START, C. J.

The respondents in March, 1893, entered into a contract with the appellant, which was executed on his behalf by his son and agent, Lane MacGregor, whereby they agreed to build for him a store building, according to certain plans and specifications, upon his lots in the city of Duluth, for the sum of $32,323.90. They commenced the work of erection April 1, and completed the building September 5, 1893, and the contract price was paid in full; but the respondents claimed payment for extra work, which being-refused, they brought this action. They claimed to recover the sum of $983 for the removal of certain rocks from the lots upon which the building was to be erected. Such claim is made under an alleged contract with the agent made after the original building contract was entered into. The appellant denied the making of this contract, and set up in his answer several counterclaims, only one of which is here material, it being a claim for $620 damages by reason of the failure of the respondents to complete the building within the time agreed. The verdict was for the respondents, in the sum of $517.15, which included the respondents’ claim for extra work, less one-half of the appellant’s counterclaim, and he appeals from an order denying his motion for a new trial. The assignments of error, summarized, are (1) that no competent evidence was offered to prove respondents’ cause of action; (2) that the whole of the counterclaim was proved by undisputed evidence, and should have been allowed.

1. The original building contract was executed on behalf of the-appellant by Lane MacGregor, by virtue of a power of attorney,, which, among other matters, contained the following provision: “I,. James W. MacGregor, * *' * appoint Lane MacGregor * * *■ my true and lawful attorney, for me, and in my place and stead, to act for me in all matters wherein I would be required to act in relation to signing contracts, accepting bond, and all other matters [200]*200relating to the erection, construction, leasing, renting, and hiring of a certain block to be erected for me upon lots 302 and 30á, block 3o, Duluth proper, according to certain plans and specifications drawn by Wangenstein and Bailley, architects.” The contract for the extra work was oral, and was made on behalf of the appellant by such agent; but the appellant claims that the agent was not authorized to make this oral contract for him, and that, eliminating the proof ■of this contract, there is no evidence in the case to support the respondents’ claim. The verdict establishes the fact that the oral ■contract was made, and the finding is fully supported by the evidence. This leaves for consideration the question of the authority •of the agent to make the contract.

The appellant claims that the power of attorney gave to the agent authority simply to sign contracts, not to make any oral contracts touching the business he was authorized to perform for his principal. This is too narrow a construction to give to the terms of the power, for it not only confers upon the agent the power to sign contracts relating to the erection and leasing of the building, but it further authorizes the agent to act for his principal in all other matters relating to the construction of the building, and make all contracts necessary to cause the building to be erected in accordance with the plans and specifications. If, in the work of construction, exigencies arose necessitating the making of further contracts in order to secure the completion of the building, it ■seems clear that the agent, under this power, would be authorized to make such contracts for his principal. The agent’s authority is not limited to the mechanical act of signing such contracts in reference to the erection of the building, for no contracts had been .agreed on when the power was given; and the only reasonable interpretation of the power is that the agent was authorized, not ■simply to sign, but to make, such contracts as might be necessary to begin, carry on, and complete the work intrusted to him by the appellant. The authority of the agent, however, does not rest alone ■upon the naked terms of the power; for, as we shall see as we proceed, the nature of the oral contract, the emergency which gave rise to it, the subsequent conduct of the parties in relation to it, .and .the benefits received by the appellant from the performance [201]*201of the contract by .the respondents, all strongly reinforce the authority conferred by the power, and leave no serious question as to the agent’s authority to make the contract for his principal.

2. The appellant further claims that there was no consideration to support the contráct, for the reason that the respondents were required, by the terms of their original contract, to. do the very work for which they claim pay under the subsequent contract; that their promise to do, and the doing by them of, that which they were under a previous valid obligation to do, furnish no consideration for his promise to pay for such performance. There are many cases holding that if one party to a contract refuse to perform it, unless promised some further pay or benefit than the contract provides, and such promise is made by the opposite party, it is binding. The decisions in these cases rest upon the proposition that the refusal to perform the previous contract subjects the party to such damages as the other party can show he is entitled to recover, but if he sees fit to waive this right, and makes the new promise, and the party refusing performs in reliance upon it, the first contract is waived, and the new one is binding on the parties. Bryant v. Lord, 19 Minn. 342 (396); Munroe v. Perkins, 9 Pick. 298. This rule is subject to the criticism that it is a direct invitation to a party desiring to escape from the obligation of an unsatisfactory contract, or to secure an inequitable increase of the stipulated compensation, to take advantage of the necessities of the opposite party and force him to accede to his demands. But we are of the opinion that the consideration for this oral contract was materially different from mat claimed by the appellant, and that it is not necessary to determine what the effect on the validity of the contract would have been, if it had been simply an agreement to pay the respondents extra compensation if they would perform their original contract.

The evidence tends to show that, while the respondents were excavating trenches for the purpose of driving piles upon which the foundation of the building was to be placed, they discovered that a large quantity of rocks had been previously placed upon the lots by the city of Duluth, and that they had become imbedded in the yielding soil of the lots, below its surface, so that it was'impossible to «drive the piles without removing the rocks, and that neither party [202]*202had any knowledge of the existence of any- rocks below the surface of the lots until the work of opening the trenches had been commenced; that thereupon a controversy arose between the parties,, the appellant’s agent claiming that the removal of the rocks was. included in the contract. This the respondents denied, and refused to proceed further under their contract, unless the agent would, agree to pay the costs of such removal. The evidence further tends-to show that the parties compromised the matter by entering into.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MBT Construction Corp. v. Kelhen Corp.
432 A.2d 670 (Supreme Court of Rhode Island, 1981)
Angel v. Murray
322 A.2d 630 (Supreme Court of Rhode Island, 1974)
Haughton Elevator Co. v. C. Rallo Contracting Co.
395 S.W.2d 238 (Missouri Court of Appeals, 1965)
Lehman v. Stout
112 N.W.2d 640 (Supreme Court of Minnesota, 1961)
Bailey v. Martin
112 S.E.2d 807 (Court of Appeals of Georgia, 1960)
United States v. I. B. Miller, Inc.
81 F.2d 8 (Second Circuit, 1936)
Snowball v. Maney Bros. & Co.
270 P. 167 (Wyoming Supreme Court, 1928)
Blakeslee v. Board of Water Commissioners
139 A. 106 (Supreme Court of Connecticut, 1927)
Burner v. American Bar Quartz Mining Co.
246 P. 77 (California Court of Appeal, 1926)
McWilliams v. Dawes
5 Pelt. 577 (Louisiana Court of Appeal, 1922)
Western Lithograph Co. v. Vanomar Producers
197 P. 103 (California Supreme Court, 1921)
Walberg v. Jacobson
173 N.W. 409 (Supreme Court of Minnesota, 1919)
Leland v. Modern Samaritans
126 N.W. 728 (Supreme Court of Minnesota, 1910)
Linz v. Schuck
67 A. 286 (Court of Appeals of Maryland, 1907)
Youngberg v. Lamberton
97 N.W. 571 (Supreme Court of Minnesota, 1903)
King v. Duluth, Missabe & Northern Railway Co.
63 N.W. 1105 (Supreme Court of Minnesota, 1895)

Cite This Page — Counsel Stack

Bluebook (online)
63 N.W. 479, 61 Minn. 198, 1895 Minn. LEXIS 333, Counsel Stack Legal Research, https://law.counselstack.com/opinion/michaud-v-macgregor-minn-1895.