Linz v. Schuck

67 A. 286, 106 Md. 220, 1907 Md. LEXIS 98
CourtCourt of Appeals of Maryland
DecidedJune 24, 1907
StatusPublished
Cited by48 cases

This text of 67 A. 286 (Linz v. Schuck) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Linz v. Schuck, 67 A. 286, 106 Md. 220, 1907 Md. LEXIS 98 (Md. 1907).

Opinion

Boyd, J.,

delivered the opinion of the Court.

The appellee sued the appellant on the common counts for a balance claimed to be due for work done and materials provided, etc., under the following circumstances: The appellant owned a house known as No. 3038 Elliott street, at the corner of Canton street in Baltimore City, which was built without a cellar, was not plastered or partitioned off on the second story, and the rear was arranged for a stable. The appellee entered into a contract in writing with the appellant which states: “Cellar to be dug under the entire store to the partition wall between kitchen and store to a depth of 7 feet, and walls to be underpinned with good hard brick laid in cement. * * •* cellar to be connected with sewer and cemented,” and provides for work to be done in the kitchen, the second story of the house and a number of other things not necessary to mention. It concludes, “I will do the work and furnish material for the sum of fifteen hundred dollars ($1,500).” The paper was drawn in the shape of an estimate or bid, but was *226 accepted by the appellant and the appellee identified it as his contract.

The appellee began the work in April, 1903. He gave the contract to build the cellar to a sub-contractor who started to excavate. The appellee thus described the conditions of the ground: “The house stood on a hard crust about three feet thick and the foundation of that house didn’t extend through that hard crust, it was built on that crust and the more we got through that the more we got into a swamp, like the bottom of an old creek, black, muddy stuff and soft and they tried to dig and dig and it all ran into this place and finally a big lump would cave off and fall in every now and then and they continued on that way to get a trench dug to connect the cellar with the sewer so we thought we could drain the place a little.” His foreman notified him that the house was cracking, and he then got lumber and drove “lagging” in to hold the ground. He testified that he notified Mr. Preston, the Building Inspector of the city, who went there with one of his assistants; that they “took sticks and shoved them down in the ground about fourteen feet deep, that Mr. Linz was present upon this occasion.”. He also said that Mr- Preston told him no cellar could be made and he should fill in what he had taken out and he stopped the work. He further testified that the appellant called on him “off and on” and wanted to see “whether we couldn’t make a cellar there; wouldn’t it be possible in some way to overcome it even if a small cellar.” They finally thought they “could make a little cellar to get so’me cellar there,” and he said “let the thing lay and we will drain the ground into the sewer and may be we can overcome it provided you pay the additional post and stand the consequences.” He demanded a writing from the appellant and he'said “his word was as good as mine, and if I put a cellar there he would see that I got pay for it; that he would pay for the additional work I was compelled to do to make a cellar.” In another place he stated; “He says if I was able to get a cellar'under there he would reimburse or pay me the additional cost, whatever it was, to get a cellar there; that the *227 house was no good to him without a cellar.” In October he went to work again, dug out eight feet, then drove poles down eight feet long, used “concrete and cement in there to form our footing” and went to great expense and trouble to make the cellar, under the new arrangement.

The appellant introduced evidence which tended to show that some of the trouble about the cellar was owing to the negligent way in which the appellee’s men did the work, and that the bad condition of the soil did not extend as deep as the appellee said it was, but there can be no doubt that the conditions were altogether different from what appeared on the surface or what was anticipated. The appellee also testified that before he made the offer he “wanted to know how the ground was and defendant took plaintiff in the cellar of his building” (which was on the opposite side of the street) “and he showed me he had a cellar dug there and it went all right, and the soil was nice and sound there on the other corner, and when I started I wouldn’t have any trouble, and I made my figures on his say so.” After the work was begun, the owner of the adjoining property sued the appellant and the appellee for damages to her house sustained by reason of the excavation, and the suit was compromised by the appellant buying the house and -the appellee agreeing to put it in proper condition. That was No. 3036 Elliott street.

The principal question in the case is whether the plaintiff was entitled to recover for the additional costs and expenses incurred, by reason of those conditions, on the promise of the appellant to pay him for them. The precise question for our consideration is presented by the plaintiff’s fifth prayer, which was granted. After referring to the written contract made in April or May, 1903, and the refusal of the plaintiff in June, 1903, to perform and complete said contract, the prayer further submitted to the jury to find whether “said refusal on the part of the plaintiff was induced by substantial and unforeseen difficulties in the performance, which would cast upon the plaintiff additional burden not anticipated by the parties when the contract was made, and if they further find that after said refusal *228 by the plaintiff, the defendant to induce the plaintiff to resume the work thus abandoned promised him to see him through and to stand the consequences, and that relying upon said promise the plaintiff completed the work, then their verdict may be for the plaintiff,” etc. That prayer seems to have followed quite closely the language used in King v. Duluth M. & N.Ry. Co., 61 Minn. 487 (s. c. 63 N. W. 1105), which case, notwitstanding unfavorable criticism by some writers, in our opinion announces a principle which is not only just and equitable,. but is easily reconcilable with the general rule that a promise to do, or actually doing, that which a party to a contract is already under legal obligation to do, is not a valid consideration to support the promise of the other party to the contract to pay additional compensation for such performance. In King v. Duluth, after stating that general rule, it is added: “In other words, a promise by one party to a subsisting contract to the opposite party to prevent a breach of the contract on his part is without consideration.” The Court then cited Ayers v. R. R. Co., 52 Iowa, 478; Linginfelder v. Brewing Co., 103 Mo. 578; Vanderbilt v. Schreyer, 91 N. Y. 392, and other cases, most of which are among those relied on by the appellant, as sustaining and illustrating the general rule which the Supreme Court of Minnesota unhesitatingly and emphatically approved of. Indeed the Court said that the doctrine of Monroe v. Perkins, 9 Pick. 305; Goebel v. Linn, 47 Mich. 489; Rogers v. Rogers, 139 Mass. 440; Bryant v. Lord, 19 Minn. 396, and Moore v. Locomotive Works, 14 Mich. 266, as it is frequently applied, did not commend itself to their judgment or sense of justice.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Questar Homes of Avalon, LLC v. Pillar Construction, Inc.
882 A.2d 288 (Court of Appeals of Maryland, 2005)
DirecTV, Inc. v. Mattingly
829 A.2d 626 (Court of Appeals of Maryland, 2003)
Allstate Insurance v. Stinebaugh
824 A.2d 87 (Court of Appeals of Maryland, 2003)
Berringer v. Steele
758 A.2d 574 (Court of Special Appeals of Maryland, 2000)
National School Studios, Inc. v. Mealey
126 A.2d 588 (Court of Appeals of Maryland, 1999)
Department of Public Safety & Correctional Services v. Ara Health Services, Inc.
668 A.2d 960 (Court of Special Appeals of Maryland, 1995)
McComas v. Criminal Injuries Compensation Board
594 A.2d 583 (Court of Special Appeals of Maryland, 1991)
Smith v. Smith
558 A.2d 798 (Court of Special Appeals of Maryland, 1989)
Lowey v. Watt
684 F.2d 957 (D.C. Circuit, 1982)
Miller v. United States Naval Institute
423 A.2d 283 (Court of Special Appeals of Maryland, 1980)
Raymond International, Inc. v. Baltimore County
412 A.2d 1296 (Court of Special Appeals of Maryland, 1980)
Majestic Builders Corp. v. Harris
598 F.2d 238 (D.C. Circuit, 1979)
Brian Construction & Development Co. v. Brighenti
405 A.2d 72 (Supreme Court of Connecticut, 1978)
Fran Realty, Inc. v. Thomas
354 A.2d 196 (Court of Special Appeals of Maryland, 1976)
Angel v. Murray
322 A.2d 630 (Supreme Court of Rhode Island, 1974)
n.sidney Nyhus v. Travel Management Corporation
466 F.2d 440 (D.C. Circuit, 1972)
Dowling v. Bruffey
291 A.2d 471 (Court of Appeals of Maryland, 1972)
Dewey Jordan v. MD.-NAT'L CAP. P. & P.
265 A.2d 892 (Court of Appeals of Maryland, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
67 A. 286, 106 Md. 220, 1907 Md. LEXIS 98, Counsel Stack Legal Research, https://law.counselstack.com/opinion/linz-v-schuck-md-1907.