Nelson v. Hazel

406 P.2d 138, 89 Idaho 480, 1965 Ida. LEXIS 390
CourtIdaho Supreme Court
DecidedSeptember 30, 1965
Docket9539
StatusPublished
Cited by21 cases

This text of 406 P.2d 138 (Nelson v. Hazel) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nelson v. Hazel, 406 P.2d 138, 89 Idaho 480, 1965 Ida. LEXIS 390 (Idaho 1965).

Opinion

SMITH, Justice.

• Respondent instituted this action to foreclose laborer’s and materialman’s lien on appellants’ real property. In his complaint respondent alleges that he performed labor and furnished materials of the reasonable value of $5,090.86 in the remodeling, alteration and construction of appellants’ dwelling house; that appellants paid $1,997.51 on the account, and refused to pay the balance of $3,093.35. Respondent also seeks attorneys’ fees and costs, and foreclosure of the lien on, and sale of, the property.

Appellants in their answer admit that pursuant to an oral understanding respondent furnished some labor and materials used in and upon the dwelling, hut allege that he failed to perform the work in good and workmanlike manner or to furnish proper materials. They admit having paid respondent $1,997.51, but allege that they owe him nothing more.

Appellants then cross-claimed for breach of the oral agreement, alleging that respondent was to perform the agreed work for a sum not to exceed $3500; that respondent performed certain work in a negligent and unworkmanlike manner, left the premises in an unfinished condition and breached his contract; that in numerous instances, specifically alleged, respondent performed the work in a negligent and unworkmanlike manner. Appellants pray for $5,000 general damages to their premises and for $2300 as *483 the reasonable cost of labor and material to tear out and repair respondent’s improper and unworkmanlike work.

The trial court, sitting without a jury, after a trial had, found that appellants orally hired respondent to remodel appellants’ dwelling on a time and material basis, although respondent submitted an estimate on the original work contemplated; that the contract implied that the work would be performed in good and workmanlike manner, which it was not, setting forth instances of defective construction; that although appellants claimed that respondent was deficient in placing a footing for a fireplace, to be constructed by a third party, appellants had not furnished to respondent any specifications for the footing; that appellants had not submitted adequate proof as to their alleged damage; that respondent had substantially performed the work contemplated by the oral agreement and was not entitled to the full amount of $3,093.35 alleged as owing on the account. The court then found that “due to the defects in the work performed * * * the plaintiff [respondent] is not entitled to an award of attorney’s fees,” also denied appellants any relief on their counterclaim. The court entered judgment accordingly in favor of respondent; also adjudged that the lien be foreclosed, and that the property be sold in satisfaction of the judgment. Appellants perfected an appeal from the judgment.

Appellants specified error of the trial court in finding:

That appellants hired respondent on a time and material basis rather than on a contract basis of $3500 ;
That respondent had substantially completed all the work contemplated by the original contract;
That appellants failed to sustain their burden of proof as to the cost of repair;
Also in granting respondent full recovery, and in failing to grant appellants damage on their counterclaim, while finding that respondent had breached the contract by failing to build the structure in good and workmanlike manner.

Respondent submitted bills for labor and materials amounting to $5,090.86 upon which appellants paid $1,997.51, leaving a balance of $3,093.35. Additionally, appellants paid direct to the subcontractors, for plumbing and electrical work, the sum of $1117.98.

The new addition to the rear of appellants’ 2-story house was agreed to be an oblong 2-story, 9 feet by 32 feet structure, with a new slanting roof over the entire rear portion, and a connecting slanted roof added over the remaining portion to join the roof of the older portion of the dwelling. A fireplace was not to be con *484 structed by respondent, but he did construct a “footing” for the fireplace and chimney.

The interior of the second story of the addition was not to be completed, nor was the “finishing” or any of the painting; the material from the older structure was to be used as much as possible so as to reduce the expense of remodeling. Respondent and various of his employees worked on the addition during July and August and part of September, 1961. After September 15, 1961, respondent had nothing further to do with the added structure, and in fact never returned to view it.

Appellants’ specifications of error question the sufficiency of the evidence to support certain findings and the judgment of the trial court, thus necessitating a review of the evidence.

Respondent testified that under the oral contract he was to build the addition on the basis of cost plus 5%; that the parties placed no limit on the expense of the remodeling and that he attempted to keep the costs down. After the work had progressed to some extent he stated that he told appellants that the work would cost around $5,000.00 but that he did not at any time tell them that the work would not cost in excess of $3500.00.

He described the sagging condition of the floors in the older portion of the house, and the fact that the roof sagged some in the area where the new portion of the roof was joined to the old roof, but that the slight sag was not particularly noticeable; also that any unevenness in the floor could have been remedied by sanding operations.

He also stated that there were some changes from the original plan of remodeling, such as changing positions of windows, a doorway and a door; certain built-in cabinet work, and other minor details; also a footing for the fireplace was added.

He was specific in his testimony that all the work was performed in a good and workmanlike or carpenterlike manner; that the new structure, including the cabinet work, was level, straight and plumb in all particulars and that good results were obtained in joining it with the older structure.

John Hazel, one of the appellants, testified that about June 27, 1961, he and respondent agreed that the cost of the addition would not exceed $3500. He stated that where the roof of the new structure joined the old portion of the roof, the construction did not match, and that there was a distinct sag in the middle portion of the roof; that the cement block foundation under the new addition was not set straight in that it “jogged.” The floor in the new portion of the kitchen was not level, in that it sloped downward to the outside wall. The kitchen ceiling had an appearance of being “kind of corrugated,” and wasn’t level. The “built-ins” or cabinets installed *485 in the kitchen were not level, discernible with the naked eye; the new floors upstairs all sloped toward the exterior of the new addition. The upstairs rooms were not square, and such defects also could be discerned with the naked eye.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Flynn Builders, L.C. v. Matthew P. Lande and Chris Lande
814 N.W.2d 542 (Supreme Court of Iowa, 2012)
Perception Construction Management, Inc. v. Bell
254 P.3d 1246 (Idaho Supreme Court, 2011)
Martel v. Bulotti
65 P.3d 192 (Idaho Supreme Court, 2003)
Ervin Construction Co. v. Van Orden
874 P.2d 506 (Idaho Supreme Court, 1993)
Afton Energy, Inc. v. Idaho Power Co.
834 P.2d 850 (Idaho Supreme Court, 1992)
Fuller v. Wolters
807 P.2d 633 (Idaho Supreme Court, 1991)
Comstock Investment Corp. v. Kaniksu Resort
793 P.2d 222 (Idaho Court of Appeals, 1990)
Gilbert v. City of Caldwell
732 P.2d 355 (Idaho Court of Appeals, 1987)
Owen v. Newberg Cedar
609 P.2d 144 (Idaho Supreme Court, 1980)
Raimer v. Stout
14 V.I. 568 (Supreme Court of The Virgin Islands, 1978)
Lewis v. Anchorage Asphalt Paving Co.
535 P.2d 1188 (Alaska Supreme Court, 1975)
Hafer v. Horn
515 P.2d 1013 (Idaho Supreme Court, 1973)
Eldred v. CL Folkman Company
456 P.2d 775 (Idaho Supreme Court, 1969)
Miller v. Bob Dean Steel Buildings, Inc.
218 So. 2d 459 (District Court of Appeal of Florida, 1968)
Nelson v. Hazel
433 P.2d 120 (Idaho Supreme Court, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
406 P.2d 138, 89 Idaho 480, 1965 Ida. LEXIS 390, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nelson-v-hazel-idaho-1965.