MBT Construction Corp. v. Kelhen Corp.

432 A.2d 670, 1981 R.I. LEXIS 1226
CourtSupreme Court of Rhode Island
DecidedJuly 15, 1981
Docket79-83-Appeal
StatusPublished
Cited by9 cases

This text of 432 A.2d 670 (MBT Construction Corp. v. Kelhen Corp.) is published on Counsel Stack Legal Research, covering Supreme Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MBT Construction Corp. v. Kelhen Corp., 432 A.2d 670, 1981 R.I. LEXIS 1226 (R.I. 1981).

Opinion

OPINION

BEVILACQUA, Chief Justice.

This is an appeal by the defendant Kel-hen Corporation from a judgment by the Superior Court awarding the plaintiff MBT Construction Corp. the sum of $4,617.87 in an action involving a contract executed by the parties. 1

Henry Bigger, president of defendant corporation, and Brian Gillson, vice president and general manager of plaintiff corporation, began discussions in May 1976 concerning a restaurant defendant wished to have constructed in a building on Thames Street in Newport. The defendant corporation was the lessee of this building, which was owned by Seaboard Realty Corp. It was agreed eventually that plaintiff would build the restaurant for defendant and also would do some work on the premises for Seaboard.

The plaintiff, acting as general contractor, began work at the Thames Street location sometime in June 1976 but did not start the work contracted with defendant until July 9, 1976. The parties delayed signing a contract until July 23, 1976, preferring to operate on the basis of “mutual trust” in the early weeks. The July 23rd agreement called for payment under a cost-plus arrangement with defendant 'agreeing to pay an additional 10 percent for materials and subcontracted labor and 15 percent for plaintiff’s employees’ labor, as well as the actual cost. The parties further agreed that defendant’s liability for work done under the contract would not exceed $10,000.

Apparently, the $10,000 limit did not attach to all work that plaintiff might perform in constructing the restaurant for defendant. The contract terms indicated that plaintiff would proceed in accordance with plans described in the contract and specifications drawn by both an architect and a restaurant-equipment company. Another contract provision, however, allowed defendant to request additions not contemplated by the plans or specifications. The plaintiff was to add the cost of any such requested additions to the contract price. The parties further stipulated to put agreements for these changes in writing before the additional labor and materials were furnished.

As the work progressed, Gillson began to realize that some changes might be necessary to construct the kind of restaurant defendant wanted. Consequently, either Gillson or his foreman talked to Bigger concerning each proposed change. In each case, Bigger was informed that the change would cost more money although neither party seemed to realize exactly how much more. By Bigger’s own admission, he agreed to every change that plaintiff made.

None of these contract modifications was put in writing, nor does it appear that either party made any attempt or request to reduce the modifications to writing. At the time the parties executed the agreement, some of the extra work had already been discussed and initiated. In addition, the contract made time of the essence and recited a completion date of August 1,1976; but as the work continued, it became apparent that this date was not realistic. Nevertheless, defendant did pay plaintiff the sum of $10,000 in several installments.

In late August, plaintiff ceased construction after presenting defendant with a bill that defendant refused to honor. The plaintiff had substantially completed the work under the contract, including a number of extras. This bill, dated August 27, 1976, showed a total charge for labor and *673 materials of $20,058, a credit for the $10,000 payment, and a balance due of $10,058. 2

The defendant continued to refuse to make payment, and plaintiff filed a four-count complaint in Superior Court. Each count asked for the balance due plus interest and costs. The defendant responded with an answer denying plaintiff’s allegations and a counterclaim alleging plaintiff’s failure to complete certain work and the improper installation of the floor. The defendant asked for $10,000 in damages plus interest and costs.

At the trial, plaintiff attempted to prove that the amount of labor and materials for work under the contract equaled or exceeded $10,000. The plaintiff also offered testimony and other evidence to demonstrate that he had expended over $10,000 worth of extra labor and materials in building the restaurant. - The plaintiff’s proof of cost consisted of receipts, invoices, canceled checks, memoranda, payroll records, and his own testimony.

The trial justice found that the parties had executed a valid contract that closely paralleled an earlier unexecuted draft of their agreement. He further found that plaintiff’s work for defendant started on July 9, 1976, and terminated on August 12, 1976. After examining the evidence, the court concluded that plaintiff had actually spent more than $20,000 in rendering services for defendant but also expended more than $10,000 for items covered under the contract. Although the court found expenditures in excess of $10,000 for improvements made under the contract plans, plaintiff was not allowed to recover for these excess expenditures.

With regard to the extras, however, the court granted plaintiff a partial recovery for expenditures made. In reaching this determination, the trial justice made several findings. The court found that both parties consistently ignored the contract provision requiring contract modifications for extras to be in writing. The court determined that defendant agreed to each change proposed by Gillson. In addition, the trial justice used the contract cost-plus formula to fix the amount of recovery for those extras awarded to plaintiff.

The court reviewed evidence of all alleged extras and made a specific award for most items; in some cases recovery was denied or only partially allowed. The total amount awarded to plaintiff was $4,617.87. This amount was reduced by a $500 judgment for defendant on its counterclaim for unfinished contract work. Thereafter, defendant took this appeal.

The three issues we must decide are (1) whether plaintiff expended $10,000 in completing construction work covered by the contract plans and specifications, 3 (2) whether the trial justice correctly computed the amount of extras recovered by plaintiff, and (3) whether the trial justice erred by relying on Gillson’s testimony.

I

In its brief, plaintiff concedes that the trial justice “was required to find that at least $10,000 in labor and materials was expended by MBT on the [restaurant] exclusive of extra work.” We agree with this conclusion and observe that the trial justice could have made deductions from this award of extras either for work not completed pursuant to the contract or for the difference between $10,000 and any lesser amount that represented the total of contract expenditures. As noted previously, the trial justice found more than $10,000 was expended on contract work but also found $500 worth of contract work not completed and entered judgment accordingly.

The defendant questions the adequacy of proof offered by plaintiff on this issue. The defendant points out that much of Gill-son’s testimony concerned the extras and that plaintiff had made no attempt to distinguish between labor expended on extras *674 and labor costs covered by the contract plans.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Providence Worcester v. Pawtucket
Superior Court of Rhode Island, 2008
Jalex Builders, Inc. v. Monaghan, 98-0130 (2002)
Superior Court of Rhode Island, 2002
Fondedile, S.A. v. C.E. Maguire, Inc.
610 A.2d 87 (Supreme Court of Rhode Island, 1992)
Goldman v. Goldman
543 A.2d 1304 (Supreme Court of Rhode Island, 1988)
Royer v. Royer
501 A.2d 739 (Supreme Court of Rhode Island, 1985)
Berube v. Montgomery
463 A.2d 158 (Supreme Court of Rhode Island, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
432 A.2d 670, 1981 R.I. LEXIS 1226, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mbt-construction-corp-v-kelhen-corp-ri-1981.