Town of Newington v. General Sanitation Service Co.

491 A.2d 363, 196 Conn. 81, 1985 Conn. LEXIS 746
CourtSupreme Court of Connecticut
DecidedApril 30, 1985
Docket12257
StatusPublished
Cited by48 cases

This text of 491 A.2d 363 (Town of Newington v. General Sanitation Service Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town of Newington v. General Sanitation Service Co., 491 A.2d 363, 196 Conn. 81, 1985 Conn. LEXIS 746 (Colo. 1985).

Opinion

Shea, J.

In this action1 for breach of contract the trial court found the issues for the plaintiff town against the defendant General Sanitation Service Company (General) and its surety on the bond given to secure performance of the contract, the defendant Balboa Insurance Company (Balboa). In their appeal from the judgment the defendants claim that the court erred (1) in concluding that a material breach of contract justifying termination had occurred; (2) in calculating damages for the cost of completing the remainder of the contract based upon employment of another sanitation company which was not the lowest bidder for the job; (3) in allowing a recovery against the surety, Balboa, without its participation in the bidding procedure as provided by the contract; and (4) in awarding damages for the entire period of the contract rather [83]*83than for only the period remaining until expiration of the performance bond. The plaintiff has cross appealed from the refusal to include an allowance for prejudgment interest in the damages awarded. We find no error in either the appeal or the cross appeal.

It is not disputed that on November 9,1976, the plaintiff town entered into a refuse disposal contract with the defendant General for a period of five years, January 1,1977, to December 31,1981. As required by the contract, General posted security for its performance in the form of a surety bond for the calendar year 1977, the first year of the contract. A similar performance bond with the defendant Balboa as surety was filed for the calendar year 1978.

On July 14, 1978, the town notified the defendants by letter of numerous instances of untimely and incomplete refuse collection and also declared its intention to terminate the agreement for default in the event that the deficiencies specified should persist. On August 31, 1978, the town in another letter detailed many additional contract violations that had occurred after the previous notification and declared the contract “in default and terminated effective September 30,1978.” This letter also asserted a claim for damages.

The trial court concluded that the defendant General had defaulted in its performance of the contract and awarded damages of $240,218.35 less certain adjustments against the defendant General. The judgment against the defendant Balboa was limited to $130,159, the amount of the bond.

I

In attacking the conclusion of the trial court that the evidence proved a “just and legitimate cause” for the town to terminate the contract, the defendants maintain that the memorandum of decision fails to set forth [84]*84the subordinate facts found to support that conclusion. It is not claimed, however, that the evidence is insufficient to support the conclusion reached. Practice Book § 3060B requires that in nonjury trials “the court shall, either orally or in writing, state its decision on the issues in the case and, if there are factual issues, the factual basis of its decision.” We have frequently indicated that if an appellant requires amplification or clarification of the factual basis of a decision to present his claims of error he should seek a further articulation from the trial court. John J. Brennan Construction Corporation, Inc. v. Shelton, 187 Conn. 695, 708, 448 A.2d 180 (1982); Kaplan v. Kaplan, 186 Conn. 387, 388 n.1, 441 A.2d 629 (1982); Pandolphe’s Auto Parts, Inc. v. Manchester, 181 Conn. 217, 222 n.5, 435 A.2d 24 (1980).

Fairly construed, the memorandum of decision adequately sets forth the subordinate facts relied upon for the conclusion of default reached by the trial court. It refers specifically to the two letters sent to the defendants that detailed numerous instances of delays in collecting refuse in certain areas of the town until after 6 p.m., the deadline for such collection activities as specified in the contract. Although these letters were admitted for the limited purpose of showing the correspondence between the parties prior to the suit and not for the truth of the facts contained therein, the memorandum notes that the complaint “closely follows” the grounds for termination detailed in these letters and finds that the plaintiff “has proven by a preponderance of the evidence that it bad just and legitimate cause to terminate the contract as it did.” Several residents of the town testified to their observations of failure to pick up refuse as scheduled. The court rejected the defendants’ claims of a political motivation for termination on the part of the town and of its violation of the contract by changing the location [85]*85of the refuse disposal area. The memorandum expressly finds that delays in refuse collection “kept happening in various degrees each week” and that consequently “there was not that orderly, regular, stable, predictable or whatever refuse collection that was contemplated, expected and due under the contract.” In the absence of a request for further articulation, this finding of subordinate facts sufficiently supports the court’s conclusion of default.

II

The trial court based its award of damages upon the increase in the cost of refuse collection and disposal to be incurred by the town for the thirty-nine months of the contract remaining after its termination on September 30,1978. After receiving bids solicited from six rubbish collection companies, the award was made to Trash-Away of New Britain, which had bid $24.68 annually per unit. A slightly lower bid of $24.15 per unit was submitted by Nutmeg Sanitation. The defendants claim that the court erred in allowing damages based upon the Trash-Away bid rather than the lower Nutmeg bid.

The contract provided that in the event of default “the contractor shall pay the town, as liquidated damages, the amount of any excess of the new contract price over the contract price herein provided for, both pro-rated to the period of time covered by the unexpired term of the contract at the time of default.” The trial court followed this provision in its award of damages. We agree with the defendants that the contract should not be construed to excuse the plaintiff from a duty to use reasonable care to minimize its damages. Brown v. Middle Atlantic Transportation, Co., 131 Conn. 197, 199, 38 A.2d 677 (1944). The fact that a bid slightly higher than the lowest of the six received was accepted by the town and used as the basis for its cal[86]*86culation of damages, however, does not necessarily imply a breach of this duty. Other factors, such as the responsibility, experience, qualifications and reputation of the bidders also warranted consideration.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

AGW Sono Partners, LLC v. Downtown Soho, LLC
343 Conn. 309 (Supreme Court of Connecticut, 2022)
Sosin v. Sosin
14 A.3d 307 (Supreme Court of Connecticut, 2011)
HH East Parcel, LLC v. Handy & Harman, Inc.
947 A.2d 916 (Supreme Court of Connecticut, 2008)
Chatterton v. Infinity Ins. Co., No. Cv98-0064615s (Oct. 1, 1999)
1999 Conn. Super. Ct. 13279 (Connecticut Superior Court, 1999)
Gianetti v. Norwalk Hospital, No. Cv84 021 43 40 S (Sep. 9, 1999)
1999 Conn. Super. Ct. 12277 (Connecticut Superior Court, 1999)
Holeva v. M Z Associates, No. Cvnh 9709-8403 (Jan. 12, 1998)
1998 Conn. Super. Ct. 620 (Connecticut Superior Court, 1998)
Odorczuk v. Tirrell, No. Cv 97 0073697 (Sep. 4, 1997)
1997 Conn. Super. Ct. 9349 (Connecticut Superior Court, 1997)
Hackbarth v. Ross, No. Cv 96-7800 (Aug. 1997)
1997 Conn. Super. Ct. 8249 (Connecticut Superior Court, 1997)
Dematteo v. Villano, No. Cvnh 9604-7493 (Jul. 10, 1997)
1997 Conn. Super. Ct. 7436 (Connecticut Superior Court, 1997)
Grande v. Behling, No. Cv95-0250416s (Apr. 24, 1997)
1997 Conn. Super. Ct. 4768 (Connecticut Superior Court, 1997)
Foley v. Huntington Co.
682 A.2d 1026 (Connecticut Appellate Court, 1996)
Buitekant v. Zotos Corporation, No. Cv94 0135874 (Feb. 20, 1996)
1996 Conn. Super. Ct. 1331-XXXX (Connecticut Superior Court, 1996)
Quinn Assoc. Inc. v. Fga Serv. Inc., No. Cv91 0315433s (Dec. 22, 1995)
1995 Conn. Super. Ct. 13381 (Connecticut Superior Court, 1995)
Barone v. O'connell, No. Cvbr 9407-02447 (Dec. 13, 1995)
1995 Conn. Super. Ct. 14666 (Connecticut Superior Court, 1995)
Spearhead Construction Corp. v. Bianco
665 A.2d 86 (Connecticut Appellate Court, 1995)
Loomis Institute v. Town of Windsor
661 A.2d 1001 (Supreme Court of Connecticut, 1995)
Lynch v. Granby Holdings, Inc.
658 A.2d 592 (Connecticut Appellate Court, 1995)
Levine v. Massey, No. Cv93-0345481-S (May 11, 1995)
1995 Conn. Super. Ct. 4792 (Connecticut Superior Court, 1995)
Republic Insurance v. Pat Dinardo Auto Sales, Inc.
678 A.2d 516 (Connecticut Superior Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
491 A.2d 363, 196 Conn. 81, 1985 Conn. LEXIS 746, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-newington-v-general-sanitation-service-co-conn-1985.