Bolo Corporation v. Homes & Son Construction Co.

464 P.2d 788, 105 Ariz. 343, 1970 Ariz. LEXIS 265
CourtArizona Supreme Court
DecidedJanuary 16, 1970
Docket9674
StatusPublished
Cited by27 cases

This text of 464 P.2d 788 (Bolo Corporation v. Homes & Son Construction Co.) is published on Counsel Stack Legal Research, covering Arizona Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bolo Corporation v. Homes & Son Construction Co., 464 P.2d 788, 105 Ariz. 343, 1970 Ariz. LEXIS 265 (Ark. 1970).

Opinion

HAYS, Justice.

The appellant, Bolo Corporation, has appealed an order of the Superior Court granting the plaintiff-appellee’s motion to compel arbitration. The argument raised in opposition is that the plaintiff, by its actions had waived its right to compel arbitration and must therefore proceed with the civil action originally brought. We agree with the position taken by the appellant for the reasons stated below.

The parties entered into a written contract, executed on the 27th day of December, 1963, wherein the appellee, Homes and Son Construction Co., Inc., agreed to construct for the appellant a shopping center building to be known as “Mesa Plaza Shopping Center,” and to be located at Main Street and Lazona Drive, Mesa, Arizona.

The contract contained a “General Conditions” provision which required that any dispute arising out of the contract or the performance of the contractor be settled by arbitration.

CONTRACT EXHIBIT NUMBER 2: GENERAL CONDITIONS
******
“I. Arbitration. — If at any time any controversy should arise between the Owner and the Contractor regarding anything pertaining to this Agreement and which the parties hereto do not promptly adjust and determine, or which the Owner cannot decide to the satisfaction of both parties, the written orders of the Owner to the Contractor shall be followed. The controversy existing between the parties shall be submitted to and determined by arbitration. Each of the parties hereto shall select an arbitrator and the arbitrators so selected by them shall select a third person to serve as arbitrator with them. The parties hereto agree to be bound by the award in such arbitration.” Abstract of the Record at p. 217.

Construction under the contract began in early 1964. In September of that year, with the structure nearing completion, a dispute arose between the parties as to variances between the quality of the performance and the plans and specifications re *344 ferred to in the contract. At that point there was a balance of $87,000.00 owing and unpaid under the agreement, which the appellant withheld pending satisfactory-completion of the project in accordance with the specifications.

The correspondence between the parties during this period is summarized in the affidavit of W. E. Homes, Jr., an officer of the plaintiff corporation; which affidavit is attached to plaintiff’s motion for leave to amend the complaint. It is therein stated that in September of 1964, the project having been substantially completed, Homes & Son sent its final billing to Bolo. Bolo, in response, indicated that it was withholding the final payment because of various questions regarding cost charges. On October 12, 1964, plaintiff requested arbitration and named one arbitrator. Homes alleges that on December 26, 1964, Bolo made an expression that arbitration was acceptable, but declined to appoint an arbitrator or to enter into formal negotiations until there could be an audit of plaintiff’s books. According to Homes, an audit was done, but Bolo continued to postpone arbitration pending “more information on additional matters.” Finally, on November 12, 1964, or thereabouts, the defendant corporation indicated its unwillingness to arbitrate.

The first formal action taken by either party in an attempt to resolve the dispute was the filing by Homes & Son of a complaint at law charging Bolo with a breach of the contract and seeking a money judgment. In conjunction with the filing of the complaint, plaintiff commenced garnishment proceedings against several tenants of the defendant, said garnishees being lessees of the premises in question.

Bolo answered the complaint on January 14, 1965, attaching thereto a counterclaim alleging failure, negligence and refusal on the part of Homes & Son to perform its obligations under the contract and praying judgment in the sum of $10,200.00, plus such additional sums as might thereafter be determined to be the result of the plaintiff’s failure to perform the contract. Plaintiff filed a reply on January 29, 1965.

Correlatively and simultaneous therewith, writs of garnishment directed toward tenants of the shopping center were issued, answers were filed thereto by the respective garnishees and there was tender of issue.

It was not until the 24th day of June, 1965, or thereabouts, nealy six months after the original filing of the lawsuit, that the appellee filed a motion for leave to amend the complaint and for an order to compel arbitration as is provided for under the Uniform Arbitration Act, A.R.S. § 12-1502, subsec. A 1 .

The order of the trial court directing that arbitration be commenced was objected to by the appellant and it is the correctness of the trial court’s ruling which we are called upon to decide.

The question thus presented is whether or not there has been a waiver, mutual rescission, repudiation, laches or estoppel by or on behalf of the plaintiff in the enforcement of the arbitration clause.

One need only look at the Arizona Statutes to discover that the express language of the Arbitration Act as adopted by the legislature acknowledges revocability. The statute, A.R.S. § 12-1501, Validity of Arbitration Agreement, is couched in these terms:

“A written agreement to submit any existing controversy to arbitration or a provision in a written contract to submit to arbitration any controversy thereafter *345 arising between the parties is valid, enforceable and irrevocable, save upon such grounds as exist at law or in equity for the revocation of any contract.” (Emphasis added).

The general rule governing the waiver or repudiation of such agreements when combined with the public policy which favors the enforcement of arbitration is well stated in the opinion of United Paper Machinery Corp. v. DiCarlo, 19 A.D.2d 663, 241 N.Y.S.2d 711 (1963):

“Arbitration is by consent and those who agree to arbitrate should be made to keep their solemn, written promises. Such is New York’s public policy, plainly written in article 84 of the Civil Procedure Act. The courts should follow a ‘liberal policy of promoting arbitration both to accord with the original intention of the parties and to ease the congestion of court calendars.’ ”
:f: i{c ‡ ‡ sfc
“There is, however, nothing irrevocable about an agreement to arbitrate. Both of the parties may abandon this method of settling their differences, and under a variety of circumstances one party may waive or destroy by his conduct his right to insist upon arbitration.”

A- further explanation of the rule is found in the case of In re Aller’s Petition, 47 Cal.2d 189, 302 P.2d 294 (1956), in which the California Supreme Court quoted from Drake v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CASTLE ROCK v. PERRY
Court of Appeals of Arizona, 2026
ANDRICH v. THRASHER
Court of Appeals of Arizona, 2026
Russo v. Barger
366 P.3d 577 (Court of Appeals of Arizona, 2016)
Cortez v. Avalon Care Center Tucson, L.L.C.
245 P.3d 892 (Court of Appeals of Arizona, 2010)
Cooper v. QC Financial Services, Inc.
503 F. Supp. 2d 1266 (D. Arizona, 2007)
Sears Roebuck and Co. v. Avery
593 S.E.2d 424 (Court of Appeals of North Carolina, 2004)
Matter of Noel R. Shahan Trust
932 P.2d 1345 (Court of Appeals of Arizona, 1997)
Meineke v. Twin City Fire Insurance
892 P.2d 1365 (Court of Appeals of Arizona, 1994)
City of Cottonwood v. James L. Fann Contracting, Inc.
877 P.2d 284 (Court of Appeals of Arizona, 1994)
BancAmerica Commercial Corp. v. Brown
806 P.2d 897 (Court of Appeals of Arizona, 1990)
U.S. Insulation, Inc. v. Hilro Construction Co.
705 P.2d 490 (Court of Appeals of Arizona, 1985)
Rancho Pescado, Inc. v. Northwestern Mutual Life Insurance
680 P.2d 1235 (Court of Appeals of Arizona, 1984)
Forest City Dillon v. Super. Ct. in & for Pima
675 P.2d 297 (Court of Appeals of Arizona, 1984)
American Continental Life Insurance v. Ranier Construction Co.
607 P.2d 372 (Arizona Supreme Court, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
464 P.2d 788, 105 Ariz. 343, 1970 Ariz. LEXIS 265, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bolo-corporation-v-homes-son-construction-co-ariz-1970.