State v. Bacon Construction Co.

15 A.3d 147, 300 Conn. 476
CourtSupreme Court of Connecticut
DecidedApril 5, 2011
DocketSC 18360
StatusPublished
Cited by7 cases

This text of 15 A.3d 147 (State v. Bacon Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State v. Bacon Construction Co., 15 A.3d 147, 300 Conn. 476 (Colo. 2011).

Opinion

[478]*478 Opinion

VERTEFEUILLE, J.

The named defendant, Bacon Construction Company, Inc.,1 appeals2 from the trial court’s decision overruling its objection, on collateral estoppel grounds, to the application for a prejudgment remedy filed by the plaintiff, the state of Connecticut, on behalf of its department of public works and its department of correction. The dispositive issue in this appeal is whether a party properly may appeal from such a ruling prior to a decision granting or denying the application for a prejudgment remedy. We conclude that a ruling precluding a collateral estoppel defense to an application for a prejudgment remedy does not come within our exception permitting an immediate appeal from the denial of a claim of collateral estoppel, and, accordingly, may not be appealed prior to a ruling on the application itself. We therefore dismiss the defendant’s appeal.

The record reveals the following undisputed facts and procedural history. In 1992, the defendant entered into a contract with the plaintiff to provide masonry services during the construction of fifteen buildings on the grounds of the York correctional institution. After completion of the contract, the defendant filed a demand for arbitration against the plaintiff, asserting [479]*479breach of contract and seeking money damages. In the course of the arbitration, the plaintiff stipulated that “for the purposes of this arbitration only: [the defendant] undertook the performance of its obligations under the [c]ontract in strict and full accordance with the plans, specifications, and general and special conditions of the contract and amendments thereto.” Relying partially on that stipulation, the arbitrator subsequently ruled in favor of the defendant and awarded damages. That award was confirmed by the Superior Court and the trial court’s judgment subsequently was affirmed by this court in a separate appeal. Bacon Construction Co. v. Dep t. of Public Works, 294 Conn. 695, 987 A.2d 348 (2010).

After the arbitrator’s initial award, but prior to the Superior Court’s confirmation of that award, the plaintiff brought the action underlying this appeal in the Superior Court. The action arises out of the same contract that was the subject of the arbitration and alleges that the defendant was negligent and breached its contract in the construction at York correctional institution. As part of the action, the plaintiff filed an application for a prejudgment remedy against the defendant seeking various forms of relief. See General Statutes § 52-278a et seq. In its objection to that application, the defendant asserted, inter alia, that, in light of the finding in the arbitrator’s award that the defendant had performed its obligations under the contract, the plaintiffs claims were barred by res judicata and/or collateral estoppel. The trial court thereafter overruled the defendant’s objection. This appeal followed.

After the parties had filed their initial briefs in this court, we ordered the parties to submit supplemental briefs addressing the following questions: “Should Convalescent Center of Bloomfield, Inc. v. Dept. of Income Maintenance, 208 Conn. 187, [194—95, 544 A.2d 604] (1988), which permits an immediate appeal from the [480]*480denial of a claim of collateral estoppel, be overruled?” and “If Convalescent Center of Bloomfield, Inc. ... is not overruled, is the denial of a defense of collateral estoppel issued in the context of a prejudgment remedy proceeding an appealable final judgment?” We now assume, without deciding, that Convalescent Center of Bloomfield, Inc., should not be overruled,3 and we answer the second question in the negative. Accordingly, we dismiss the present appeal for lack of a final judgment.4

We begin by setting forth the applicable standard of review. “The lack of a final judgment implicates the subject matter jurisdiction of an appellate court to hear an appeal. A determination regarding . . . subject matter jurisdiction is a question of law . . . [over which we exercise plenary review].” (Internal quotation marks omitted.) Pritchard v. Pritchard, 281 Conn. 262, 270, 914 A.2d 1025 (2007). “We commence the discussion of our appellate jurisdiction by recognizing that there is no constitutional right to an appeal. . . . Unless a specific right to appeal otherwise has been provided by statute, we must always determine the threshold question of whether the appeal is taken from a final judgment before considering the merits of the claim.” (Citations omitted; internal quotation marks omitted.) Palmer v. Friendly Ice Cream Corp., 285 Conn. 462, 466-67, 940 A.2d 742 (2008). Pursuant to well settled [481]*481law, however, “[a]n . . . interlocutory order is appeal-able in two circumstances: (1) where the order or action terminates a separate and distinct proceeding, or (2) where the order or action so concludes the rights of the parties that further proceedings cannot affect them.” State v. Curcio, 191 Conn. 27, 31, 463 A.2d 566 (1983); see also State v. Bell, 179 Conn. 98, 99, 425 A.2d 574 (1979).

In Convalescent Center of Bloomfield, Inc. v. Dept. of Income Maintenance, supra, 208 Conn. 188-89, this court heard an appeal from a ruling of the trial court determining that the defendant agency improperly had concluded that the plaintiff was collaterally estopped from rearguing an issue that was adversely decided in a previous administrative proceeding that was not subject to judicial review. A final judgment question arose because the trial court had remanded the case to the agency to consider the plaintiffs claims. Id., 192. This court in Convalescent Center of Bloomfield, Inc., relied on the second prong of Curcio in reaching the conclusion that rejection of a collateral estoppel defense in an administrative proceeding was “ripe for immediate appellate review. Further proceedings on the substantive merits of the plaintiffs’ claim . . . cannot affect the rights of the parties with respect to collateral estoppel. Indeed, to postpone appellate review . . . would defeat the very purpose that collateral estoppel is intended to serve. [T]he basic proposition . . . has always been essentially the same: A party should not be allowed to relitigate a matter that it already had opportunity to litigate. ... If the defendant is correct that the plaintiffs are precluded from relitigating their entitlement to reimbursement, it would be unfair to require the defendant to expend its resources to defeat the plaintiffs’ claims on the merits. We have held an interlocutory order to be final for purposes of appeal if it involves a claimed right the [482]*482legal and practical value of which would be destroyed if it were not vindicated before trial.” (Citation omitted; internal quotation marks omitted.) Id., 194.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

U.S. Bank National Assn. v. Crawford
Supreme Court of Connecticut, 2019
A1Z7, LLC v. Dombek
205 A.3d 740 (Connecticut Appellate Court, 2019)
Blakely v. Danbury Hospital
150 A.3d 1109 (Supreme Court of Connecticut, 2016)
Cefaratti v. Aranow
141 A.3d 752 (Supreme Court of Connecticut, 2016)
State v. Bacon Construction Co.
Connecticut Appellate Court, 2015
People's United Bank v. Kudej
39 A.3d 1139 (Connecticut Appellate Court, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
15 A.3d 147, 300 Conn. 476, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-v-bacon-construction-co-conn-2011.