Spearhead Construction Corp. v. Bianco

665 A.2d 86, 39 Conn. App. 122, 1995 Conn. App. LEXIS 402
CourtConnecticut Appellate Court
DecidedSeptember 5, 1995
Docket13090
StatusPublished
Cited by30 cases

This text of 665 A.2d 86 (Spearhead Construction Corp. v. Bianco) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Spearhead Construction Corp. v. Bianco, 665 A.2d 86, 39 Conn. App. 122, 1995 Conn. App. LEXIS 402 (Colo. Ct. App. 1995).

Opinions

LAVERY, J.

The chief issues in this much litigated building contract case are: (1) what are the rights if any of a prevailing party in an arbitration award who fails to confirm the award within the statutory period and what effect does the statutorily unconfirmed award have; and (2) is the trial court bound by the findings of the attorney trial referee as to the date from which postjudgment interest runs. We reverse the judgment of the trial court.

The facts are as follows. The plaintiff had contracted to build an addition to the defendants’ house in Greenwich when a dispute arose. The matter was arbitrated in accordance with the terms of the contract. The arbitration award, dated June 14, 1988, provided that the plaintiff would obtain from the Greenwich building department the approvals necessary for the owner’s permanent records, including construction drawings, a certificate of occupancy and all plumbing, electrical and heating and ventilation approval as was usual for the town. The award further provided that when the documents had been received by the plaintiff, they would be turned over to the defendants and that the defendants would immediately pay to the plaintiff the sum of $101,000 for full and final payment for the work completed on their residence. The award further provided that upon payment, the plaintiff would immediately remove the lien placed on the defendants’ residence, and that the $101,000 to be paid by the defendants would be placed in an escrow account administered by the plaintiffs attorney with the understanding that the funds would immediately be used to pay subcontractors and materialmen who were owed money on account of the work performed on the defendants’ residence. The payments to the subcontractors and materialmen were to be made first to remove all liens and foreclosure actions brought against the defendants on account of the work done by the plaintiff.

[125]*125Neither party sought either to confirm or vacate the award within the time permitted by statute.1

Performance under the award was thwarted. The documents specified in the arbitration award were a certifi[126]*126cate of occupancy, stamped construction drawings and usual building department approvals. The town officials had erroneously approved plans that omitted a smoke detector in the maid’s room. That omission was noted after work was completed and the plans were fulfilled. The town would not issue a certificate of occupancy for the addition until the relatively inexpensive smoke detector was installed. The defendants refused to allow the plaintiff or its agents on the premises. The defendants did not pay the $101,000, and on September 19, 1990, the plaintiff brought this action seeking enforcement of the arbitration award plus interest or, in the alternative, arbitration anew.

Before the trial in this case, two of the plaintiffs subcontractors brought their own actions against the defendants, with one settling and the other going to judgment. L & M Company (L & M), the roofer, settled with the defendants for $18,000. W. G. Glenney Company (Glenney), which did business as Continental Lumber Company, tried its mechanic’s hen foreclosure action to judgment in the Fairfield judicial district. In that action, the court, Spear, J., found that “[a]s the [defendants] have prevented [the contractor] from installing the detector and thereby obtaining the certificate, the debt is due now.” The defendants sought to reduce the Glenney claim by application of the apportionment statute, General Statutes § 49-36 (b).2 Their [127]*127argument was that the sum of Glenney’s claim for $55,185.81, L & M’s claim for $44,000 and that of another claimant for approximately $6700 exceeded $101,000. The trial court made a factual finding, based on the settlement of the L & M claim for $18,000, that the aggregate of the claims against the defendants’ property did not exceed their $101,000 debt and denied apportionment. This court upheld that ruling because the L & M claim, when settled for $18,000, reduced the debt owed by the defendants from $101,000 to $83,000, which exceeded the remaining liens for $55,185.81 and $6700. W. G. Glenney Co. v. Bianco, 27 Conn. App. 199, 208, 604 A.2d 1345 (1992). This case was tried before an attorney trial referee, who found that the plaintiff had satisfied the terms of the arbitration award and determined that the sums thereunder should be paid. The referee found that the defendants should receive a credit of $81,628.31 for sums paid directly to the subcontractors. The referee also found that the plaintiff was entitled to the full arbitration award and that the fact that the defendant had bargained away the lien for $18,000 was irrelevant to the terms of the award. The attorney trial referee recommended that the arbitration award of June 16, 1988, be confirmed and refused to rewrite its terms or to correct or modify any of its conditions. The referee concluded that an award may be confirmed under General Statutes § 52-417 after the one year period.

The plaintiff and the defendants filed numerous motions to correct. For purposes of this appeal the important motion is the plaintiffs motion to correct, which provides in pertinent part: “8. The finding should be corrected to add the following omissions:

[128]*128“a. The principal amount due the plaintiff is $27,814.19. This amount is arrived at by giving the [defendants] credit against a $101,000 award for their payments of $55,155.81 to Glenney and $18,000 to L & M.
“b. To this award must be added interest at the statutory rate of 10% for 4V2 years, or $12,516.39. (The arbitration award dated June 16, 1988, has not been paid. [Section] 37-4aandthe [American Institute of Architects (ALA)] contract both provide for interest.)”

In response to the various motions to correct, the attorney trial referee made the following reply: “[T]he effect of the findings is to confirm the arbitration award (finding in the plaintiffs favor) and leaves the resolution of the exact sum to the wording of that award. Insofar as interest is collectible under the terms of the award, [General Statutes §] 37-3a would apply (and indeed AIA contract confirms same). Plaintiffs paragraph 8a in [its] motion to correct accurately reflects the findings of the referee, but the discrepancy comes from the problematic compromise of a claim for less than the award figures. The referee accepts the correction therein and confirms the amount due as $12,516.39± plus statutory interest from the date of the award.”

The attorney trial referee further responded: “The trier accepts as confusing some of the mathematical contortions caused by her avoidance of rewriting the award and the attempt to adjust a compromised claim the defendants paid after the award. ... In essence, the decision has the affect of confirming the arbitration award.”

The trial court in its memorandum of decision interpreted the attorney trial referee’s decision to have given the defendants $36,000 credit, which is the amount of the L & M claim rather than the $18,000 actually paid to the subcontractor. The trial court rendered judgment for the plaintiff in accordance with the referee’s report [129]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Michaud v. Travel Indemnity Co.
Connecticut Appellate Court, 2025
Forestier v. Bridgeport
223 Conn. App. 298 (Connecticut Appellate Court, 2024)
Larmel v. Metro North Commuter Railroad Co.
341 Conn. 332 (Supreme Court of Connecticut, 2021)
Franco v. East Shore Development, Inc.
858 A.2d 703 (Supreme Court of Connecticut, 2004)
Franco v. East Shore Development, Inc.
807 A.2d 1039 (Connecticut Appellate Court, 2002)
Fitzpatrick v. Scalzi
806 A.2d 593 (Connecticut Appellate Court, 2002)
Killion v. Davis
793 A.2d 1237 (Connecticut Appellate Court, 2002)
Metropolitan Dist. v. Ct Reso. Rec. Auth., No. Cv 01-0809181 (Oct. 12, 2001)
2001 Conn. Super. Ct. 13997 (Connecticut Superior Court, 2001)
Allapattah Services, Inc. v. Exxon Corp.
157 F. Supp. 2d 1291 (S.D. Florida, 2001)
Mitchell v. Guardian Systems, Inc., No. Cv97-032 87 05s (Nov. 27, 2000)
2000 Conn. Super. Ct. 14576 (Connecticut Superior Court, 2000)
Paulus v. LaSala
742 A.2d 379 (Connecticut Appellate Court, 1999)
Kleszczewski v. Alibigi, No. Cv98-0146404s (Mar. 4, 1999)
1999 Conn. Super. Ct. 2887 (Connecticut Superior Court, 1999)
Krystoff v. KALAMA LAND CO., LTD.
965 P.2d 142 (Hawaii Intermediate Court of Appeals, 1998)
Post Road Iron Works v. Lexington Dev., No. Cv 95 0143463 (Feb. 24, 1998)
1998 Conn. Super. Ct. 2083 (Connecticut Superior Court, 1998)
Lawler v. Blazawski, No. Cv 94 0056909 S (Feb. 11, 1998)
1998 Conn. Super. Ct. 1651 (Connecticut Superior Court, 1998)
Paulus v. Lasala, No. Cv 87 0089213 (Jan. 20, 1998)
1998 Conn. Super. Ct. 844 (Connecticut Superior Court, 1998)
Mucha v. Brown, No. Cv91 004 87 96 (Oct. 21, 1997)
1997 Conn. Super. Ct. 9913 (Connecticut Superior Court, 1997)
Crowley v. Crowley
699 A.2d 1029 (Connecticut Appellate Court, 1997)
Plaza Rlty. Mgmt. Corp. v. Sylvan Knoll, No. Cv 95 0148938 (Apr. 18, 1997)
1997 Conn. Super. Ct. 4425 (Connecticut Superior Court, 1997)
Westport Resources Inv. Services v. Parker, No. Cv95 0145076 (Dec. 3, 1996)
1996 Conn. Super. Ct. 7327 (Connecticut Superior Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
665 A.2d 86, 39 Conn. App. 122, 1995 Conn. App. LEXIS 402, Counsel Stack Legal Research, https://law.counselstack.com/opinion/spearhead-construction-corp-v-bianco-connappct-1995.