Department of Public Works v. Ecap Construction Co.

737 A.2d 398, 250 Conn. 553, 1999 Conn. LEXIS 310
CourtSupreme Court of Connecticut
DecidedSeptember 7, 1999
DocketSC 16036
StatusPublished
Cited by19 cases

This text of 737 A.2d 398 (Department of Public Works v. Ecap Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Department of Public Works v. Ecap Construction Co., 737 A.2d 398, 250 Conn. 553, 1999 Conn. LEXIS 310 (Colo. 1999).

Opinion

Opinion

PALMER, J.

The dispositive issue raised by this appeal is whether, under General Statutes § 4-61,1 a [555]*555contractor who claims that the state has breached a public works contract may compel the state to arbitrate a dispute over the state’s alleged agreement to settle the contractor’s underlying breach of contract claim. We conclude that the state may not be compelled to submit to arbitration in such circumstances and, accordingly, reverse the judgment of the trial court rejecting the state’s application for a permanent injunction prohibiting the arbitration of the alleged settlement agreement.

The following facts and procedural history are relevant to this appeal. On March 11,1994, the named defendant, ECAP Construction Company (ECAP),2 entered into a contract with the plaintiff, the state department of public works (department), to perform concrete work in connection with the construction of a law library at the University of Connecticut School of Law in Hartford. The contract required ECAP to provide all materials, labor, equipment and services necessary to construct the concrete portions of the building, including the foundation walls and floor slabs. During the construction of the library, a dispute arose between the department and ECAP regarding changes in work orders and schedules, delays in the work caused by the department and its general contractor, and the unpaid balance of the contract price. In late 1995, ECAP submitted an informal notice of claim to the department setting forth its alleged damages.

From December, 1995, until April, 1996, department officials and ECAP representatives met several times to discuss the dispute. ECAP alleges that, at one of these meetings, Richard Piotrowski, the department’s bureau chief of facilities design and construction, made a firm offer to settle the dispute for $425,000. ECAP also alleges that it subsequently accepted that offer. [556]*556According to the department, however, PiotrowsM’s settlement offer was only a tentative one, subject to approval by the department’s commissioner and the formal approval process required under General Statutes § 3-7 (c).3 Such approval was never obtained, and the department notified ECAP that, in its view, there was no settlement of the dispute.

On February 18, 1997, ECAP filed a demand for arbitration before the American Arbitration Association (arbitration association), the other defendant in this case, under § 4-61, seeking $1,870,169.83 in damages for extra work and delays under the construction contract. Although the department contested ECAP’s claim, the department did not dispute the arbitrability of the claim.

On October 29, 1997, ECAP filed an amended demand for arbitration, adding allegations that the department had: (1) breached the purported agreement to settle the dispute under the contract; and (2) acted in bad faith and “in willful disregard of ECAP’s rights under the terms of the [settlement] [agreement and with reckless indifference and wanton and intentional violation of those rights . . . .” The amended demand for arbitration sought, inter alia, an additional $425,000 in damages.

The state then filed this action seeking, inter alia, a permanent injunction against ECAP and the arbitration association from proceeding with the amended demand for arbitration.4 At the hearing on the state’s action, the state asserted that the arbitration association lacked [557]*557subject matter jurisdiction over ECAP’s amended demand. Specifically, the state maintained that ECAP’s amended demand did not fall within the limited sovereign immunity waiver of § 4-61 because the parties’ disagreement over the purported settlement did not constitute a disputed claim arising “under” the contract within the meaning of the statute.

The trial court denied the state’s application for injunctive relief. The court concluded that, because ECAP’s original disputed claims were subject to arbitration, its amended demand concerning a dispute over the alleged agreement to settle those claims also was arbitrable. In particular, the trial court rejected the state’s claim that, for purposes of § 4-61, a distinction must be made between a disputed claim arising “under” a public works contract, and a disputed claim, such as ECAP’s claim, that is “related to,” “derived from” or “based upon” the underlying contract.5 Accordingly, the trial court rendered judgment for the defendants.

The state appealed from the judgment of the trial court to the Appellate Court, and we transferred the appeal to this court pursuant to what is now Practice Book § 65-1, and General Statutes § 51-199 (c).

On appeal, the state argues that the trial corut improperly concluded that § 4-61 authorizes arbitration of ECAP’s claims concerning the department’s alleged breach of the settlement agreement. The state maintains that § 4-61 provides for a waiver of the state’s sovereign immunity only in narrowly defined circumstances and, furthermore, that ECAP has failed to establish that its amended demand for arbitration falls within the limited [558]*558scope of that waiver. According to the state, the department’s alleged breach of the settlement agreement did not constitute a “disputed [claim] under [a public works] contract” within the meaning of § 4-61. The state claims, therefore, that the arbitration association lacks subject matter jurisdiction to arbitrate these claims. We agree with the state.

Whether the department’s alleged breach of the settlement agreement is subject to arbitration under § 4-61 is a question of statutory interpretation. “The process of statutory inteipretation involves a reasoned search for the intention of the legislature. ... In other words, we seek to determine, in a reasoned manner, the meaning of the statutory language as applied to the facts of this case, including the question of whether the language actually does apply. In seeking to determine that meaning, we look to the words of the statute itself, to the legislative history and circumstances surrounding its enactment, to the legislative policy it was designed to implement, and to its relationship to existing legislation and common law principles governing the same general subject matter.” (Internal quotation marks omitted.) Babes v. Bennett, 247 Conn. 256, 261-62, 721 A.2d 511 (1998).

“Our analysis is more specifically illuminated by the well settled principle that when the state waives sovereign immunity by statute a party attempting to sue under the legislative exception must come clearly within its provisions, because [statutes in derogation of sovereignty should be strictly construed in favor of the state, so that its sovereignty may be upheld and not narrowed or destroyed .... Where there is any doubt about [the] meaning or intent [of a statute in derogation of sovereign immunity, it is] given the effect which makes the least rather than the most change in sovereign immunity. . . . The state’s sovereign right not to be sued may be waived by the legislature, provided clear [559]*559intention to that effect is disclosed by the use of express terms or by force of a necessary implication.” (Citations omitted; internal quotation marks omitted.) Id., 262. Thus, before bringing suit under a statutory waiver of sovereign immunity, “[a] plaintiff must prove . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Praisner v. State
208 A.3d 667 (Connecticut Appellate Court, 2019)
Paragon Construction Co. v. Department of Public Works
23 A.3d 732 (Connecticut Appellate Court, 2011)
C. R. Klewin Northeast, LLC v. State
9 A.3d 326 (Supreme Court of Connecticut, 2010)
Bacon Construction Co. v. Department of Public Works
987 A.2d 348 (Supreme Court of Connecticut, 2010)
Rivers v. City of New Britain
950 A.2d 1247 (Supreme Court of Connecticut, 2008)
Department of Transportation v. White Oak Corp.
946 A.2d 1219 (Supreme Court of Connecticut, 2008)
MBNA America Bank, N.A. v. Boata
926 A.2d 1035 (Supreme Court of Connecticut, 2007)
First Union National Bank v. Hi Ho Mall Shopping Ventures, Inc.
869 A.2d 1193 (Supreme Court of Connecticut, 2005)
St. George v. Gordon
825 A.2d 90 (Supreme Court of Connecticut, 2003)
Egri v. Foisie, No. Cv 00 0091579 S (Dec. 10, 2002)
2002 Conn. Super. Ct. 15391 (Connecticut Superior Court, 2002)
Bostick v. City of Willimantic, No. Cv 01 0065265 S (Jan. 29, 2002)
2002 Conn. Super. Ct. 1226 (Connecticut Superior Court, 2002)
St. George v. Gordon, No. Cv01-0379943-S (Nov. 21, 2001)
2001 Conn. Super. Ct. 15941-gx (Connecticut Superior Court, 2001)
Miller v. Egan, No. Cv00-0556827-S (Sep. 6, 2001)
2001 Conn. Super. Ct. 12438 (Connecticut Superior Court, 2001)
Collins v. Colonial Penn Insurance
778 A.2d 899 (Supreme Court of Connecticut, 2001)
Sanchez v. Capitol Region Education Coun., No. Cv 00 0598554 (Apr. 6, 2001)
2001 Conn. Super. Ct. 5018 (Connecticut Superior Court, 2001)
Trustees, Scsu v. Morin Brothers Auction, No. Cv 00 0594471 (Nov. 6, 2000)
2000 Conn. Super. Ct. 13983 (Connecticut Superior Court, 2000)
Commissioner of Transport. v. Capone, No. Cv 96 039 32 89 (Sep. 29, 2000)
2000 Conn. Super. Ct. 11840 (Connecticut Superior Court, 2000)
State v. L. F. Pace Construction, No. Cv 99 058 89 53 (Sep. 24, 1999)
1999 Conn. Super. Ct. 12996 (Connecticut Superior Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
737 A.2d 398, 250 Conn. 553, 1999 Conn. LEXIS 310, Counsel Stack Legal Research, https://law.counselstack.com/opinion/department-of-public-works-v-ecap-construction-co-conn-1999.