Kovacs Construction Corp. v. Water Pollution & Control Authority

992 A.2d 1157, 120 Conn. App. 646, 2010 Conn. App. LEXIS 158
CourtConnecticut Appellate Court
DecidedApril 27, 2010
DocketAC 30143
StatusPublished
Cited by10 cases

This text of 992 A.2d 1157 (Kovacs Construction Corp. v. Water Pollution & Control Authority) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kovacs Construction Corp. v. Water Pollution & Control Authority, 992 A.2d 1157, 120 Conn. App. 646, 2010 Conn. App. LEXIS 158 (Colo. Ct. App. 2010).

Opinion

Opinion

ALVORD, J.

The defendant, the water pollution and control authority of the city of New Haven, appeals from the judgment, rendered after a court trial, in favor of the plaintiff, Kovacs Construction Corporation. On appeal, the defendant claims that the court improperly awarded the plaintiff a portion of its claimed damages *648 because the court failed to state, and the evidence failed to demonstrate, that the defendant had breached its contractual obligations. The plaintiff cross appeals from the judgment, claiming that the court improperly failed to award the plaintiff (1) the liquidated damages withheld by the defendant, (2) additional costs it incurred for site dewatering and other work it performed after December 2, 2004, and (3) prejudgment interest pursuant to General Statutes § 37-3a. We affirm the judgment of the trial court in part and reverse it in part.

The following facts were found by the court or are not disputed. In August, 2003, the parties entered into a construction contract in which the plaintiff agreed to renovate and upgrade two existing sewer pump stations located at Barnes Avenue and Quinnipiac Avenue in New Haven and to install related sewer piping and manholes at each site. Although the bid specifications for the project specifically required that all dewatering activities were to be performed from inside the excavations at both sites, the plaintiff bid the job on the assumption that the defendant ultimately would permit it to site dewater from outside of the excavation areas. 1 On the basis of this assumption, the plaintiff was able to reduce its total bid price significantly.

Following the competitive bidding process, the plaintiff was awarded the contract as the lowest qualified bidder. The bid signed by the plaintiff and the contract documents all compelled the plaintiff to adhere to the “excavation dewatering” requirement. The parties’ contract further provided that the plaintiff would not be entitled to extensions of time to complete the work or *649 to compensation for any change in work or extra costs unless certain requirements were met and certain procedures were followed. Two months after the contract was executed, Richard T. Kovacs, the plaintiffs chief executive officer, contacted one of the project engineers at Metcalf & Eddy, Inc. (M & E), 2 and informed him that the plaintiff wanted to deviate from the contract by site dewatering the project. 3 A few days later, at the first job meeting on October 8, 2003, the plaintiff agreed to excavation dewatering at both sites as required by the contract.

The Barnes Avenue site is the site at issue in these appeals. Construction at that site began in early 2004 and continued through the spring of that year. Throughout that time period, the plaintiff dewatered the area around the pump station from inside the excavation. Beginning in May, 2004, however, the plaintiff commenced the next phase, which was the installation of the yard piping within the trench area. At that point, by letter dated May 4, 2004, the plaintiff renewed its request to deviate from the contract’s excavation dewa-tering requirement. M & E immediately responded that site dewatering was not allowed by the contract. Nevertheless, a few weeks later, the plaintiff sent M & E a letter from Clarence Welti, the plaintiffs geotechnical engineer, in which he outlined a potential method of site dewatering. At a progress meeting held May 25, 2004, the parties discussed Welti’s recommendations for site dewatering. By correspondence dated June 3, 2004, M & E advised the plaintiff that a request for a change order to deviate from the contract’s excavation dewatering specifications had to be predicated on the *650 discovery of a physical condition at the site that was materially different from the conditions indicated in the contract. Nevertheless, M & E indicated that it would consider granting the request if the plaintiff complied with the four conditions identified in the letter from M & E dated October 6, 2003. 4

On July 6, 2004, the plaintiff sent a letter to M & E in which it claimed, for the first time, that it had encountered site conditions that were materially different from those represented in the contract documents. Although the plaintiff indicated in that letter that it wanted to implement site dewatering, it did not provide M & E with a proposed method or plan for the proposed site dewatering, nor did it address how it would satisfy the four conditions set forth in the October 6, 2003 letter. On July 22, 2004, the plaintiff submitted a letter to the defendant entitled “Claim and Protest Notification,” in which it indicated that it (1) would continue to work at the Barnes Avenue site “under protest” in accordance with the excavation dewatering requirement of the contract, (2) would file a claim for all additional costs incurred in connection with excavation dewatering and (3) would not accept responsibility for any damage caused by undermining or settlement of existing utilities resulting from the excavation dewater-ing method.

On November 29, 2004, however, the plaintiff unilaterally decided that the contract’s excavation dewatering method was “ ‘unsafe and commercially impracticable’ ” and ordered and installed a site dewatering system without the defendant’s authorization. Beginning December 2, 2004, the plaintiff proceeded to dewater the entire yard piping site from outside the excavation.

As a result of the many difficulties with the project at both sites, some of which were unforeseen, the contract *651 price was increased and the completion date extended on several occasions by approved change orders. A number of the plaintiffs requests for additional compensation, however, were denied, and the defendant did not grant all of the extensions of time requested for the delays in completing the project. The plaintiff substantially completed the project on May 18, 2005, which was 114 days beyond the final extension date. Accordingly, pursuant to § 307 of the contract, the defendant assessed the plaintiff $57,000 in liquidated damages for its failure to complete the work within the stipulated time. In addition, the defendant retained a balance of $9334.61 of the total contract amount as “ ‘unbilled retention.’ ”

On August 4, 2005, more than two months after the project was substantially completed, the plaintiff submitted a claim to the defendant seeking additional compensation for the dewatering problems at the Barnes Avenue site. Subsequently, on November 2, 2005, the plaintiff submitted an additional claim to the defendant for delay related costs it claimed it had incurred during the various extensions of time that had been granted through approved change orders. The plaintiffs requests were denied.

On February 8, 2006, the plaintiff filed the present action against the defendant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Village Mortgage Co. v. Garbus
201 Conn. App. 845 (Connecticut Appellate Court, 2020)
Chase Home Finance, LLC v. Scroggin
Connecticut Appellate Court, 2017
Ring v. Litchfield Bancorp
167 A.3d 462 (Connecticut Appellate Court, 2017)
Brusby v. Metropolitan District
Connecticut Appellate Court, 2015
Emerick v. Town of Glastonbury
74 A.3d 512 (Connecticut Appellate Court, 2013)
New Breed Logistics, Inc. v. Ct Indy Nh Tt, LLC
19 A.3d 1275 (Connecticut Appellate Court, 2011)
Caltabiano v. L & L Real Estate Holdings II, LLC
15 A.3d 1163 (Connecticut Appellate Court, 2011)
Kovacs Construction Corp. v. Water Pollution & Control Authority
297 Conn. 912 (Supreme Court of Connecticut, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
992 A.2d 1157, 120 Conn. App. 646, 2010 Conn. App. LEXIS 158, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kovacs-construction-corp-v-water-pollution-control-authority-connappct-2010.