C. R. Klewin Northeast, LLC v. State

9 A.3d 326, 299 Conn. 167, 2010 Conn. LEXIS 442, 2010 WL 4909978
CourtSupreme Court of Connecticut
DecidedDecember 7, 2010
DocketSC 18609
StatusPublished
Cited by16 cases

This text of 9 A.3d 326 (C. R. Klewin Northeast, LLC v. State) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C. R. Klewin Northeast, LLC v. State, 9 A.3d 326, 299 Conn. 167, 2010 Conn. LEXIS 442, 2010 WL 4909978 (Colo. 2010).

Opinion

Opinion

ROGERS, C. J.

This appeal requires us to determine what constitutes adequate notice of a claim under Gen *169 eral Statutes § 4-61 (a), 1 a provision that waives the state’s sovereign immunity to allow actions against the state for disputes arising from construction contracts. The plaintiff, C. R. Klewin Northeast, LLC, appeals 2 from the trial court’s judgment in favor of the defendant, the *170 state of Connecticut, following the court’s dismissal of the plaintiffs complaint. In dismissing the complaint, the trial court reasoned that, because the plaintiff had failed to comply properly with the notice requirement of § 4-61 (a), its claim against the state was barred by sovereign immunity and, therefore, the court lacked subject matter jurisdiction. We agree with the plaintiff that the trial court improperly concluded that the notice given by the plaintiff was inadequate and, accordingly, reverse the court’s judgment.

The following facts, which were found by the trial court following an evidentiary hearing, 3 and procedural history are relevant to this appeal. On October 6, 1998, the plaintiff entered into a contract with the state department of public works (department) to construct or alter certain buildings at Manchester Community College. While performing the contract, the plaintiff encountered various delays and change orders that caused it to incur additional expenses.

On August 31,2001, approximately nine months after the completion of the project, 4 the plaintiff sent Richard Piotrowski, the department’s bureau chief of facilities, design and construction, a detailed communication requesting that it be paid an additional $2,678,256 for contract overruns. 5 On April 15, 2004, after attempts to *171 obtain compensation for the overruns failed, Michael D’Amato, the plaintiffs president, hand delivered a letter to James T. Fleming, the department’s commissioner. The April 15, 2004 letter began by “requesting] [Fleming’s] assistance in resolving an issue that has been pending since August 31, 2001,” and proceeded to identify the contract, project and amount and cause of the overruns. 6 After referring to the August 31, 2001 submission to the department and detailing the plaintiffs futile efforts to receive payment despite repeated assurances that the submission was being processed, 7 the plaintiff concluded its letter by emphasizing that it “has been extremely patient waiting for payment. We have not submitted a claim requesting interest, home office overhead or other items. We have worked within the system and have followed all the rules. We have been out of pocket more than $2,000,000 since Novem *172 ber, 2000. This has caused a significant impact on our business. All we ask is to be treated fairly and honestly and that payment due us be made.”

Following receipt of the plaintiffs April 15, 2004 letter, Fleming directed David O’Heam, the department’s deputy commissioner, to request additional documentation from the plaintiff and, thereafter, to meet with the plaintiff to discuss its request for additional payment. In an April 28, 2004 letter to D’Amato, O’Heam stated: “We have located your original submission of August 31,2001, and I have asked the project manager to review the notebook and comment.” The plaintiff replied on May 4, 2004, by providing a copy of a change order proposal dated March 14, 2002, and Joel Baranowski, a state project manager, responded on June 7, 2004, with a list of questions. D’Amato, O’Heam and Baranow-ski then met in September, 2004, to discuss the plaintiffs request. The minutes of that meeting reflected that the plaintiff had hired a claims consultant who valued the claim at more than $5 million, but that the plaintiff was willing to accept $1.2 million in compromise. On September 20, 2004, Fleming contacted Marc Ryan, the secretary of the office of policy and management, to recommend discussion of the plaintiffs claim, and both Fleming and the attorney general recommended to Governor M. Jodi Rell (governor) that the plaintiff be paid. On March 8, 2005, the governor authorized the department to settle the plaintiffs claim for $1.2 million. 8 Nevertheless, the plaintiff was never paid.

On November 27, 2007, the plaintiff filed the present action pursuant to § 4-61 (a). 9 On January 28, 2008, the *173 state filed a motion to dismiss the action for lack of subject matter jurisdiction. Specifically, the state claimed that the court lacked jurisdiction because the plaintiff had failed to comply with the notice provision of § 4-61 (a). The plaintiff objected to the motion to dismiss, claiming that it had given the requisite notice, and requested a hearing to resolve the factual dispute. The trial court heard oral argument and received evidence on October 30, 2008, and held a hearing on November 25, 2008, at which witnesses testified and further evidence was submitted.

Thereafter, the trial court granted the state’s motion to dismiss, concluding that the state had not received sufficient statutory notice of the plaintiffs claim. As to the plaintiffs August 31,2001 communication, the court noted that it had not been delivered to Fleming, who was the head of the department, as required by § 4-61 (a). 10 As to the April 15, 2004 letter, the court reasoned that “[n]o reference to any intent to pursue a claim, pursuant to § 4-61, or by suit or arbitration, is contained in this letter.” The trial court analogized to jurisprudence concerning notice provisions in other statutes unrelated to state contracts and held that, “under § 4-61, providing the head of the agency with details about a request for an adjustment to a contract or about a contract dispute is insufficient. A purported notice is insufficient under § 4-61 if it lacks an essential element: notice of intent to pursue a claim for damages, either by an action in court or through an arbitration claim.” *174 The trial court acknowledged testimony from both Fleming and O’Heam confirming “that, in 2004, [the plaintiff] was claiming that the state owed [the plaintiff] money on the [Manchester Community College] project, and provided information in support of its claim to [the department]; and that [the department] conducted an investigation which led to the recommended settlement,” but concluded that the officials’ testimony did “not amount to evidence that [the plaintiff] provided a notice of claim that met the statutory requirements.” The trial court concluded further that the April 15, 2004 letter did not provide the factual basis for the plaintiffs claim as required by § 4-61 (a). The trial court then dismissed the plaintiffs complaint. This appeal followed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rainbow Housing Corp. v. Cromwell
340 Conn. 501 (Supreme Court of Connecticut, 2021)
Borelli v. Renaldi
Supreme Court of Connecticut, 2021
Graham v. Friedlander
334 Conn. 564 (Supreme Court of Connecticut, 2020)
Praisner v. State
208 A.3d 667 (Connecticut Appellate Court, 2019)
Dept. of Transportation v. White Oak Corp.
Supreme Court of Connecticut, 2015
Department of Transportation v. White Oak Corp.
62 A.3d 599 (Connecticut Appellate Court, 2013)
Estate of Bochicchio v. Quinn
46 A.3d 239 (Connecticut Appellate Court, 2012)
Rana v. Terdjanian
46 A.3d 175 (Connecticut Appellate Court, 2012)
Canty v. Otto
41 A.3d 280 (Supreme Court of Connecticut, 2012)
Brouillard v. Connecticut Siting Council
38 A.3d 174 (Connecticut Appellate Court, 2012)
Housatonic Railroad v. Commissioner of Revenue Services
21 A.3d 759 (Supreme Court of Connecticut, 2011)
Roger Sherman Liberty Center, Inc. v. Williams
28 A.3d 1026 (Connecticut Superior Court, 2011)
Peruta v. Commissioner of Public Safety
20 A.3d 691 (Connecticut Appellate Court, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
9 A.3d 326, 299 Conn. 167, 2010 Conn. LEXIS 442, 2010 WL 4909978, Counsel Stack Legal Research, https://law.counselstack.com/opinion/c-r-klewin-northeast-llc-v-state-conn-2010.