Ervin Construction Co. v. Van Orden

874 P.2d 549, 125 Idaho 738, 1992 Ida. App. LEXIS 241
CourtIdaho Court of Appeals
DecidedOctober 23, 1992
DocketNo. 19406
StatusPublished
Cited by1 cases

This text of 874 P.2d 549 (Ervin Construction Co. v. Van Orden) is published on Counsel Stack Legal Research, covering Idaho Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ervin Construction Co. v. Van Orden, 874 P.2d 549, 125 Idaho 738, 1992 Ida. App. LEXIS 241 (Idaho Ct. App. 1992).

Opinion

WALTERS, Chief Judge.

The dispute in this case arose from a contract to construct a log home. The central issues on appeal involve the appropriate measure of damages where both parties to the agreement are in breach. As explained below, we vacate the judgment entered by the district court and remand the case for a recalculation of damages.

[740]*740FACTS AND PROCEDURAL BACKGROUND

Ervin Construction Company (Ervin) contracted to construct a log home for Jay and Shelli Van Orden (the Van Ordens) in Aberdeen, Idaho. The terms of the contract provided that the Van Ordens would make monthly progress payments, allowing the Van Ordens to retain ten percent until final completion, and permitted the Van Ordens to terminate the contract at any time by paying Ervin the appropriate percentage of the contract price based on work completed and the value of the materials. The contract expressly guaranteed the home would be built “in a workman-like manner.”

Construction began in November, 1985. The Van Ordens paid the first four monthly billings for the work completed from November through February. Prior to receiving the March billing, the Van Ordens began to notice defects in the home’s construction, in particular, large gaps in log walls and joints. They voiced their concerns to Ervin at a meeting in April, followed by a letter to Ervin enumerating the defects. Ervin mailed a reply several weeks later acknowledging the need for certain repairs. At the end of the month the Van Ordens received the billing for the work completed in March and April. The Van Ordens told Ervin they would make payment on May 15, and Ervin continued with the construction. On May 15 the Van Ordens handed Ervin a check in payment of the March and April bills. Ervin attempted to deposit the check in its account, unaware that the Van Ordens had post-dated the check to August 15. When the check was returned for insufficient funds on May 21, Ervin promptly notified the Van Ordens that, unless they paid the bill and gave assurances of timely payment in the future, it would immediately withdraw from the job site. Although the Van Ordens were financially capable of paying the bill, they refused to do so. Ervin left the site on May 22. The Van Ordens hired another contractor to complete the home and repair some of Ervin’s defective work. However, the improperly constructed deck and roof structure and the gap between the log walls and roof remained uncorrected. The Van Ordens moved into the home in the fall of 1986, where they resided at the time of trial.

Ervin subsequently brought an action to collect the unpaid balance of approximately $16,000 owing for the work it had completed under the contract. The Van Ordens denied liability and filed various counterclaims alleging theories of breach of contract, breach of warranty, negligence and fraud. The parties tried the case before the district court without a jury. At the conclusion of the evidence, which included testimony from both parties, their experts, and an on-site viewing of the home, the court found that some of Ervin’s work was defective and substandard. Accordingly, the court held that Ervin had breached its express and implied duties under the contract, in that certain parts of the home had not been constructed in a workmanlike manner. The court further held, however, that Ervin’s breach was not substantial, and hence, the Van Ordens’ refusal to pay the monthly billings for March and April was unjustified and constituted a breach of the contract.

In crafting the remedy, the court articulated a concern that the Van Ordens’ unjustified refusal to make payments had essentially forced Ervin off the job and unfairly deprived Ervin of the opportunity to repair its own defective work. Believing an equitable “balance” was in order, the court allowed the Van Ordens to recover only one-half of the $10,348 in costs they had incurred to partially repair Ervin’s defective workmanship. However, the court awarded no damages for the construction defects that were not repaired. In a separate award, the court allowed Ervin to recover the unpaid balance of $15,506 for work it completed under the contract before vacating the job site, plus prejudgment interest on that entire amount, accruing from the time of breach. The court further ruled that Ervin was the overall prevailing party and entitled to its costs and a reasonable attorney fee. The Van Ordens appeal.

ISSUES

On appeal, the Van Ordens raise the following issues:

[741]*7411. Whether the trial court erred in finding the Van Ordens in breach of the contract;

2. Whether the court erred in reducing the Van Ordens’ recovery of costs by one-half;

3. Whether the court erred in failing to award damages for defects that had not been corrected;

4. Whether the court erred in allowing pre-judgment interest on Ervin’s damages award;

6. Whether the court erred in finding that the Van Ordens failed to prove their negligence claim; and

7. Whether the court erred in awarding attorney fees to Ervin.

STANDARD OF REVIEW

Our role in reviewing the factual findings is limited. We do not weigh the evidence, nor do we substitute our view of the facts for that of the trial judge. I.R.C.P. 52(a); Alumet v. Bear Lake Grazing Co., 119 Idaho 946, 949, 812 P.2d 253, 256 (1991). We merely determine whether the findings are supported by substantial, albeit conflicting, evidence in the record. If so supported, such a finding cannot be deemed clearly erroneous. Barber v. Honorof 116 Idaho 767, 780 P.2d 89 (1989). However, we freely review the trial court’s application of the law to the facts found.

BREACH OF CONTRACT

The Van Ordens first contend that the court erroneously found them in breach of the contract for refusing to pay Ervin. They argue that Ervin’s defective construction constituted a substantial and material failure of its promised performance,1 and accordingly they were justified in refusing to make payment. We disagree.

The law of contracts recognizes that a material failure of performance, including defective performance as well as an absence of performance, operates as the nonoccurrence of a condition. See RESTATEMENT (SECOND) OF CONTRACTS § 237 (1981). A party’s material failure of performance has the effect of preventing the other’s duty from becoming due, at least temporarily, and of discharging that duty when the condition can no longer occur. RESTATEMENT, supra, § 237 comment a. The following Restatement comment and illustration are consistent with Idaho law2 and pertinent to our resolution of the issue at hand:

d. Substantial Performance. In an important category of disputes over failure of performance, one party asserts the right to payment on the ground that he has completed his performance, while the other party refuses to pay on the ground that there has been an uncured material failure of performance. A typical example is that of the building contractor who claims from the owner payment of the unpaid balance under a construction contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Seubert Excavators, Inc. v. Eucon Corp.
874 P.2d 555 (Idaho Court of Appeals, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
874 P.2d 549, 125 Idaho 738, 1992 Ida. App. LEXIS 241, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ervin-construction-co-v-van-orden-idahoctapp-1992.