Martin v. Karsh

298 P.2d 635, 142 Cal. App. 2d 468, 1956 Cal. App. LEXIS 2006
CourtCalifornia Court of Appeal
DecidedJune 22, 1956
DocketCiv. 16759
StatusPublished
Cited by8 cases

This text of 298 P.2d 635 (Martin v. Karsh) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Martin v. Karsh, 298 P.2d 635, 142 Cal. App. 2d 468, 1956 Cal. App. LEXIS 2006 (Cal. Ct. App. 1956).

Opinion

THE COURT.

This is an appeal in consolidated actions relating to the sufficiency of the performance of the contractors, Martin and Hastings, doing business as “Bayshore Construction Company” hereinafter referred to as “Bay-shore,” in constructing a concrete warehouse under a fixed fee contract for Harry Karsh, Hy Karsh and their wives, the owners of the property in Oakland on which the warehouse was built, hereinafter referred to as “Karsh.” Bay-shore instituted action 254691 to foreclose a mechanic’s lien against Karsh for the balance allegedly due under the construction contract; Karsh instituted against Bayshore action 25472 for damages (in the amount of $30,000) because of alleged breach of said construction contract on the ground that Bayshore had not completed the warehouse in a workmanlike manner and in conformity with the plans and specifications. The court found in substance that Bayshore had duly performed its contract and was entitled to the agreed price for the principal work and certain extra work less the sum of $625 allowed by the court for cost and expense of repairing concrete work which the court found would ordinarily be done by the contractor after the completion of a job like this one. Accordingly the foreclosure of a lien for the balance so found due was ordered and Karsh were adjudged to take nothing by their action and to pay the costs of both actions. They appeal from the judgment in the consolidated actions, contending that the evidence does not support the findings. *470 We have concluded that said contention is without merit, that the conflicting evidence contains substantial support for the findings and judgment and that appellants ’ contrary argument is based on an incorrect stressing of their own evidence, rejected by the trial court, instead of the evidence favorable to respondents on which the trial court relied.

It is conceded by respondents that there were some deviations from a strict performance of the letter of the contract, plans and specifications, which deviations, however, they contend were made in good faith and justified by the circumstances, and some slight imperfections not more than normal for such buildings. It is accordingly their position that they substantially performed their contract, that the value of the building was in no way impaired and that appellants did not suffer any damage. The court’s judgment and findings sustain those contentions except for the allowance of the stated deduction of $625 for repair of imperfections (cracks) of the concrete work, normally borne by the contractor.

The law is settled in this state, that in the case of building contracts, especially where the owner has taken possession of the building and is enjoying the fruits of the contractor’s work, no literal compliance with the contract in all details and no absence of all defects and imperfections is required to entitle the contractor to recovery on the contract, but that he can have such recovery after substantial performance in good faith, if the deviations and imperfections do not substantially affect the usefulness of the building for the purposes for which it was intended, subject to an allowance for damages if the owner has suffered any by reason of the failure to perform strictly. Whether, in any case, defects and omissions are substantial or unimportant is generally a question of fact. (Thomas Haverty Co. v. Jones, 185 Cal. 285 [197 P. 105] ; Smith v. Mathews Const. Co., 179 Cal. 797, 801-802 [179 P. 209]; Connell v. Higgins, 170 Cal. 541, 556-557 [150 P. 769].)

In this case the evidence shows that appellants were fully enjoying the intended advantages of the construction and that its usefulness for the intended purpose was not substantially impaired. The building had been leased pending construction on the plans and specifications filed for a term of 10 years at a rent of $1,700 a month, it had been occupied by the lessee in July, 1953, and since then until the trial in October, 1954, the lessee had paid the rent provided for without complaining or requiring remedying of any of the *471 defects and deviations stated by Karsh in this action and no repair or replacement of any of the work done by Bayshore had been made or requested. For their contention that the value of the building was impaired by the alleged deviations and defects appellants rely on the testimony of their expert appraisers (brokers), that the property without said deviations and defects would have been worth $170,000 whereas as constructed the value would be between $120,000 and $140,000. However, said evidence caused a conflict only with the evidence of Bayshore’s expert witnesses that none of the matters complained of was poor workmanship or a structural defect or affected the value of the building, which latter evidence was corroborated by the fact that in November, 1953, Karsh procured from The Prudential Insurance Company a loan on the warehouse of $125,000 based on an appraisal of $187,000.

As the above in itself is a sufficient justification of the judgment little need be said about the specific complaints. Karsh mainly complains of two deviations:

1. The footing for the center columns were poured separately, whereas the plans provided for a monolithic pour, in one piece with the adjacent floor slab. The reason given for the deviation by Bayshore is that Karsh eliminated from the original plans the wire mesh reinforcement which was originally intended to integrate the column footings and the adjacent floor slabs and instead increased the thickness of the floor slab and that said revision caused the separate pouring to be advisable. Even appellants’ foundation expert conceded that to reach by the monolithic pouring a good effect in distributing the load over the floor reinforcing material would probably be required. From the side of Bayshore there was much expert evidence that the separate pouring under the circumstances was better or at least not less good than the monolithic pouring which would have led to different, but worse or at least not less cracking of the concrete. Among those who so testified was Robinson, the structural engineer of the work to whose satisfaction the work according to the specifications had to be completed.
2. The purlins of the roof were not hung level with the arches between which they were fastened as provided by the plans but so that the tops of the purlins were 2 inches higher than the arches which prevented the nailing of the sheathing to the arches themselves over and above the nailing to the purlins. It is conceded by appellants that the plans requiring *472 level hanging and nailing also to the arches failed to provide for the fact that the laminated arches were tied together by stitch bolts, the heads of which extended above the top of the arches and that such created a problem in nailing the sheathing to the arches which had to be solved in some way. Appellants, however, contend that other solutions than providing room for the bolts by raising the whole ceiling two inches would have been preferable, to wit, cutting out the sheathing where it came over the bolt head or countersinking the head bolts into the laminated arches.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BPR Construction & Engineering, Inc. v. Rivers
608 S.W.2d 248 (Court of Appeals of Texas, 1980)
American Continental Life Insurance v. Ranier Construction Co.
607 P.2d 372 (Arizona Supreme Court, 1980)
Eldred v. CL Folkman Company
456 P.2d 775 (Idaho Supreme Court, 1969)
Honolulu Roofing Co. v. Felix
426 P.2d 298 (Hawaii Supreme Court, 1967)
Belts v. State ex rel. Department of Highways
388 P.2d 982 (Idaho Supreme Court, 1964)
Atlas Floor Covering v. Crescent House & Garden, Inc.
333 P.2d 194 (California Court of Appeal, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
298 P.2d 635, 142 Cal. App. 2d 468, 1956 Cal. App. LEXIS 2006, Counsel Stack Legal Research, https://law.counselstack.com/opinion/martin-v-karsh-calctapp-1956.