Jim Arnott, Inc. v. L & E, INC.

539 P.2d 1333
CourtColorado Court of Appeals
DecidedJune 17, 1975
Docket74-469
StatusPublished
Cited by4 cases

This text of 539 P.2d 1333 (Jim Arnott, Inc. v. L & E, INC.) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jim Arnott, Inc. v. L & E, INC., 539 P.2d 1333 (Colo. Ct. App. 1975).

Opinion

539 P.2d 1333 (1975)

JIM ARNOTT, INC., et al., Plaintiffs-Appellees,
v.
L & E, INC., and Pittsburgh National Mortgage Corporation, Defendants-Appellants and Cross-Appellees, and
Wilkins Company, Inc., Defendant-Appellee, and
John Ten Eyck, Defendant-Appellee and Cross-Appellant, and
P P G Industries, Inc., Intervenor-Appellee.

No. 74-469.

Colorado Court of Appeals, Div. III.

June 17, 1975.
Rehearing Denied July 22, 1975.

*1335 Wood, Ris & Hames, P. C., William K. Ris, Denver, for defendant-appellee.

Ellison, de Marino & Knapp, William H. Knapp, Denver, Robert Dunlap, Colorado Springs, for defendant-appellee and cross-appellant.

Horn, Anderson & Johnson, R. E. Anderson, Colorado Springs, for plaintiffs-appellees and intervenor-appellee.

Donald E. La Mora, Colorado Springs, for defendants-appellants and cross-appellees.

Not Selected for Official Publication.

RULAND, Judge.

In an action to foreclose mechanics' liens against a newly erected motel, the owner, defendant L & E, Inc., appeals from a judgment in favor of the principal contractor, Wilkins Company, Inc., on Wilkins' claim against L & E, as well as a judgment for a subcontractor, PPG Industries, Inc. L & E also appeals from a judgment disallowing part of its claim against defendant John Ten Eyck, the architect. Ten Eyck cross-appeals from part of the judgment against him on the claim of L & E. We affirm in part, modify and reverse in part, and remand the cause for further proceedings.

L & E engaged Ten Eyck to design and prepare the necessary plans and specifications for construction of three buildings containing a 104-unit motel and other facilities in conformity with the Sheraton Inn, Inc., franchise requirements. Upon completion of the plans and specifications, Wilkins was engaged as the principal contractor to erect the motel.

Disputes arose between these parties during the course of construction with the result that L & E refused to make substantial payments claimed due by both Wilkins and Ten Eyck. Since Wilkins was in default on payments due plaintiffs-appellees as subcontractors, the subcontractors filed mechanics' liens against L & E's property and then initiated the present action against Wilkins for the amount due for performance of their subcontracts, and against L & E (and defendant Pittsburgh National Mortgage Corporation as mortgagee of the property), to establish priority of the various liens. Wilkins, having also filed its lien, cross-claimed against L & E for the balance alleged due on its contract and for work outside the contract. L & E answered Wilkins' claim and asserted a cross-claim against Wilkins for breach of contract. L & E also asserted a claim against Ten Eyck for negligence in design of the structure; Ten Eyck denied liability for negligence and cross-claimed against L & E for payment of architectural fees.

Following a lengthy trial to the court, it awarded judgment against Wilkins on the claims of the subcontractors. Based upon extensive findings of fact and conclusions of law, it determined that Wilkins had substantially performed its contract and awarded judgment in the amount of $144,215, representing the balance due on the contract less offsets for replacement of concrete and other minor defects in the work performed. The court also awarded Wilkins judgment in the amount of $13,591 as the reasonable value of work performed by it which was not included in the contract.

*1336 The trial court awarded L & E judgment in the amount of $22,587 on its claim against Ten Eyck for negligent design of the motel kitchen and $2,471.50 for failure to assist in planning water softeners in the design of the water system for the motel. The trial court offset against this claim the balance which it determined due for services rendered by Ten Eyck in the amount of $19,193.79. This appeal followed.

I. Appeal On Issues Between L & E And Wilkins

L & E first contends that the trial court erred in determining that Wilkins had substantially performed its contract. While conceding that pursuant to the construction contract, Ten Eyck submitted certificates of substantial completion to L & E on buildings 1 and 2 in September of 1972 and on building 3 in October of 1972, L & E relies on evidence to the effect that: No attempt was made to balance the mechanical systems until December 1972; repairs to heating units were not completed until June 1973; not all of the minor defects enumerated in a "punch list" prepared by L & E were corrected; certain improperly poured concrete and allegedly defective windows were never replaced; the water pressure in the buildings was inadequate; and the certificate of consent to payment by Wilkins' surety was not issued until March 1973. In addition, L & E complains that Wilkins was obligated under its contract to assure that no liens were filed against the property by subcontractors, and such liens were filed.

If it appears that a contractor has substantially performed his contract, then he is entitled to the contract price, less an offset for the cost to remedy the deficiencies. The purpose of the doctrine of substantial performance is to avoid injustice where a building contractor has performed all major aspects of the construction and the owner seeks to avoid payment for inconsequential defects in the work. See Louthan v. Carson, 63 Colo. 473, 168 P. 656. Whether substantial completion of a construction contract has occurred is a question of fact. Little Thompson Water Assn. v. Strawn, 171 Colo. 295, 466 P.2d 915. Hence, the sufficiency, probative effect, and weight of all the evidence relative to this issue, as well as the inferences and conclusions to be drawn therefrom, rest within the province of the trial court and its conclusions may not be disturbed unless so clearly erroneous as to find no support in the record. Whatley v. Wood, 157 Colo. 552, 404 P.2d 537; Thiele v. State, 30 Colo.App. 491, 495 P.2d 558.

Pursuant to his contractually authorized authority, Ten Eyck issued certificates of substantial completion but L & E refused to make final payment to Wilkins. All defects of which L & E now complains were determined by the trial court not to be the responsibility of Wilkins or were rectified prior to trial with the exception of alleged defects in some of the windows, replacement of some concrete which was improperly poured, and certain other minor defects in construction reflected by a "punch list." The construction price for erection of the buildings under the contract was $1,447,500, and the trial court awarded offsets to L & E for defects in the construction of only $4,310. Our review of the record does not indicate that failure to cure some of the defects until after certificates of substantial completion were issued materially interfered with L & E's use of the premises. In fact, the county building department issued an occupancy permit for all buildings on September 16, 1972, and L & E rented the first room upon issuance of the permit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Continental Life Insurance v. Ranier Construction Co.
607 P.2d 372 (Arizona Supreme Court, 1980)
Rissler & McMurry Co. v. Atlantic Richfield Co.
559 P.2d 25 (Wyoming Supreme Court, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
539 P.2d 1333, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jim-arnott-inc-v-l-e-inc-coloctapp-1975.