American Continental Life Insurance v. Ranier Construction Co.

607 P.2d 372, 125 Ariz. 53, 1980 Ariz. LEXIS 172
CourtArizona Supreme Court
DecidedFebruary 6, 1980
Docket13950
StatusPublished
Cited by60 cases

This text of 607 P.2d 372 (American Continental Life Insurance v. Ranier Construction Co.) is published on Counsel Stack Legal Research, covering Arizona Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Continental Life Insurance v. Ranier Construction Co., 607 P.2d 372, 125 Ariz. 53, 1980 Ariz. LEXIS 172 (Ark. 1980).

Opinions

GORDON, Justice:

This appeal involves a suit for breach of a construction contract between American Continental Life Insurance Co. (American) and Ranier Construction Co., Inc. (Ranier). After trial by jury, a verdict was returned for Ranier in the amount of $130,000 and for American in the amount of $10,000 on its counterclaim. The trial judge determined that neither party was entitled to recover attorney’s fees from the other. Both parties appeal. Having jurisdiction pursuant to 17A A.R.S., Rules of Civil Appellate Procedure, Rule 19(e), we reverse the judgment in favor of Ranier and the court’s disposition of attorney’s fees.

American contracted with Ranier to construct a building for $517,286.30. To date, American has paid Ranier $457,247.47. The contract required American to make monthly progress payments for 90% of the work completed each month upon the .issuance by the architect of a certificate for payment. American refused to make the final payment, consisting of the 10% retained each month and the amount due for work completed after the date of the last progress payment. It claimed that Ranier had breached the procedural requirements of the contract and had failed to construct the building in a workmanlike manner and in accordance with the plans and specifications. Ranier subsequently instituted suit for breach of the contract, to recover funds retained under the contract and damages for delays and lost profits. American counterclaimed for breach of contract and negligence, to recover damages for faulty construction and delays. The jury returned a single verdict for Ranier in the amount of $130,000 and a single verdict for American in the amount of $10,000. American appeals the verdict in favor of Ranier. Ranier cross appeals the trial court’s refusal to award attorney’s fees to Ranier as the prevailing party.1

At the close of Ranier’s case and again at the close of all the evidence, American moved for a directed verdict, which was denied. One of the grounds urged by American was that Ranier had failed to meet a condition precedent to the right to final payment, because it had failed to procure from the architect a final certificate for payment as provided in the contract. [55]*55American renews this argument on appeal, contending that the court erred in denying its motion for a directed verdict.

Article 7 of the contract provides:

“Final payment constituting the entire unpaid balance of the Contract Sum shall be paid by the Owner to the Contractor within thirty (30) days after Substantial Completion of the Work * * * provided the work has then been completed * * * and a final Certificate for Payment has been issued by the Architect.”

Issuance of the final certificate for payment is governed by paragraph 9.7.2 of the General Conditions of the contract:

“Upon receipt of written notice that the Work is ready for final inspection and acceptance and upon receipt of a final Application for Payment, the Architect will promptly make such inspection and, when he finds the Work acceptable under the Contract Documents and the Contract fully performed, he will promptly issue a final Certificate for Payment stating that to the best of his knowledge, information and belief, and on the basis of his observations and inspections, the Work has been completed in accordance with the terms and conditions of the Contract Documents and that the entire balance found to be due the Contractor, and noted in said final Certificate, is due and payable.”

The architect issued a certificate of substantial completion,2 but Ranier admits that a final certificate for payment, as provided for in the contract, was never applied for or obtained. American asserts, and it is undisputed by Ranier, that it was Ranier’s responsibility to procure issuance of the certificate. Ranier argues, however, that strict compliance with the requirement of a final certificate for payment was waived, because, from the beginning, both parties deviated from the formal requirements of the contract in other respects. Ranier cites as examples the fact that change orders, although done at the owner’s request, were not signed by the owner; that on occasion the owner even ordered changes to be made without execution of a formal change order; that extensions of time were granted both formally and informally; and that the owner, although in agreement, also failed to sign extensions of time. The trial court believed that there was sufficient evidence to support a submission to the jury as to whether strict compliance had been waived. We disagree.

Waiver is either the express, voluntary, intentional relinquishment of a known right or such conduct as warrants an inference of such an intentional relinquishment. See, e. g., City of Tucson v. Koerber, 82 Ariz. 347, 313 P.2d 411 (1957). Waiver by conduct must be established by evidence of acts inconsistent with an intent to assert the right. Occidental Life Insurance Co. v. Jacobson, 15 Ariz. 242, 137 P. 869 (1914); see Bolo Corp. v. Homes and Son Construction Co., Inc., 105 Ariz. 343, 464 P.2d 788 (1970). The waiver of one right under a contract does not necessarily waive other rights under the contract. See O’Malley v. Cummings, 86 Ill.App.2d 446, 229 N.E.2d 878 (1967). Thus, even if American did waive other rights under the contract relating to change orders or extensions of time, that conduct does not manifest an intent to waive any right relating to payment for [56]*56work. See Practical Construction Co. v. Granite City Housing Authority, 416 F.2d 540 (7th Cir. 1969). Ranier does not indicate any evidence, nor does any evidence appear in the record, that the parties ever disregarded any of the terms of the contract relating to payments. Accordingly, we find no waiver.3

Ranier also argues, alternatively, that certain acts by American4 prevented ■fulfillment of the condition precedent, thereby excusing performance. We fail to perceive how these acts prevented Ranier from seeking a final certificate of payment from the architect. Similarly, we reject Ranier’s assertion that seeking a final certificate of payment would have been a futile act, because American had already demonstrated its unwillingness to co-operate by refusing to sign the certificate of substantial completion. The failure of American to sign the certificate of substantial completion has nothing to do with Ranier’s obligation under the contract to procure the final certificate of payment in order to be in a posture to claim that payment from American is due. Moreover, even if Ranier is correct in assuming that American would not have made the final payment had Rani-er sought and received the final certificate of payment from the architect, Ranier is not excused from the contractually-imposed duty of acquiring the certificate. Without it, we have no way of knowing if the architect was satisfied that the list of items to be completed between the time of issuance of the certificate of substantial compliance and the application for final payment5 had been completed and that the contract was, thus, fully performed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McMahan v. Grasshopper
Court of Appeals of Arizona, 2025
brooks/phoenix v. Hon. Agne
Court of Appeals of Arizona, 2022
S S Holdings v. American Green
Court of Appeals of Arizona, 2022
Fann v. Hon. kemp/american
505 P.3d 301 (Court of Appeals of Arizona, 2022)
Ryan v. eXp Realty LLC
D. Arizona, 2021
Aspen v. Wakefield
Court of Appeals of Arizona, 2021
Hkb, Inc. v. Imperial
Court of Appeals of Arizona, 2021
Mago v. Az Escrow
Court of Appeals of Arizona, 2021
Aerial Funding v. Van Sickle
Court of Appeals of Arizona, 2020
Jessicah C. v. Dcs, J.P.
Court of Appeals of Arizona, 2020
State v. Coger
Court of Appeals of Arizona, 2019
La Borgata v. Retreat
Court of Appeals of Arizona, 2019
Pinal Cnty. v. Fuller
429 P.3d 570 (Court of Appeals of Arizona, 2018)
Marinello v. Glover
Court of Appeals of Arizona, 2018
Commerce v. Zinke
Court of Appeals of Arizona, 2017

Cite This Page — Counsel Stack

Bluebook (online)
607 P.2d 372, 125 Ariz. 53, 1980 Ariz. LEXIS 172, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-continental-life-insurance-v-ranier-construction-co-ariz-1980.