’s appeal to this court, held: 1. The plaintiff could not prevail on its claim that the trial court’s use of the June 7, 2016 delivery date to calculate N Co.’s damages on its breach of contract counterclaim was clearly erroneous; under the court’s timeline, using June 7, 2016, as a start date, and combined with a thirty- six day period of completion pursuant to a nonaccelerated work pace, when construed as a worst case scenario, N Co. would have earned the maximum incentive payment by reopening Route 74 on or before July 19, 2016, as the court determined that N Co. was on track to earn the maximum incentive payment when it scheduled delivery on June 29, 2016, and was working at an accelerated pace at that time; moreover, the court determined, even if N Co. had worked at a nonaccelerated pace and had endured delays in rescheduling subcontractors and equipment rental, it would have reopened Route 74 by July 13, 2016, at the latest, had the beams been delivered on time; furthermore, as the beams necessarily were to be ready for delivery on or before June 7, 2016, to coincide with commencement of the road closure, the June 29, 2016 scheduled delivery date did not alter the plaintiff’s contractual obligation to have the beams ready and available by June 7. 2. Contrary to the plaintiff’s claim that the trial court improperly declined to find that N Co. failed to mitigate its damages by failing to work on the project at an accelerated pace once the beams were delivered, the record supported the court’s finding that N Co. acted reasonably following delivery of the beams; N Co. already had lost the opportunity to earn any incentive payment and could not recover the expense of accelerating the work, it had lost its subcontractors in terms of when they would be able to come back to the project, and the acceleration costs would have caused N Co. to sustain significant losses that may have been passed on to the plaintiff. 3. The trial court erred in rendering judgment for A Co. on the plaintiff’s payment bond claim, which was based on the court’s determination that the plaintiff could not prevail on its claim for interest and attorney’s fees under § 49-41a (c): no language in the payment bond or in §§ 49- 41a or 49-42 prevented A Co. from being held jointly and severally liable for the amount that N Co. was liable, even though the court did not award the plaintiff interest and attorney’s fees pursuant to § 49-41a (c) against N Co., the court, in analyzing the plaintiff’s claims against both defendants under § 49-41a while making no mention of § 49-42, effec- tively made A Co.’s liability under § 49-42 dependent on the plaintiff’s succeeding against N Co. under § 49-41a; moreover, although the express terms of the payment bond made A Co. jointly and severally liable with N Co., the court concluded that N Co. was liable for the unpaid contract price, and, in the absence of N Co.’s having made payment for all materials and labor used or employed, A Co.’s obligation remained in full force and effect; accordingly, the judgment was reversed as to the plaintiff’s payment bond claim, and the case was remanded for a new trial on that claim. 4.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Palkimas v. Quilli
Connecticut Appellate Court, 2026
Toni v. Progressive Direct Ins. Co.
Connecticut Appellate Court, 2026
Jones v. State
Connecticut Appellate Court, 2026
Sargent v. Zoning Board of Appeals
236 Conn. App. 269 (Connecticut Appellate Court, 2025)
Circulent, Inc. v. Hatch & Bailey Co.
217 Conn. App. 622 (Connecticut Appellate Court, 2023)
Maye v. Canady
214 Conn. App. 455 (Connecticut Appellate Court, 2022)

Cite This Page — Counsel Stack

Bluebook (online)
207 Conn. App. 551, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-concrete-products-inc-v-njr-construction-llc-connappct-2021.