Hafer v. Horn

515 P.2d 1013, 95 Idaho 621, 1973 Ida. LEXIS 323
CourtIdaho Supreme Court
DecidedOctober 31, 1973
Docket11052
StatusPublished
Cited by20 cases

This text of 515 P.2d 1013 (Hafer v. Horn) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hafer v. Horn, 515 P.2d 1013, 95 Idaho 621, 1973 Ida. LEXIS 323 (Idaho 1973).

Opinion

McFADDEN, Justice.

On May 9, 1968, W. R. Hafer, the plaintiff-appellant, contracted with Russ and Sally Horn, husband and wife, defendants-respondents, to build them a house in the Trail End Subdivision in Blaine County, Idaho, for $23,500. Under the contract the Horns were credited with certain amounts for items they supplied including the lot, fireplace, brick, well, painting, etc., in the total amount of $5,900, leaving a balance ultimately to be paid under the contract of $18,600. Respondents furnished appellant with sketches to be used as the basis for construction of their house. No architect was employed for preparation of detailed plans.

The record discloses that initially the parties were quite informal in planning the house. As stated by the trial court this “started out to be a friendly ‘build me a home agreement’ along certain general lines, thus saving the costs of an architect and specific plans and specifications.” On July 2; 1968, respondents paid appellant $13,000 on the contract price, leaving a balance of $5,600 payable upon completion of the dwelling. Appellant started construction early in the summer and continued work on the house until about September 4, 1968.

Both parties have different versions of what happened after appellant terminated *622 work on the house. The respondents deny that appellant formally notified them to inspect the house before he left the job; but, appellant claims that the Horns inspected the house, and accepted it. After appellant ceased work on the house and removed his men and equipment from the worksite, the Horns moved in. After the Horns had lived in the place for a few days, they found alleged defects in the construction and workmanship of their home. They complained to appellant about these defects, and in a letter on September 13, 1968, specified some fifteen items allegedly incomplete or unsatisfactory. They advised appellant that final payment for the contract balance would be withheld until he corrected the deficiencies.

Appellant executed and verified a claim of materialman’s lien on the premises under date of September 11, 1968, which was recorded September 20, 1968. In his claim of lien, appellant asserted that there was $4,991.85 due him. Appellant timely filed a complaint to foreclose this lien, seeking the balance due, plus attorney fees. The Horns answered the complaint, denying there was any money due and counterclaimed for breach of implied warranty of fitness in the construction of the home, seeking damages in the amount of $6,875.00.

The case was tried to the court sitting without a jury on the issues presented by the pleadings. The trial court entered its findings of fact, conclusions of law and judgment in favor of appellant in the amount of $3,024.62. In the judgment the trial court ordered foreclosure of the materialman’s lien. However, the trial court refused to allow the appellant any attorney’s fee.

In its findings of fact the trial court found the parties had entered into a contract for construction of a dwelling for the respondents for which the appellant was to be paid $23,950. ' The trial court further found that respondents were entitled to certain specified credits for items they furnished in the amount of $5,950; that they had paid $13,000 to appellant on the contract ; that the parties were obligated to adjust as between themselves concerning floor coverings; that appellant was entitled to certain allowances for extras in the amount of $443.75, but not entitled to other extras he claimed; that the respondents were entitled to offsets arising from either materials and labor they had to furnish which appellant should have furnished under the contract terms, and that respondents were entitled also to offsets for defects in the performance of the contract by the appellant. The trial court then calculated the respective credits and debits and arrived at a balance still due the appellant of $3,024.62. Following entry of the judgment appellant perfected this appeal.

Three issues are presented by this appeal. The first issue is whether the trial court erred in allowing respondents to measure their damages in terms of repair costs. Pertinent to this damage issue is whether the trial court erred in applying a warranty of fitness by allowing a setoff for items neither warranted nor properly installed. The next issue is whether the trial court erred in computing the judgment. The third issue is whether the trial court erred in not allowing an attorney’s fee upon entry of judgment of foreclosure in this action.

Concerning the district court’s measure of damages and allowance of offsets for breach of implied warranty of fitness against the contract price, it is our conclusion that the appellant misinterpreted what the trial court did in entering its findings of fact, conclusions of law and judgment.

In resolution of the issues presented by the pleadings, the trial court attempted to determine how much the. respondents owed to the appellant by reason of non-payment of the full amount agreed upon in the written contract. The trial court then simply attempted to determine which of the numerous deficiencies claimed by respondent were in fact not in conformity with the agreement of the parties. In the contract appellant agreed “to furnish all the materials and labor for a new residence * * * according to the plans and specifications hereto attached, in a good substan *623 tial and ivorkmanlike manner. * * * And the Contractor upon notice shall remove and replace all defective and unfit material and work whether complete or not, at his own expense.” (Emphasis added.)

The trial court found a number of defects or deficiencies in the residence, and determined the cost of correction. Its findings in this regard were fully sustained by the record. Appellant urges, however, that the trial court erred in measuring the allowances to respondents for the defects or deficiencies on the basis of repair costs. He asserts that the proper measure of damages to be applied in a case of this nature is the difference in value between the structure as it was actually constructed and as it ought to have been constructed; he contends that there was no proof submitted by respondents as to the market value of the residence, and hence, no basis for allowances made by the trial court.

Although appellant in his assignments of error asserts the trial court erred in its “application of warranty of fitness,” the trial court did not deal with such warranty, but determined deficiencies in appellant’s performance under the express contract. In such a case the measure of damages is as discussed in Restatement of Contracts, § 346:

“§ 346. Damages for Breach of a Construction Contract.
“(1) For a breach by one who has contracted to construct a specified product, the other party can get judgment for compensatory damages for all unavoidable harm that the builder had reason to foresee when the contract was made, less such part of the contract price as has not been paid and is not still payable, determined as follows:
(a) For defective or unfinished construction he can get judgment for either

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Petrus Family Trust Dated May 1, 1991 v. Kirk
415 P.3d 358 (Idaho Supreme Court, 2018)
Ervin Construction Co. v. Van Orden
874 P.2d 506 (Idaho Supreme Court, 1993)
Ervin Construction Co. v. Van Orden
874 P.2d 549 (Idaho Court of Appeals, 1992)
Miller v. Miller
745 P.2d 294 (Idaho Supreme Court, 1987)
Gilbert v. City of Caldwell
732 P.2d 355 (Idaho Court of Appeals, 1987)
W. F. Construction Co. v. Kalik
652 P.2d 661 (Idaho Court of Appeals, 1982)
Viehweg v. Thompson
647 P.2d 311 (Idaho Court of Appeals, 1982)
Pope v. Intermountain Gas Co.
646 P.2d 988 (Idaho Supreme Court, 1982)
Holloway v. University of Montana
582 P.2d 1265 (Montana Supreme Court, 1978)
Hunt Bros. Construction, Inc. v. Wolcott
580 P.2d 418 (Idaho Supreme Court, 1978)
Raimer v. Stout
14 V.I. 568 (Supreme Court of The Virgin Islands, 1978)
Treasure Valley Foods, Inc. v. J-M Poultry Packing Co.
564 P.2d 978 (Idaho Supreme Court, 1977)
Pollard v. Land West, Inc.
526 P.2d 1110 (Idaho Supreme Court, 1974)
Standall v. Teater
525 P.2d 347 (Idaho Supreme Court, 1974)
Ellis v. Jones
524 P.2d 1062 (Idaho Supreme Court, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
515 P.2d 1013, 95 Idaho 621, 1973 Ida. LEXIS 323, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hafer-v-horn-idaho-1973.