Eldred v. CL Folkman Company

456 P.2d 775, 93 Idaho 131, 1969 Ida. LEXIS 272
CourtIdaho Supreme Court
DecidedJune 30, 1969
Docket10211
StatusPublished
Cited by7 cases

This text of 456 P.2d 775 (Eldred v. CL Folkman Company) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eldred v. CL Folkman Company, 456 P.2d 775, 93 Idaho 131, 1969 Ida. LEXIS 272 (Idaho 1969).

Opinion

McQUADE, Justice.

R. D. Eldred, Jr., (Eldred) is a Nebraska construction contractor specializing in the construction of grain storage and handling facilities. C. L. Folkman Company (Folk-man) is a grain company based in Terreton, Idaho. On May 15, 1963, these two parties entered into a contract for the purposes of constructing certain grain storage and handling facilities on the Folkman property. This dispute involves only one structure called the grain receiving house.

Pertinent provisions of the contract are as follows. By paragraph VII, Folkman agreed to pay a total price of $53,220 according to a schedule of payments. All payments except the last one of $8,320 were in fact made. Paragraph II provided that:

“The contractor agrees that the work under this Contract shall be commenced immediately upon the execution of this agreement, and shall be completed within See Item XI in specification pages, days thereafter, and in the event of its failure to so complete the same so that the same shall not be ready for occupancy by said date, it will remit to the owner the reasonable rental value thereof during all of the time thereafter required to complete the same * *

Paragraph XII provided that “[t]ime is of the essence of this Contract as to both parties hereto.” Paragraph XI of the specifications provided:

“That the receiving house shall be completed within 45 working days after receipt of building materials from Behlen Mfg. Co. Their schedule of production indicates that this structure should clear their plant in 3^4 weeks.”

This contract was drafted by Folkman’s attorneys but the specification made part of the contract for purposes of establishing a completion date was originally composed and submitted to Folkman by Eldred himself.

The evidence then shows that Eldred failed to perform as the contract required. Eldred did not begin work immediately but rather delayed submission of shop drawings to Behlen Mfg. Co. for metal prefabrication purposes for three weeks. This caused an extra five weeks delay in the receipt of materials. Eldred did not arrive at the construction site until August 10, 1963, and all of the materials did not arrive there until about September 1, 1963. Eldred had various labor problems during construction. As a result, the receiving house was not completed until about December 20, 1963.

Because of the delay and certain defects said to exist in the building, Folkman refuesd to make the last payment. Eldred brought suit for the last installment of $8,320. Folkman counterclaimed for damages under the liquidated damages provision of the contract, for wages due Leon Folkman for construction work, for rental for the use of a Folkman tractor, and for damages caused by defects in construction as well as for other asserted consequential damages.

After trial to the court without a jury, the district court entered judgment for Eldred in the amount of the last payment due, of $8,320, and for Folkman by way of set-off in the following amounts.

(1) liquidated damages under the contract of 1 cent per month per bushel of grain rental (testified to as reasonable by “expert” witness at Tr. 84) times 39,000 bushels (the capacity of the receiving house) times 5 months (the amount of delay figured from July 20 to December 20) ................. $1,950.00 (2) wages due Leon Folkman (750 hours times $2.00 per hour .... 1,500.00
$3,450.00

The court found that Folkman got what it bargained for in the way of storage capacity because the contract was a merger of all negotiations and made no mention of specific storage capacity. The court also found that various other damage claims by Folkman were not supported by the evi *133 dence. However, because the court was uncertain whether one of various defects in the building was repairable, it ordered that Eldred follow a procedure to repair the defects within a reasonable time and that Folkman retain an additional $3,000 of the last payment until they were completed. The court also construed paragraph XI of the contract as preventing the award of attorney fees to either party because neither party was completely “successful” in its legal action. Plaintiff Eldred has appealed.

Appellant Eldred makes four assignments of error. First, Eldred argues that the court below erred in allowing respondent Folkman conditionally to retain $3,000 of the last payment due. Since the construction contract was substantially performed, Eldred contends, the court should have simply deducted from Eldred’s recovery the cost of repairing any defects shown to exist in the structure. Eldred, the most knowledgeable witness on these matters, gave rebuttal testimony to the effect that certain bulging in three of the corrugated metal panels of the grain receiving house could be remedied for approximately $250, that a certain space near the roof of the structure could be sealed for approximately $75, and that a defective door could be repaired for about $25. This testimony as to the cost of necessary repairs was not impeached.

The district court found that “[m]ost of the defects can be remedied by the expense of a little expert time and money.” However, the court made no finding as to whether or not certain leakage between the grain bins which had caused some mixing of separate types of grain was repairable. It is also unclear whether the court actually found that this particular defect in fact had caused $3,000 worth of damage to Folkman, since the court’s finding states only that “[Folkman] has claimed as a loss on account of this particular defect the sum of $3,000.” (Emphasis added). In its conclusions of law, the court indicated that it was “at somewhat of a loss to determine just what to do about the defects in this building.” Therefore the court in effect retained jurisdiction of the issue by devising a rather complex procedure for completing the possible repair of the bin leakage along with the other defects.

The general rule on this matter is that a contractor is entitled to recover the contract price of a structure which substantially conforms to the terms of the contract, less the cost of repairing minor defects in the structure. 1 Of course, the difficulty arises in the application of this principle, for the question whether or not the contractor’s performance is “substantial” and the structure’s deficiencies are “minor” is one of degree, turning upon circumstances such as the particular structure involved, its intended purposes, and the nature and relative expense of the repairs, as well as equitable considerations.

As we read the court’s findings of fact, all of the defects in the grain receiving house were found to be quite minor and repairable with the exception the inter-bin leakage, which apparently was related to the certain bulging panels, and as to this latter defect, the court made no finding one way or the other on repairability. It it clear from the record, however, that Folkman received substantially that for which it contracted. Keith L. Folkman, president of C. L. Folkman Grain Company, testified on cross-examination that the first mixing of grain occurred as a result of the shearing off of two bolts, which were subsequently repaired. C. L. Folk-man testified on cross-examination as follows:

“Q.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Schroeder v. Partin
259 P.3d 617 (Idaho Supreme Court, 2011)
Perception Construction Management, Inc. v. Bell
254 P.3d 1246 (Idaho Supreme Court, 2011)
Ujdur v. Thompson
878 P.2d 180 (Idaho Court of Appeals, 1994)
Ervin Construction Co. v. Van Orden
874 P.2d 506 (Idaho Supreme Court, 1993)
Ervin Construction Co. v. Van Orden
874 P.2d 549 (Idaho Court of Appeals, 1992)
State v. Myers
494 P.2d 574 (Idaho Supreme Court, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
456 P.2d 775, 93 Idaho 131, 1969 Ida. LEXIS 272, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eldred-v-cl-folkman-company-idaho-1969.