Blakeslee Arpaia Chapman, Inc. v. EI Constructors, Inc.

687 A.2d 506, 239 Conn. 708, 1997 Conn. LEXIS 11
CourtSupreme Court of Connecticut
DecidedJanuary 21, 1997
Docket15381
StatusPublished
Cited by126 cases

This text of 687 A.2d 506 (Blakeslee Arpaia Chapman, Inc. v. EI Constructors, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blakeslee Arpaia Chapman, Inc. v. EI Constructors, Inc., 687 A.2d 506, 239 Conn. 708, 1997 Conn. LEXIS 11 (Colo. 1997).

Opinions

BERDON, J.

This appeal1 involves, among numerous lesser issues, the award of offer of judgment interest pursuant to General Statutes (Rev. to 1983) § 52-192a.2 The offer of judgment issue raises the following: (1) whether the plaintiff was entitled to such interest when a unified offer of judgment was directed to multiple defendants; (2) whether the plaintiff was entitled to such interest because, subsequent to the filing of the offer, the plaintiff amended its complaint to add a new claim; (3) whether the plaintiff should have been awarded such interest for the period of time this action was stayed pending the outcome of related federal liti[711]*711gation; and (4) whether the offer of judgment statutes, General Statutes (Rev. to 1983) §§ 52-192a and 52-193, and General Statutes §§ 52-194 and 52-195,3 treat plaintiffs and defendants so differently as to violate the due process and equal protection guarantees of the federal and state constitutions.

On January 11,1983, the defendant general contractor El Constructors, Inc. (El), and the defendant city of Waterbury (Waterbury) entered into a contract (contract) for the construction of the Waterbury water treatment plant (plant). El, as principal, and the defendant Aetna Insurance Company (Aetna), as surety, furnished a payment bond in the amount of $21,274,000 pursuant to the contract and as required by General Statutes (Rev. to 1983) § 49-41 et seq.4 Thereafter, the plaintiff Blakeslee Arpaia Chapman, Inc., entered into a subcontract with El to perform certain work with respect to the plant (subcontract) for the price of $440,000. El defaulted on the contract by failing to perform its obligation, and Waterbury took control of the construction of the plant.

The plaintiff thereafter brought this multiple count action for damages arising out of the construction of the plant against El on the subcontract, against Aetna as surety on the payment bond, and against Waterbury for tortious conduct. The nine counts of the complaint relevant to El and Aetna are: count one for progress payments under its subcontract pursuant to invoices for July, August and September, 1984; count two for equipment rentals and standby labor costs; count three for rental and liquidation costs of steel sheeting and structured members; count four for the 5 percent retainage held pursuant to the subcontract; count five for extra work; count six for the cost of failing to supply [712]*712electricity; count seven for unbilled costs and profits under the subcontract; count eight for extra costs for unforeseen construction conditions; and count nine for increased labor costs. The relevant facts for each count that is the subject of this appeal will be discussed when addressing the particular issue.

The trial court, in a thoughtful and comprehensive written opinion, rendered judgment in favor of the plaintiff against EI for $1,506,687.235 and against Aetna for $967,338.16.6 These amounts included interest pursuant [713]*713to General Statutes (Rev. to 1983) § 37-3a7 (compensatory interest) and interest pursuant to § 52-192a (offer of judgment interest). The trial court also rendered judgment in favor of Waterbury. Aetna appealed8 and the plaintiff cross appealed9 to the Appellate Court and we transferred both appeals to this court pursuant to Practice Book § 4023 and General Statutes § 51-199 (c).10 We affirm the judgment of the trial court.

Although the principal issues in this case pertain to the offer of judgment interest pursuant to § 52-192a, [714]*714several other issues raised by Aetna on the appeal and the plaintiff on the cross appeal must first be addressed. We begin our analysis with the appropriate standard of review. On appeal, our function is not to retry the facts. Torosyan v. Boehringer Ingelheim Pharmaceuticals, Inc., 234 Conn. 1, 16, 662 A.2d 89 (1995). Rather, “[t]he trial court’s findings are binding upon this court unless they are clearly erroneous in light of the evidence and the pleadings in the record as a whole. ... A finding of fact is clearly erroneous when there is no evidence in the record to support it ... or when although there is evidence to support it, the reviewing court on the entire evidence is left with the definite and firm conviction that a mistake has been committed.” (Internal quotation marks omitted.) Groton v. Yankee Gas Services Co., 224 Conn. 675, 691, 620 A.2d 771 (1993).

The liability of Aetna under the payment bond will be reviewed in part I of this opinion, and the issues of compensatory interest and offer of judgment interest will be reviewed in parts II and III, respectively.

I

LIABILITY OF AETNA

General Statutes (Rev. to 1983) §§ 49-41 through 49-43, which provide for the furnishing of bonds guaranteeing payment (payment bonds) on public works construction projects, were “enacted to protect workers and materials suppliers on public works projects who cannot avail themselves of otherwise available remedies such as mechanic’s liens.” Herbert S. Newman & Partners v. CFC Construction Ltd. Partnership, 236 [715]*715Conn. 750, 757, 674 A.2d 1313 (1996); see National Fireproofing Co. v. Huntington, 81 Conn. 632, 633, 71 A. 911 (1909) (mechanic’s lien cannot lie against the state or any of its subdivisions). Section 49-4111 requires that the general contractor provide a payment bond with surety to the state or governmental subdivision, which bond shall guarantee payment to those who supply labor and materials on a public works project. See Nor’easter Group, Inc. v. Colossale Concrete, Inc., 207 Conn. 468, 471, 542 A.2d 692 (1988). Section 49-4212 provides [716]*716that any person who has performed work or supplied materials on a public works project, but who has not received full payment for such materials or work, may enforce his right to payment under the payment bond.

This legislation, known as the “Little Miller Act” (act), “was patterned after federal legislation popularly known as the Miller Act; 40 U.S.C. §§ 270a through 270d; and, therefore, we have regularly consulted federal precedents to determine the proper scope of our statute. American Masons’ Supply Co. v. F. W. Brown Co., [174 Conn. 219, 223-24, 384 A.2d 378 (1978)]; Pittsburgh Plate Glass Co. v. Dahm, [159 Conn. 563, 567-68, 271 A.2d 55 (1970)]; International Harvester Co. v. L. G. DeFelice & Son, Inc., [151 Conn. 325, 332-34, 197 A.2d 638 (1964)].” Okee Industries, Inc. v. National Grange Mutual Ins. Co., 225 Conn. 367, 374, 623 A.2d 483 (1993). “The federal precedents, like our own, counsel liberal construction of statutory requirements other than those relating to specific time constraints.” Id.; see also Herbert S. Newman & Partners v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Glory Chapel International Cathedral v. Philadelphia Indemnity Ins. Co.
224 Conn. App. 501 (Connecticut Appellate Court, 2024)
Byrne v. Avery Center for Obstetrics & Gynecology, P.C.
212 Conn. App. 339 (Connecticut Appellate Court, 2022)
Medical Device Solutions, LLC v. Aferzon
207 Conn. App. 707 (Connecticut Appellate Court, 2021)
United Concrete Products, Inc. v. NJR Construction, LLC
207 Conn. App. 551 (Connecticut Appellate Court, 2021)
Georges v. OB-GYN Services, P.C.
Supreme Court of Connecticut, 2020
Lavy v. Lavy
210 A.3d 98 (Connecticut Appellate Court, 2019)
Izzarelli v. R.J. Reynolds Tobacco Co.
767 F. Supp. 2d 335 (D. Connecticut, 2011)
Voris v. Middlesex Mutual Assurance Co.
999 A.2d 741 (Supreme Court of Connecticut, 2010)
Earlington v. Anastasi
976 A.2d 689 (Supreme Court of Connecticut, 2009)
Rosado v. Bridgeport Roman Catholic Diocesan Corp.
970 A.2d 656 (Supreme Court of Connecticut, 2009)
Anquillare, Lipnicki, Ruocco v. Vcr Realty, No. Cv00-007017s (Feb. 5, 2003)
2003 Conn. Super. Ct. 2026 (Connecticut Superior Court, 2003)
Bredeau v. Scott, No. Cv 01 0446633 S (Dec. 5, 2002)
2002 Conn. Super. Ct. 15406 (Connecticut Superior Court, 2002)
Ditullio v. Ross, No. Cv00-034 01 16 S (Oct. 25, 2002)
2002 Conn. Super. Ct. 13566 (Connecticut Superior Court, 2002)
Connecticut Elec. v. Fidelity Guaranty, No. Cv00-0274893-S (Oct. 24, 2002)
2002 Conn. Super. Ct. 13633 (Connecticut Superior Court, 2002)
Millgard Corp. v. White Oak Corp.
224 F. Supp. 2d 425 (D. Connecticut, 2002)
One Station Place v. Stamford, No. Cv00 0179485 S (Jul. 12, 2002)
2002 Conn. Super. Ct. 8685 (Connecticut Superior Court, 2002)
Hoffman v. Stamford, No. Cv00 0179476 S (Jul. 12, 2002)
2002 Conn. Super. Ct. 8566 (Connecticut Superior Court, 2002)
969 Associates v. Stamford, No. Cv00 0179492 S (Jul. 12, 2002)
2002 Conn. Super. Ct. 8679 (Connecticut Superior Court, 2002)
May Department Stores v. Stamford, No. Cv00 0179479 S (Jul. 12, 2002)
2002 Conn. Super. Ct. 8571 (Connecticut Superior Court, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
687 A.2d 506, 239 Conn. 708, 1997 Conn. LEXIS 11, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blakeslee-arpaia-chapman-inc-v-ei-constructors-inc-conn-1997.