HH East Parcel, LLC v. Handy & Harman, Inc.

947 A.2d 916, 287 Conn. 189, 2008 Conn. LEXIS 217
CourtSupreme Court of Connecticut
DecidedJune 3, 2008
DocketSC 18055
StatusPublished
Cited by19 cases

This text of 947 A.2d 916 (HH East Parcel, LLC v. Handy & Harman, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
HH East Parcel, LLC v. Handy & Harman, Inc., 947 A.2d 916, 287 Conn. 189, 2008 Conn. LEXIS 217 (Colo. 2008).

Opinion

Opinion

NORCOTT, J.

In this appeal, we consider the appropriate level of deference that the courts, in performing their de novo review of whether an arbitration award violates public policy, should give to the arbitrator’s factual findings. The defendant, Handy and Harman, Inc., appeals 1 from the judgment of the trial court granting the application of the plaintiff, HH East Parcel, LLC, to confirm, and denying the defendant’s application to vacate, an arbitration award rendered in favor of the plaintiff. On appeal, the defendant claims that the trial court, in confirming the award, improperly deferred to the arbitrator’s factual findings when the court concluded that a per diem provision in a contract for the sale and remediation of real estate was a valid liquidated damages clause, rather than a penalty clause, the enforcement of which would violate the public policy of Connecticut. We conclude that the trial court properly deferred to the arbitrator’s factual findings in determining that the award did not violate public policy. Accordingly, we affirm the judgment of the trial court.

The record reveals the following undisputed background facts and procedural history. On or about December 31, 2003, the defendant sold real property located in Fairfield to the plaintiff for $8 million. The purchase and sale agreement (purchase agreement) required the defendant to demolish all existing buildings and structures on the property, and to remediate all environmental contamination on the property by December 31, 2004. The purchase agreement also pro *192 vided that time was of the essence with regard to the remediation. Sections 14 and 15 of the purchase agreement contained a per diem clause that required the defendant to pay to the plaintiff $5000 for each day after December 31, 2004, that the defendant had failed to complete the demolition and remediation as specified therein.

Although the plaintiff paid the defendant $8 million and received title to the property, the defendant failed to complete the remediation by December 31, 2004, as agreed to by the parties. The defendant also failed to pay the necessary contractors and subcontractors for remediation services rendered by December 31, 2004, and they placed various mechanic’s liens on the property. Thus, the parties then entered into an environmental indemnification agreement (indemnification agreement) that required the defendant to indemnify and hold harmless the plaintiff for the losses caused by the defendant’s failure to complete the remediation.

Thereafter, on April 5, 2005, the plaintiff filed a demand for arbitration with the American Arbitration Association (association) pursuant to § 6 of the indemnification agreement, 2 and served a copy of that demand *193 on the defendant. 3 Attorney Edward V. Lahey, Jr., was selected as the arbitrator, and he conducted a two day arbitration in Stamford. At the arbitration, the defendant did not dispute its liability for breach of the purchase agreement, but did dispute the validity of the $5000 per diem clause, which the defendant claimed was an unenforceable penalty. The plaintiff contended, however, that the per diem clause was a valid liquidated damage provision. The arbitrator issued an award in December, 2005, upon concluding that the $5000 per diem clause was a reasonable and valid liquidated damages provision that had been properly negotiated by the parties. The arbitrator ordered the defendant to pay the plaintiff $5000 per day for all unpaid per diem charges occurring since January 1, 2005, through November 30, 2005, for a total of $1,670,000, and directed the defendant to begin making monthly payments on that sum starting January 1, 2006. The arbitrator also ordered the defendant to pay the plaintiff 6 percent interest on all unpaid per diem charges, and to fund and complete the demolition and remediation of the property without delay. 4

Shortly thereafter, the plaintiff brought this application to confirm the arbitration award pursuant to General Statutes § 52-417, 5 and the defendant filed its *194 application and cross motion to vacate the award pursuant to General Statutes § 52-418 (a), 6 claiming, inter alia, that “the award violate[d] public policy by awarding a draconian, limitless penalty . . . .” 7 The trial court relied on our decision in Schoonmaker v. Cummings & Lockwood of Connecticut, P.C., 252 Conn. 416, 747 A.2d 1017 (2000), and noted that, although it was required to review the award de novo because the defendant claimed that it violated the well established public policy against the enforcement of penalty clauses in contracts, it nevertheless was obligated to defer to the arbitrator’s factual findings and interpretation of the *195 underlying contract. The trial court determined that the arbitrator properly applied Connecticut law to conclude that the purchase agreement contained a valid liquidated damages clause based on his findings that the damages resulting from the breach of the contract would be difficult to estimate or provide, that the parties had intended to liquidate any resulting damages, and that the amount agreed upon in the contract was not unreasonable. The trial court also conducted, however, an additional review of the record in detail to determine whether the arbitrator’s findings were in fact supported by substantial evidence, and concluded that the findings were supported by: (1) the negotiated nature of the per diem charge and the date that it would begin; and (2) the difficulties of ascertaining economic loss because of the fluctuating liens on the property and determining how long the remediation would take. Accordingly, the trial court rejected the defendant’s claim that the arbitration award violated public policy, and rendered judgment confirming the award. This appeal followed. 8

On appeal, the defendant claims that the trial court improperly deferred to the arbitrator’s factual findings, *196 because the issue of whether the per diem clause was a penalty is a mixed question of fact and law subject to de novo review. The defendant also claims that the trial court improperly confined its review to the issue of whether the arbitrator’s findings were supported by substantial evidence, and claims that, even under that more restrictive standard of review, the evidence in the record does not support the arbitrator’s conclusion that the per diem clause was not an illegal penalty. In response, the plaintiff relies on our recent decision in C. R. Klewin Northeast, LLC v. Bridgeport, 282 Conn. 54, 919 A.2d 1002

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Salce v. Cardello
Supreme Court of Connecticut, 2023
DeRose v. Jason Robert's, Inc.
Connecticut Appellate Court, 2019
Clasby v. Zimmerman
Connecticut Appellate Court, 2019
Toland v. Toland
182 A.3d 651 (Connecticut Appellate Court, 2018)
State v. Connecticut Employees Union Independent
142 A.3d 1122 (Supreme Court of Connecticut, 2016)
Katz, Nannis & Solomon, P.C. v. Levine
46 N.E.3d 541 (Massachusetts Supreme Judicial Court, 2016)
SBD Kitchens, LLC v. Jefferson
Connecticut Appellate Court, 2015
Helen Yu-Wen Chang v. Siu
323 P.3d 725 (Court of Appeals of Arizona, 2014)
City of Hartford v. Hartford Municipal Employees Ass'n
39 A.3d 1146 (Connecticut Appellate Court, 2012)
Nafta Traders, Inc. v. Quinn
339 S.W.3d 84 (Texas Supreme Court, 2011)
State v. AFSCME, COUNCIL 4, LOCAL 391
7 A.3d 931 (Connecticut Appellate Court, 2010)
AFSCME, Council 4, Local 1565 v. Department of Correction
6 A.3d 1142 (Supreme Court of Connecticut, 2010)
Pugh's Lawn Landscape Co. v. Jaycon Development Corp.
320 S.W.3d 252 (Tennessee Supreme Court, 2010)
Coldwell Banker Manning Realty, Inc. v. Cushman & Wakefield
980 A.2d 819 (Supreme Court of Connecticut, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
947 A.2d 916, 287 Conn. 189, 2008 Conn. LEXIS 217, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hh-east-parcel-llc-v-handy-harman-inc-conn-2008.