Bacon Construction Co. v. Department of Public Works

987 A.2d 348, 294 Conn. 695, 2010 Conn. LEXIS 22
CourtSupreme Court of Connecticut
DecidedFebruary 9, 2010
DocketSC 18198
StatusPublished
Cited by37 cases

This text of 987 A.2d 348 (Bacon Construction Co. v. Department of Public Works) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bacon Construction Co. v. Department of Public Works, 987 A.2d 348, 294 Conn. 695, 2010 Conn. LEXIS 22 (Colo. 2010).

Opinion

Opinion

ZARELLA, J.

The defendant, the department of public works, appeals 1 from the judgment of the trial court granting the application of the plaintiff, Bacon Construction Company, Inc., to confirm an arbitration award for damages relating to a public works contract between the parties and denying the defendant’s motion to vacate the award, and from the court’s denial of the defendant’s motion to dismiss the application to confirm. The defendant claims that the trial court improperly accepted the arbitrator’s determination regarding the arbitrability of the plaintiffs claims and, specifically, the arbitrator’s interpretation of General *698 Statutes § 4-61 2 and conclusion that the plaintiffs claims had been timely asserted under that statute. The defendant claims that it therefore follows that (1) the trial court and this court lack subject matter jurisdiction because the plaintiffs claims are barred by the doctrine of sovereign immunity, (2) the plaintiffs claims are not *699 arbitrable, and (3) the award does not conform to the submission. The plaintiff responds that (1) the defendant is not entitled to judicial review of whether the plaintiffs claims are arbitrable under § 4-61 because the defendant submitted the issue of arbitrability to the arbitrator without objection, and (2) the trial court properly granted the plaintiffs application to confirm the award because the award conformed to the submission. We affirm the judgment of the trial court.

The record reveals the following relevant facts and procedural history. 3 On May 13, 1992, the plaintiff and the defendant entered into a contract pursuant to which the plaintiff agreed to perform masonry and plank work in connection with the construction of a correctional facility in Niantic. The plaintiff was to commence work on June 1,1992, and the contract provided for an overall project duration of 300 calendar days. The plaintiffs work on the project required coordination with various other contractors. Coordination was the responsibility of the defendant, which delegated that responsibility to its construction manager, Tishman Construction Corporation (Tishman). Tishman failed to schedule and coordinate the contractors properly, and, as a result, the plaintiff was delayed in performing its work. Ultimately, the plaintiff remained at the work site until November, 1993, well past the 300 day duration provided for in the contract.

Early on in the project, the plaintiff complained to the defendant that it would be incurring additional costs due to delays and issued to the defendant various notices of claims for reimbursement of such costs. The *700 defendant initially disputed the plaintiffs claims but eventually, in October, 1994, authorized the issuance of several change orders that approved contract payment for the plaintiffs claims. On November 8, 1994, Tishman advised the plaintiff to submit two requisitions for payment, one for the value of the outstanding contract work, adjusted by the change orders, and the second for the retainage. 4 In response, on November 10, 1994, the plaintiff submitted requisitions for payment in accordance with Tishman’s directive. In December, 1994, the defendant issued a check to the plaintiff for the first requisition but did not pay the retainage.

In April, 1995, the defendant advised the plaintiff that it would issue final payment in exchange for a release in its favor. On May 22, 1995, the plaintiff gave the defendant a release, but the defendant subsequently failed to pay the plaintiff the retainage. The plaintiff sent letters to the defendant in June and July, 1995, advising that the release had been issued on the basis of the defendant’s representation that it would issue the final payment. The defendant did not respond to these letters.

In March, 1996, the plaintiff again sent a letter to the defendant, advising that if it did not pay the balance in full, the plaintiff would take legal action. This letter also went unanswered. In August, 1996, however, the defendant advised the plaintiff that some of the buildings that the plaintiff had worked on were leaking due to the plaintiffs allegedly defective workmanship. In response, the plaintiff submitted a quote to perform the repair work, agreeing to absorb one third of the cost. *701 The plaintiff performed the work and submitted an invoice for two thirds of its cost. The defendant did not pay that invoice.

Having received no satisfaction from its letters to the defendant seeking payment in the years that followed, the plaintiff submitted a notice of claim to the defendant on October 1, 2004, pursuant to § 4-61 (b). 5 Thereafter, on or about August 1, 2005, the plaintiff filed a demand for arbitration, seeking damages for the following: (1) lost productivity arising from the delay that required the plaintiff to remain on site after the project completion date; (2) additional expenses incurred as a result of being forced to work during the winter of 1993; (3) reimbursement for the settlement of a delay claim asserted against the plaintiff by one of its subcontractors; (4) lost profits and overhead expenses; (5) payment of the outstanding contract balance; (6) payment for the repair work performed in 1996; and (7) prejudgment interest.

In April, 2006, the arbitrator appointed to decide the parties’ dispute conducted a preliminary telephone conference with the parties, during which the defendant asserted that the arbitrator lacked authority to consider the plaintiff’s claims under § 4-61 because the plaintiff had not filed notice of its claim and had not commenced the arbitration within the statute’s time limitations. The defendant then requested that the arbitrator decide the issue of his authority to hear the plaintiffs claims before proceeding further. Thereafter, the arbitrator ordered that the evidentiary hearings be bifurcated. In the initial phase of the proceedings, the arbitrator was to decide the defendant’s affirmative defenses of (1) sovereign *702 immunity based on the plaintiffs alleged failure to comply with the time limitations set forth in § 4-61, (2) release, and (3) settlement by accord and satisfaction. In the second phase, the arbitrator was to decide the merits of the plaintiffs claims. In an answering statement dated October 12, 2006, the defendant stated in relevant part: “The actual issues in this proceeding are [the plaintiffs] delay and disruption claims, and [the defendant’s] special defenses that: [the plaintiffs] claims are barred by the doctrine of sovereign immunity; [the plaintiff] released [the defendant] from its claims; and [the plaintiff] settled its claims with [the defendant]. Those issues may be heard and fully and finally determined by this arbitration.

“This approach is precisely what the parties anticipated at the outset of this arbitration. . . .”

On November 15 and 16, 2006, the arbitrator conducted the initial phase of the evidentiary hearings.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Autumn View, LLC v. Planning & Zoning Commission
193 Conn. App. 18 (Connecticut Appellate Court, 2019)
Garlock v. 3DS Properties
303 Neb. 521 (Nebraska Supreme Court, 2019)
Garlock v. 3DS Props., L. L.C.
303 Neb. 521 (Nebraska Supreme Court, 2019)
Bd. of Educ. of the Town of New Milford v. New Milford Educ. Ass'n
205 A.3d 552 (Supreme Court of Connecticut, 2019)
Norris v. Town of Trumbull
201 A.3d 1137 (Connecticut Appellate Court, 2019)
Com. v. Uravage, M.
Superior Court of Pennsylvania, 2018
Arciniega v. Feliciano
184 A.3d 1202 (Supreme Court of Connecticut, 2018)
Dept. of Transportation v. White Oak Corp.
Supreme Court of Connecticut, 2015
State v. Bacon Construction Co.
Connecticut Appellate Court, 2015
Morneau v. State
Connecticut Appellate Court, 2014
Cuozzo v. Town of Orange
82 A.3d 647 (Connecticut Appellate Court, 2013)
Department of Transportation v. White Oak Corp.
62 A.3d 599 (Connecticut Appellate Court, 2013)
Rizzo v. Mohegan Tribal Gaming Authority
12 Am. Tribal Law 239 (Mohegan Gaming Disputes Trial Court, 2012)
City of New Britain v. AFSCME, COUNCIL 4
43 A.3d 143 (Supreme Court of Connecticut, 2012)
Perez-Dickson v. City of Bridgeport
43 A.3d 69 (Supreme Court of Connecticut, 2012)
Directory Assistants, Inc. v. Big Country Vein, L.P.
39 A.3d 777 (Connecticut Appellate Court, 2012)
Markley v. Department of Public Utility Control
23 A.3d 668 (Supreme Court of Connecticut, 2011)
Kubala v. Hartford Roman Catholic Diocesan Corp.
41 A.3d 351 (Connecticut Superior Court, 2011)
State v. Bacon Construction Co.
15 A.3d 147 (Supreme Court of Connecticut, 2011)
C. R. Klewin Northeast, LLC v. State
9 A.3d 326 (Supreme Court of Connecticut, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
987 A.2d 348, 294 Conn. 695, 2010 Conn. LEXIS 22, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bacon-construction-co-v-department-of-public-works-conn-2010.