Atlas Floor Covering v. Crescent House & Garden, Inc.

333 P.2d 194, 166 Cal. App. 2d 211, 1958 Cal. App. LEXIS 1390
CourtCalifornia Court of Appeal
DecidedDecember 16, 1958
DocketCiv. 23207
StatusPublished
Cited by11 cases

This text of 333 P.2d 194 (Atlas Floor Covering v. Crescent House & Garden, Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Atlas Floor Covering v. Crescent House & Garden, Inc., 333 P.2d 194, 166 Cal. App. 2d 211, 1958 Cal. App. LEXIS 1390 (Cal. Ct. App. 1958).

Opinion

LILLIE, J.

This is an appeal by defendants from a judgment confirming an arbitration award of money damages to plaintiff.

The dispute between the parties arose out of separate written agreements entered into on October 19, 1955, between plaintiff and 13 defendant corporations for the installation of asphalt floor tiling in tract houses to be constructed on land owned by defendants. The remaining defendant, the Tobin Companies (hereinafter referred to as Tobin) was a licensed building contractor and held an exclusive agency agreement with all the other defendants for the management of their properties and the construction of improvements thereon. Approximately four months after the execution of the October 19 agreements, defendant Tobin delivered to plaintiff a purported letter of rescission based upon plaintiff’s asserted failure to properly attend to work orders. Plaintiff *214 then instituted damage actions for anticipatory breach against the 13 defendants represented by Tobin, and against Crescent House and Garden, Inc., and Dayton House and Garden, Inc., for labor and materials, in addition to damages. Plaintiff also sued Tobin for work and labor performed at the latter’s request on different tracts owned by other corporations not here involved. A counterclaim was filed by Tobin for the cost of correcting defective materials and workmanship on 11 houses covered by defendants’ letter of rescission.

Subsequently, the entire dispute was submitted to arbitration on the following issues: (1) justification for defendants’ rescission and (2) absent justification, the amount of plaintiff’s damages. As to defendants Crescent House and Garden, Inc., and Dayton House and Garden, Inc., a further “alternative” issue whether defendants were obligated to plaintiff for a certain sum “or any other sum” as.and for labor and materials furnished at the request of the two defendants was submitted.

The hearing was held on July 19 and August 1,1957. Thereafter, the arbitrators rendered their decision awarding plaintiff money damages against each of 11 defendants for breach of contract, and in the case of Crescent House and Garden, Inc., and Dayton House and Garden, Inc., an award for labor and materials furnished, in addition to damages. With respect to Tobin, an award to plaintiff was offset by the allowance of Tobin’s counterclaim for the cost of correcting defective materials and workmanship. A motion was then made by plaintiff in the lower court to confirm the award. Defendants countered with a motion to vacate and set it aside. The award was confirmed in all respects and the motion to vacate in effect denied. It is from the judgment confirming the arbitration award defendants appeal.

Appellants contend that the award should have been vacated because the arbitrators were guilty of misconduct “in refusing to hear evidence, pertinent and material to the controversy” (Code Civ. Proc., § 1288, subd. (c)). Thus, it is claimed that the arbitrators refused to hear (1) proffered evidence with respect to respondent’s assertedly defective work on other tracts owned by companies not parties to these proceedings, it being claimed that such evidence was material on the question of appellants’ justification for terminating their contract; (2) proffered testimony of an appellants’ witness regarding asserted defects on 11 houses upon which respondent *215 had performed some work, this likewise bearing on the question of justification; (3) testimony of an expert witness on the issue of damages, specifically with respect to the profit made by said witness on similar though not identical houses; and (4) further cross-examination of a respondent’s witness regarding work orders for repair work on tracts owned by companies not parties to this controversy, this also being assertedly material to the issue of damages; and refused to issue a subpoena duces tecum at appellants’ oral request for all of respondent's business records in order that damages might thus be minimized, it being further claimed that the arbitrators thereby " exceeded their powers” (§ 1288, subd. (d)). On oral argument, it was additionally contended by appellants that the arbitrators exceeded their powers, contrary to subdivision (d), supra, as well as the terms of submission, by awarding to plaintiff in the case of Crescent House and Garden, Inc., and Dayton House and Garden, Inc., both damages for breach of contract and reimbursement for labor and materials furnished.

At the outset, we point out that the record of the arbitration proceedings presented to the trial court, and to this court on appeal, is incomplete, no reporter’s transcript of the first of the two-day hearing having been filed. Too, the partial transcript relied upon by appellants, although certified to by the reporter, does not reflect any certification of the arbitrators. While respondent has asked that the appeal be dismissed for these deficiencies, we shall dispose of the matter on its merits.

In connection with the review of arbitration awards, “it is well settled that both before the superior and appellate courts every intendment of validity must be given the award and that the burden is upon the one claiming error to support his contention.” (Crofoot v. Blair Holdings Corp., 119 Cal.App.2d 156, 185 [260 P.2d 156]). Where, as here, the submission to arbitration was an unlimited one to be expressly conducted under the rules of the American Arbitration Association and in the absence of some limiting clause requiring that they act in conformity with rules of law, arbitrators may “base their decision upon broad principles of justice and equity, and in doing so may expressly or impliedly reject a claim that a party might successfully have asserted in a judicial action. ’ ’ (Sapp v. Barenfeld, 34 Cal.2d 515, 523 [212 P.2d 233].)

*216 Appellants’ first contention of asserted misconduct relates to the arbitrators' refusal to admit evidence of respondent’s failure to repair defective and defectively installed floor tiling in homes constructed by associated companies not parties to these proceedings. Appellants’ theory is that Tobin, as agent for such companies, had knowledge of respondent’s defective work on those units and that the proffered evidence went directly to appellants’ defense of justification for their termination of the contract. This claim is without merit. It appears from the partial record of the proceedings that direct evidence was received from Tobin’s principal witness, H. D. Tobin, bearing upon the reasons for appellants’ letter of rescission, including the asserted defects on work orders relating to other companies. Any additional proffered testimony would have been cumulative. Had this been a judicial proceeding the rejection of such testimony would have been within the court’s inherent discretionary power. (18 Cal.Jur. 2d 563.) Also, appellants’ theory of admissibility, for which no California authority is cited, overlooks the fact that in arbitration proceedings an award may be predicated on “broad principles of justice and equity” (Sapp v. Barenfeld, supra,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kaufman v. Diskeeper CA2/4
California Court of Appeal, 2014
Moncharsh v. Heily & Blase
832 P.2d 899 (California Supreme Court, 1992)
Cobler v. Stanley, Barber, Southard, Brown & Associates
217 Cal. App. 3d 518 (California Court of Appeal, 1990)
City of Fairbanks Municipal Utilities System v. Lees
705 P.2d 457 (Alaska Supreme Court, 1985)
L.R. Foy Construction Co. v. Spearfish School District 40-2
341 N.W.2d 383 (South Dakota Supreme Court, 1983)
Washington Homes, Inc. v. Interstate Land Development Co.
382 A.2d 555 (Court of Appeals of Maryland, 1978)
California State Council of Carpenters v. Superior Court
11 Cal. App. 3d 144 (California Court of Appeal, 1970)
A. A. Baxter Corp. v. Colt Industries, Inc.
10 Cal. App. 3d 144 (California Court of Appeal, 1970)
Kolton v. Nassar
99 N.W.2d 362 (Michigan Supreme Court, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
333 P.2d 194, 166 Cal. App. 2d 211, 1958 Cal. App. LEXIS 1390, Counsel Stack Legal Research, https://law.counselstack.com/opinion/atlas-floor-covering-v-crescent-house-garden-inc-calctapp-1958.