Ferris v. Mann

210 A.2d 121, 99 R.I. 630, 1965 R.I. LEXIS 494
CourtSupreme Court of Rhode Island
DecidedMay 13, 1965
DocketEx. Nos. 10610, 10611
StatusPublished
Cited by11 cases

This text of 210 A.2d 121 (Ferris v. Mann) is published on Counsel Stack Legal Research, covering Supreme Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ferris v. Mann, 210 A.2d 121, 99 R.I. 630, 1965 R.I. LEXIS 494 (R.I. 1965).

Opinion

*631 Powers, J.

These are cross actions of assumpsit to recover damages allegedly arising out of a building contract entered into between the parties. The cases were consolidated for trial to a superior court justice sitting without a jury and resulted in a decision for the plaintiff in each case. They are before us on the bills of exceptions of Milton W. Ferris as the plaintiff in one action and the defendant in the other and the sole exception in each case is to the decision.

The record establishes that on February 13, 1959, Milton W. Ferns, hereinafter referred to as the “owner,” and Roy C. Mann and George W. Cook, d.b.a. M & C Construction Co., hereinafter referred to as the “builders,” entered into a contract for the rebuilding of a house extensively damaged by fire and located on Old Usquepaugh Road in the town of Richmond, Rhode Island. The stated consideration was $8,700 and the work was to be completed within five months of the date it was started but not later than April 16, 1960.

The parties stipulated that work did commence on November 16, 1959, but the owner decided on certain changes which were incorporated in a second agreement dated April 6, 1960 and the consideration was increased to $10,800. Although the April 16, 1960 completion date was not extended by the amended agreement, the owner orally from time to time extended the period for completion until by letter dated August 21, 1960 he notified the builders that the time would not be extended beyond the following September 1. This letter complained of inactivity, pointed out lack of excuses for delay and, referring to the five months’ limitation contained in the agreement, insisted that time was of the essence.

*632 The record further discloses that the work was not completed by September 1, 1960 and thereafter the owner withdrew the key to the house from where it was customarily left for the builders’ use, thus making it impossible for the latter to continue.

The owner heard nothing from the builders for some time after sending the August 21, 1960 letter. He testified that, when he did hear, the builders informed him there was no money left to complete the job and considerable work remained unfinished; that he thereupon went to the offices of the United Builders Supply Company in Westerly where $10,706 had been deposited; and that upon learning only $137.81 remained for the completion of the work he withdrew and closed out the account.

It is also his testimony that before calling in Richard Thibodeau, another contractor, to estimate the amount and nature of the unfinished work, he laid out money for materials and supplies in finishing part of the work himself. A paper purporting to show the nature and amount of the work done by the owner and the expenses in connection therewith was admitted in evidence, together with two other instruments, one showing work remaining when Thi-bodeau inspected the property and the other work completed but in an unworkmanlike manner.

Mr. Thibodeau testified that about a year after the work had stopped he inspected the premises at the owner’s request and made a list of the items to be considered in bringing the work up to the contract specifications, and that in his opinion the completion of these items would involve an expenditure of $1,339.50.

The defendant builders denied that the owner ever complained about the workmanship and insisted that very little remained to ibe done when -the job was terminated. They flatly contradicted the testimony of the owner and Mr. Thi-bodeau as to the damages allegedly sustained by the owner.

*633 On this summary of the evidence in the case of the owner as .plaintiff the trial justice awarded damages in the sum of $1,339.50. This was the estimate of the witness Thibo-deau and it related to the owner’s claim of work remaining to be finished as well as to work which had been completed but in an unworkmanlike manner. No serious contention is made by the owner that the trial justice’s decision is erroneous in this regard.

However, he does .contend that the trial justice overlooked or disregarded the exhibit which was admitted in evidence and set forth the expenses of the owner prior to the time the premises were inspected by the witness Thibodeau, citing Lannon v. Lannon, 86 R. I. 451, and Blackstone Valley Gas & Electric Co. v. Rhode Island Power Trammission Co., 64 R. I. 204, for the proposition that the failure of the trial justice to consider all the evidence constitutes prejudicial error.

Our reading of the last-cited case fails to disclose any particular or even remote association with the proposition on which the owner relies. However, the principle advanced by him unquestionably states the rule in this jurisdiction. In the circumstances of the instant case, however, the owner takes nothing by the rule.

The instrument referred to in the record as exhibit 4 was clearly not admitted as a full exhibit and it is apparent from the colloquy between counsel and the trial justice that, plaintiff understood the limited purpose for which it was received. The builders objected to its introduction because it contained not merely a listing of the items which the owner claimed to have purchased but the amount, paid for.each such item as .well. They pointed out that it was a self-serving statement prepared by the owner for purposes of trial .and the information therein contained could be properly received in evidence only if supported by testimony. Counsel for the owner acknowledged the correctness *634 of this proposition and stated that he would follow it up by asking the proper questions of the owner. Thus, on the understanding of the parties and the ruling of the trial justice, it is obvious that he received the instrument only for a limited purpose. The only testimony by the owner with regard thereto, however, was limited to an affirmative response when asked if he had paid for the materials and supplies enumerated in the limited exhibit.

It is a well-established principle that one who sues to recover such damages has the burden of proving the reasonable value of the materials and labor in question. Sullivan v. District of Columbia Paper Mills, Inc., 67 R. I. 330, and Russolino v. A. F. Rotelli & Sons, Inc., 85 R. I. 160.

Here the enumerated materials and supplies contained in the so-called exhibit were, the owner testified, purchased by him although they are set forth in the contract as amended as part of the builders’ obligation. He offered no1 testimony, however, as to the reasonableness of what he paid for them, relying solely in that regard on the information appearing in the memorandum prepared by him.

Therefore, although the trial justice made no reference to this memorandum and it might be assumed that he overlooked it, such assumption would be of no assistance to the owner, since it was without probative force and entitled to no weight. In these circumstances the trial justice cannot be said to have overlooked or misconceived material evidence on the question of damages.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cavanaugh v. Contractors' Registration Board
Superior Court of Rhode Island, 2008
Desimone Electric Inc. v. Cmg, Inc., 01-6077 (2004)
Superior Court of Rhode Island, 2004
Iannuccillo v. Material Sand & Stone Corp.
713 A.2d 1234 (Supreme Court of Rhode Island, 1998)
National Chain Co. v. Campbell
487 A.2d 132 (Supreme Court of Rhode Island, 1985)
Dunne Leases Cars & Trucks, Inc. v. Kenworth Truck Co.
466 A.2d 1153 (Supreme Court of Rhode Island, 1983)
Kirkpatrick v. Temme
654 P.2d 1011 (Nevada Supreme Court, 1982)
MBT Construction Corp. v. Kelhen Corp.
432 A.2d 670 (Supreme Court of Rhode Island, 1981)
American Continental Life Insurance v. Ranier Construction Co.
607 P.2d 372 (Arizona Supreme Court, 1980)
Alterio v. Biltmore Construction Corp.
377 A.2d 237 (Supreme Court of Rhode Island, 1977)
DiMario v. Heeks
351 A.2d 837 (Supreme Court of Rhode Island, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
210 A.2d 121, 99 R.I. 630, 1965 R.I. LEXIS 494, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ferris-v-mann-ri-1965.