New England Rock Services, Inc. v. Empire Paving, Inc.

731 A.2d 784, 53 Conn. App. 771, 1999 Conn. App. LEXIS 244
CourtConnecticut Appellate Court
DecidedJune 15, 1999
DocketAC 17818
StatusPublished
Cited by15 cases

This text of 731 A.2d 784 (New England Rock Services, Inc. v. Empire Paving, Inc.) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
New England Rock Services, Inc. v. Empire Paving, Inc., 731 A.2d 784, 53 Conn. App. 771, 1999 Conn. App. LEXIS 244 (Colo. Ct. App. 1999).

Opinion

Opinion

SCHALLER, J.

The defendants, Empire Paving, Inc. (Empire), and its bonding company, American Insurance Company, doing business as Fireman’s Fund Insurance Company (Fireman’s Fund), appeal from the judgment of the trial court awarding damages to the named plaintiff, New England Rock Services, Inc. (Rock Services),1 under a contract between the parties. The principal issue on appeal is whether the trial court improperly concluded that an agreement made by the parties on December 9, 1995, modified an earlier contract executed by them on October 26, 1995. We affirm the judgment of the trial court.

The following facts are relevant to the disposition of this appeal. On October 26,1995, Empire entered into a contract with Rock Services under which Rock Services would provide drilling and blasting services as a subcontractor on the Niles Hill Road sewer project on which Empire was the general contractor and the city of New London was the owner.2 Pursuant to the contract, Rock [773]*773Services agreed to drill and blast a certain amount of rock encountered on the sewer project. In return, Rock Services was to be paid an agreed upon price of $29 per cubic yard with an estimated amount of 5000 cubic yards, or on a time and materials basis, whichever was less.

On October 31, 1995, Rock Services commenced work on the project. From the beginning, Rock Services experienced a number of problems with the project. The primary obstacle was the presence of a heavy concentration of water on the site. The water problem hindered Rock Services’ ability to complete its work as anticipated. The trial court found that it was the custom and practice in the industry for the general contractor to control the water on the site and that, on this particular job, Empire failed to control the water on the site properly. In an effort to mitigate the water problem, Rock Services attempted to “load behind the drill,” a process that allows a blaster to load the drilled hole with a charge immediately after the hole is drilled, before water has the opportunity to seep into the hole. The city fire marshal, however, refused to allow Rock Services to employ this method of drilling. See Regs., Conn. State Agencies § 29-349-238.3 Thereafter, in order to complete its work, Rock Services was compelled to use the more costly and time consuming method of casing the blasting hole, a process that requires the blaster to drive a plastic casing down into the drilled hole to prevent seepage.

In late November, 1995, Rock Services advised Empire that it would be unable to complete the work as anticipated because of the conditions at the site and [774]*774requested that Empire agree to amend the contract to allow Rock Services to complete the project on a time and materials basis. On December 8, 1995, Empire signed a purchase order that modified the original agreement. The modification required Empire to pay for the blasting work on a time and materials basis for the remainder of the project. Rock Services, thereafter, completed its work on the project.

Upon completion of the work, Empire refused to pay Rock Services for the remaining balance due on the time and materials agreement in the amount of $58,686.63,4 and Rock Services instituted this action. The trial court concluded that the later purchase order was a valid and enforceable modification of the earlier contract.5 The trial court found that the parties intended the purchase order to modify the earlier agreement and that Empire’s assent to the modification was not made under duress but, rather, was a calculated business decision. After finding Empire’s withholding of the amount due to Rock Services wrongful,6 the trial court awarded Rock Services damages in the amount of $58,686.63, plus interest and costs. This appeal followed.

On appeal, Empire claims that the trial court improperly found that the later purchase order was a valid and enforceable modification of the earlier contract. Specifically, Empire claims that the later agreement [775]*775lacked the requisite consideration to be a valid and enforceable modification of the earlier contract. We disagree.7

“As an appellate court, our review of trial court decisions is limited to determining whether their legal conclusions are legally and logically correct, [and] supported by facts set out in the memorandum of decision. Pandolphe’s Auto Parts, Inc. v. Manchester, 181 Conn. 217, 221-22, 435 A.2d 24 (1980).”Harris Calorific Sales Co. v. Manifold Systems, Inc., 18 Conn. App. 559, 563, 559 A.2d 241 (1989). Whether a contract or a subsequent modification exists is a question of fact for the court to determine. Id.; see also Three S. Development Co. v. Santore, 193 Conn. 174, 177-78, 474 A.2d 795 (1984); Randolph Construction Co. v. Kings East Carp., 165 Conn. 269, 277, 334 A.2d 464 (1973); Thermoglaze, Inc. v. Morningside Gardens Co., 23 Conn. App. 741, 745, 583 A.2d 1331, cert. denied, 217 Conn. 811, 587 A.2d 153 (1991). “If the factual basis of the court’s decision is challenged, our review includes determining whether the facts set out in the memorandum of decision are supported by the evidence or whether, in light of the evidence and the pleadings in the whole record, those facts are clearly erroneous.” (Internal quotation marks omitted.) Harris Calorific Sales Co. v. Manifold Systems, Inc., supra, 563.

In concluding that the modification was valid and enforceable, the trial court determined that the later agreement was supported by sufficient consideration. The trial court relied on Harris Calorific Sales Co. v. Manifold Systems, Inc., supra, 18 Conn. App. 564, to support its determination that the parties’ mutual promises were sufficient consideration to bind them to the [776]*776modification. We conclude that Harris Calorific Sales Co. does not support the finding of modification under the circumstances of this case. We do conclude, however, that the trial court’s disposition of the case is correct. “Where the trial court reaches a correct decision but on mistaken grounds, this court has repeatedly sustained the trial court’s action if proper grounds exist to support it.” Morris v. Costa, 174 Conn. 592, 597-98, 392 A.2d 468 (1978).

“The doctrine of consideration is fundamental in the law of contracts, the general rule being that in the absence of consideration an executory promise is unenforceable.” State National Bank v. Dick, 164 Conn. 523, 529, 325 A.2d 235 (1973). While mutual promises may be sufficient consideration to bind parties to a modification; Harris Calorific Sales Co. v. Manifold Systems, Inc.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Village Mortgage Co. v. Garbus
201 Conn. App. 845 (Connecticut Appellate Court, 2020)
Willamette Management Associates, Inc. v. Palczynski
38 A.3d 1212 (Connecticut Appellate Court, 2012)
Harley v. Indian Spring Land Co.
3 A.3d 992 (Connecticut Appellate Court, 2010)
Kovacs Construction Corp. v. Water Pollution & Control Authority
992 A.2d 1157 (Connecticut Appellate Court, 2010)
Russell v. Russell
882 A.2d 98 (Connecticut Appellate Court, 2005)
Foster v. Longa, No. Cv 99 0425745 S (Feb. 25, 2003)
2003 Conn. Super. Ct. 2812 (Connecticut Superior Court, 2003)
Christian v. Gouldin
804 A.2d 865 (Connecticut Appellate Court, 2002)
Brookridge Funding Corp. v. Northwestern Human Services
175 F. Supp. 2d 355 (D. Connecticut, 2001)
Jarsen v. Gunther, No. Cv 00 71986 S (Apr. 12, 2001)
2001 Conn. Super. Ct. 5113 (Connecticut Superior Court, 2001)
Christian v. Gouldin, No. Cv99-0155219s (Jan. 30, 2001)
2001 Conn. Super. Ct. 1768 (Connecticut Superior Court, 2001)
Garofalo v. Squillante
760 A.2d 1271 (Connecticut Appellate Court, 2000)
Brookridge Funding v. Dist. of Columbia, No. Cv99 033 78 58 S (Sep. 5, 2000)
2000 Conn. Super. Ct. 10843 (Connecticut Superior Court, 2000)
Keefe v. Norwalk Cove Marina, Inc.
749 A.2d 1219 (Connecticut Appellate Court, 2000)
New England Rock Services, Inc. v. Empire Paving, Inc.
738 A.2d 658 (Supreme Court of Connecticut, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
731 A.2d 784, 53 Conn. App. 771, 1999 Conn. App. LEXIS 244, Counsel Stack Legal Research, https://law.counselstack.com/opinion/new-england-rock-services-inc-v-empire-paving-inc-connappct-1999.