Camp, Dresser & McKee Inc. v. Technical Design Associates, Inc., James P. Purcell Associates, Inc., James P. Purcell Associates, Inc.

937 F.2d 840, 1991 U.S. App. LEXIS 13873
CourtCourt of Appeals for the Second Circuit
DecidedJuly 1, 1991
Docket1280, Docket 90-9088
StatusPublished
Cited by11 cases

This text of 937 F.2d 840 (Camp, Dresser & McKee Inc. v. Technical Design Associates, Inc., James P. Purcell Associates, Inc., James P. Purcell Associates, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Camp, Dresser & McKee Inc. v. Technical Design Associates, Inc., James P. Purcell Associates, Inc., James P. Purcell Associates, Inc., 937 F.2d 840, 1991 U.S. App. LEXIS 13873 (2d Cir. 1991).

Opinion

PARKER, District Judge:

BACKGROUND

On October 29, 1971, the City of New Haven (the City) and Camp, Dresser & McKee, Inc. (CDM) entered into a contract in which CDM agreed to provide the complete design for the East Shore Wastewa-ter Treatment Plant (the plant).

The design of the plant involved “process design” and “non-process design.” The former included design of the machinery, equipment and systems necessary to treat sewage. Non-process design involved design of the building which houses the processing components and the systems to serve the building such as the plumbing, electrical, heating, ventilating, and air conditioning systems (HVAC).

On September 29, 1971, CDM entered into a subcontract with James P. Purcell Associates, Inc. (Purcell) in which Purcell agreed to provide CDM with the complete non-process design for the plant. On the same date, Purcell entered into a sub-subcontract with Technical Design Associates, Inc. (TDA) in which TDA agreed to provide Purcell with the engineering services necessary for the electrical systems for the plant. Design of the plant was completed in 1975 and construction was completed in 1982.

On May 31, 1984, the City commenced suit against CDM for alleged negligence in the design and construction of the plant. On February 4,1986, CDM filed third party actions against both Purcell and TDA claiming indemnity for any damages incurred by CDM as a result of errors or deficiencies in the HVAC drawings furnished by Purcell and prepared by TDA. On June 11, 1986, Purcell filed a cross-claim against TDA. Default judgments were entered against TDA in favor of Purcell and CDM.

With regard to the defects in the HVAC system, it was determined that the HVAC fresh air intake was located too close to the exhaust vents from the ozonator, a chamber where all of the noxious gases generated in the wastewater treatment were collected, treated and then discharged. As a result, corrosive gases discharged from the ozone chamber were ingested by the air intake system and distributed to the administrative areas of the building. The discharged gases were found to have caused extensive damage to the City’s computer control equipment.

In mid-1989, the district court conducted an extensive series of settlement negotiations between the City, CDM and Purcell. The City agreed to accept $2,700,000 from CDM in full settlement of all its claims against CDM including the claims arising from damage caused by the HVAC system. CDM in turn agreed to accept a sum certain from Purcell due to defects in the HVAC system. Purcell rejected CDM’s proposal. On November 6, 1989, CDM agreed to the City’s demand and paid $2.7 *842 million. On November 29,1989 the District Court entered a stipulated judgment in favor of the City and against CDM for $2.7 million. The judgment provided:

$600,000 is attributable to the claim for improper placement of the fresh air intake vent in close proximity to the exhaust from the ozone chamber.

Joint Appendix (JA) 114-115. Purcell did not join in the stipulation of judgment. The District Court retained jurisdiction to hear and determine CDM’s third party claim for indemnity from Purcell.

On December 21, 1989, pursuant to § 52-192a of the Connecticut General Statutes, CDM filed an offer of judgment directed at Purcell to settle the claim for $250,000. JA122. Purcell rejected this offer.

By agreement of the parties, the case was referred to Magistrate Judge F. Owen Eagan for trial. The Magistrate Judge issued a decision in which he found Purcell liable to CDM for $600,000 for the defective HVAC design. He found “that pursuant to the contract between CDM and Purcell, Purcell expressly assumed the obligation of properly designing the plant’s ventilation system.” JA176. Hence, the Magistrate Judge based Purcell’s liability on breach of an express contractual agreement. The Magistrate Judge also specifically found CDM’s settlement with the City to be reasonable in amount and awarded $600,000 in damages plus interest under Connecticut General Statutes § 37-3a and § 52-192a.

Purcell objected in the district court to the Magistrate Judge’s decision on the grounds that it never identified the basis of Purcell’s obligation to indemnify CDM. Specifically, Purcell argued that “absent a statutory or contractual obligation to indemnify, the only basis for a claim of indemnity is the active passive negligence theory of Kaplan v. Merberg Wrecking Corp., 152 Conn. 405, 207 A.2d 732 (1965).” JA180. Purcell further argued that CDM failed to prove the necessary four factors under Kaplan that would entitle it to indemnification. Purcell’s final objection was to the Magistrate Judge’s imposition of interest.

On October 10, 1990, the trial court affirmed, ratified and adopted the Magistrate Judge’s Memorandum of Decision. The trial court agreed that there was no indemnity provision in the Purcell/CDM contract, but rejected Purcell’s argument that the only basis for indemnification is Kaplan. The trial court held: “Thus because the duty to indemnify is the relief sought for a breach of contract, it does not arise from operation of law and Purcell’s reliance on Kaplan ... is misplaced.” JA196. Judgment was entered on October 16, 1990 and Purcell timely filed its notice of appeal on November 4, 1990.

JURISDICTION

Appellate jurisdiction in this case is premised on either of two alternative grounds. We have appellate jurisdiction either under 28 U.S.C. § 636(c)(3) as an appeal from a judgment entered on a magistrate judge’s ruling, or as an appeal under 28 U.S.C. § 1291 from a district court judge’s ruling approving a recommended ruling of a magistrate judge under 28 U.S.C. § 636(b). 1

DISCUSSION

1. The Breach of Contract Claim

The appellant Purcell’s efforts on this appeal are essentially to spar with a *843 straw man of no substance. The argument goes that there is no express provision in the contract between Purcell and CDM whereby Purcell agrees to indemnify CDM. Therefore, the only basis for indemnification must be the decision in Kaplan v. Merberg Wrecking Corp., 152 Conn. 405, 207 A.2d 732 (1965). Under Kaplan, in order for CDM to be indemnified by operation of law CDM must show that Purcell was actively or primarily negligent, and that CDM was only secondarily or passively negligent. Purcell argues that CDM cannot meet those requirements of Kaplan and, accordingly, there is no indemnification as a matter of law and no indemnification under the contract so CDM must fail.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Case
D. Connecticut, 2026
Kelly Services, Inc. v. Senior Network, Inc.
338 Conn. 794 (Supreme Court of Connecticut, 2021)
Hardy v. Saliva Diagnostic Systems, Inc.
52 F. Supp. 2d 333 (D. Connecticut, 1999)
Knudsen v. Volpe, No. Cv94-0066028s (Dec. 4, 1998)
1998 Conn. Super. Ct. 14292 (Connecticut Superior Court, 1998)
Blakeslee Arpaia Chapman, Inc. v. EI Constructors, Inc.
687 A.2d 506 (Supreme Court of Connecticut, 1997)
In Re MacMillan, Inc.
204 B.R. 378 (S.D. New York, 1997)
Slater v. Central Plumbing and Heating Co.
912 P.2d 780 (Montana Supreme Court, 1996)
Lutynski v. Bb J Trucking Inc., No. 090363 (Oct. 14, 1994)
1994 Conn. Super. Ct. 10058-D (Connecticut Superior Court, 1994)
Patron v. Konover, No. 395106 (Apr. 24, 1994)
1994 Conn. Super. Ct. 4186-G (Connecticut Superior Court, 1994)
Stripling v. New England Savings Bank, No. 517442s (Apr. 27, 1993)
1993 Conn. Super. Ct. 4072 (Connecticut Superior Court, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
937 F.2d 840, 1991 U.S. App. LEXIS 13873, Counsel Stack Legal Research, https://law.counselstack.com/opinion/camp-dresser-mckee-inc-v-technical-design-associates-inc-james-p-ca2-1991.