State v. L. F. Pace Construction, No. Cv 99 058 89 53 (Sep. 24, 1999)

1999 Conn. Super. Ct. 12996
CourtConnecticut Superior Court
DecidedSeptember 24, 1999
DocketNo. CV 99 058 89 53
StatusUnpublished

This text of 1999 Conn. Super. Ct. 12996 (State v. L. F. Pace Construction, No. Cv 99 058 89 53 (Sep. 24, 1999)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State v. L. F. Pace Construction, No. Cv 99 058 89 53 (Sep. 24, 1999), 1999 Conn. Super. Ct. 12996 (Colo. Ct. App. 1999).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]

MEMORANDUM OF DECISION ON PLAINTIFF'S APPLICATION FOR TEMPORARY INJUNCTION
This is an action brought by the State of Connecticut, Department of Public Works ("State") to enjoin defendant L. F. Pace Construction Company ("Pace") from proceeding in on arbitration scheduled before the defendant American Arbitration Association ("AAA"). On May 10, 1999 Pace moved to stay plaintiffs motion for temporary injunction so that the arbitration could proceed. Hearings were held before this court on July 2 and 7, 1999 and closing arguments heard on August 18, with additional briefs filed up to August 28, 1999. CT Page 12997

I
The basic facts are not in dispute. The State invited bids for certain renovations and additions to Memorial Hall, Western Connecticut State University in Danbury (Conn. Project No. BD-RD-31) on October 15, 1993. A bid opening took place on December 8, 1993 at which Pace was the third low bidder. After the two lower bids had been rejected for various reasons, there ensued protracted negotiations culminating in the execution of a contract for construction of the project between the state and Pace dated September 29, 1994. Required performance and labor and material bonds were filed. After Pace commenced work under the contract a number of problems and disputes arose resulting in a letter of termination by the State on April 9, 1996. On October 24, 1996, Pace commenced suit against the State (L.F. PaceContribution. Inc. v. State of Connecticut, No. CV 960337366 S) claiming the termination was improper and after trial Judge Melville sustained this claim. Thereafter, on May 1, 1997 the parties entered a termination agreement essentially assigning the uncompleted contract to a third party. On March 26, 1998 Pace made a formal demand for arbitration of issues in dispute under the original contract, which was rejected by the state followed by an amended demand for arbitration by Pace dated October 30, 1998 which was also rejected. Thereafter, the State commenced this action, claiming Pace had no right to demand arbitration because it was a dissolved corporation on September 29, 1994.

At trial, it appeared that the secretary of state had sent a notice of intent dated October 29, 1993 to dissolve defendant corporation for failure to file an annual report followed by a notice of dissolution dated February 4, 1994. Lawrence E. Pace and Mark M. Pace incorporators and officers of Pace testified that they were not aware of these notifications until advised by their attorney, approximately August 1995. Presumably the attorney had learned of the dissolution from the office of the Attorney General. Thereafter, the officers and their attorney took reasonably prompt measures to obtain reinstatement which was granted by the secretary of state on December 26, 1995.

II
The State claims that Pace's right to claim arbitration depends on the existence of a "construction contract" under General Statutes § 4-61 (a), which reads in pertinent part as CT Page 12998 follows:

(a) Any person, firm or corporation which has entered into a contract with the state, acting through any of its departments, commissions or other agencies, for the design, construction, construction management, repair or alteration of any highway, bridge, building or other public works of the state or any political subdivision of the state may, in the event of any disputed claims under such contract or claims arising out of the awarding of a contract by the Commissioner of Public Works, bring an action against the state to the superior court for the judicial district of Hartford for the purpose of having such claims determined.

Subsection (b) of this statute gives "any such person, firm or corporation having a claim under subsection (a) may submit a demand for arbitration of such claim. . . .

The State does not dispute that the agreement of September 29, 1994 had all the elements of a construction contract under sub-section (a) but argues that Pace cannot claim arbitration because it was not a proper corporation at the time it filed its bid and signed the contract and for a long time afterward until its reinstatement in December, 1995. It argues that this statute, which creates an exception from the sovereign immunity of the State, must be narrowly construed so as to exclude from its coverage any party which claims to be a corporation but in fact has been dissolved. It claims, therefore, that there was no "construction contract" under the statute because there was no legal party to any construction contract with the State.

III
Pace claims that despite the dissolution by the Secretary of State, that it never lost its corporate status and was at least a de facto corporation at the time it entered the contract.

The State in its briefs refers variously to Pace as being "non-existent", "not in good standing", "defunct", and "dissolved" at the time of contract. It denies that Pace was a "de facto" corporation because there was no evidence of good faith efforts by Pace to effectuate a prompt reinstatement, pointing to the records of notice of dissolution in the office of the Secretary of State and the filing of annual reports for other corporations owned or controlled by the Pace family. But that CT Page 12999 evidence does not prove a lack of good faith or some devious-purpose on the part of Pace's officers. There was nothing to gain on their part by failing to file an annual report for Pace and their filing of other corporation reports during the same period tends to show at most an inexplicable inadvertence on their part. Two corporate officers testified they took immediate steps to reinstate the corporation on learning of its dissolution; there was no evidence to the contrary.

In Clark-Franklin-Kingston Press. Inc. v. Romano,12 Conn. App. 121, 125 (1987) our Appellate court in denying the personal liability of defendant officers for a corporate debt after the corporation has been dissolved for failure to file two annual reports held that the corporation continued to function as a de facto corporation because the individual defendants had made good faith efforts on learning of its dissolution and because they conducted business as a corporation believing they had a right to do so that "it would be inequitable to impose personal liability upon them due merely to a technical defect in the reinstatement process." The appellate court relies on various authorities which define "de facto" corporation, all of which would seem to apply to defendant in this case. See. Yale Cooperative Corp. v. Rogin,133 Conn. 563, 566 (1947).

The State was unable to show that it was prejudiced in any way by the status of Pace as a dissolved corporation during any portion of the period involved. Pace furnished all required performance and labor and material bonds when it entered the agreement on September 29, 1994 and performed services under the contract for which it was paid over a million dollars prior to termination. No claim has been made that the Bonds furnished in connection with the contracts were invalid or otherwise put into jeopardy by the interim period of corporate dissolution. At the time of the subsequent termination agreement on May 1, 1997, Pace had long been reinstated.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Board of Education v. Frey
392 A.2d 466 (Supreme Court of Connecticut, 1978)
Yale Co-Operative Corporation v. Rogin
53 A.2d 383 (Supreme Court of Connecticut, 1947)
White v. Kampner
641 A.2d 1381 (Supreme Court of Connecticut, 1994)
Department of Public Works v. Ecap Construction Co.
737 A.2d 398 (Supreme Court of Connecticut, 1999)
Clark-Franklin-Kingston Press, Inc. v. Romano
529 A.2d 240 (Connecticut Appellate Court, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
1999 Conn. Super. Ct. 12996, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-v-l-f-pace-construction-no-cv-99-058-89-53-sep-24-1999-connsuperct-1999.